Management has determined the need to release the product 20 days earlier than planned. What tasks need to be expedited?
Which of the following types of delay will NOT result in a time extension and additional compensation for a contractor?
Total float is defined as the amount of time an activity can be delayed without impacting
Which of the following options is NOT a feasible method to reduce the overall completion time of the toll road program?
Which of the following documents is most likely to be of the LEAST value to a planner/scheduler when planning a contractor's baseline critical path schedule for the construction of a large high-clearance bridge located very near an airport? The contractor has been awarded the contract.
In its simplest form, what is the main drawback of critical path method scheduling?
Which of the following phases does NOT describe the commonly accepted construction life cycle?
If a new hammock activity covering activities 6001 through 6003 is developed, what are governing predecessor and successor activities?
Which of the following risks CANNOT be estimated by BILCO with only a resource-loaded schedule?
Using a 1.75 cubic yard [1.34 cubic meter] bucket, how many lifts does it take to pour each 2.000-cubic foot [56.64 cubic meter] column?
Which of the following is NOT required when performing weekly or monthly schedule updates?
Using the "normal" schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?
Who will receive the most benefit from a master schedule of the Spring Highway project?
For activity 11001. why would the crashed direct cost be greater than the direct cost of the normal schedule?
In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):
Using the normal schedule, what is the early finish date and total float of Activity 10002?
The congested site only has room for 3 cranes to operate concurrently. Only 1.75 cubic yard ICY] or1.34 cubic meter [CM] concrete buckets are available. Each crane can perform up to 35 lifts per day. Assuming a total of 30 lifts per crane pet day. what is the maximum volume of concrete that could be placed using 3 small tower cranes over a 5-day period?
If a cost estimate assumes that 240 hours will be expended on a given activity, and the projected crew size expected to perform that activity is 5 personnel working and 8-hour workday, what is the calculated duration for the activity?
Using the "normal" schedule, given Activity 3001 and the relationship with Activity 4001, what is indicated?
Theoretically construct a summary activity for activities 6001 through 6003. Identify the governing predecessor and successor activities for the hammock: