During Sprint Planning the Product Owner and the Developers are unable to reach an
understanding about the highest order Product Backlog items. Because of this, the Developers
are unable to determine how many Product Backlog items they can forecast for the upcoming
Sprint However, the Product Owner and the Developers are able to agree on a Sprint Goal.
Which of the following actions should the Scrum Master support?
(choose the best two answers)
Which two ways of creating Scrum Teams are consistent with Scrum's values?
(choose the best two answers)
What is the tactic a Scrum Master should use to divide a group of 100 people into multiple Development Teams?
Which of the following are topics for the Developers to discuss at the Daily scrum as they inspect their progress toward the Sprint Goal?
(choose the best three answers)
Which two of the following are appropriate topics for discussion during a Sprint Retrospective? (Choose two.)
How much of the Sprint Backlog must be defined during the Sprint Planning event?
A properly functioning Scrum Team will have at least one Release Sprint and may well have several.
A Scrum Master is introducing Scrum to a new Development Team. The Development Team gas decided that a Sprint Retrospective is unnecessary. What action should the Scrum Master take?
If burndown charts are used to visualize progress, what does a trend line through a release burndown chart indicate?
When is it most appropriate for a Scrum Team to change the definition of “Done”?
What is the accountability of the Product Owner during Sprint 0? (Choose the best answer.)
A Scrum Master is working with a Development Team that has members in different physical locations. The Development Team meets in a variety of meeting rooms and has much to do logistically (for example, set up conference calls) before the Daily Scrum. What action should the Scrum Master take?
When multiple teams work together on the same product, each team should maintain a separate Product Backlog.
You have just been hired by a company new to Scrum. Your management has assigned you to
be the Scrum Master of six new Scrum Teams. These teams will build one product Select two
conditions you should strive tor in this scenario.
(choose the best two answers)
Multiple Scrum Teams working on the same product or system all select work from the same Product Backlog.
How should Product Backlog items be chosen when multiple Scrum Teams work from the same Product Backlog?
True or False Developers do not meet with stakeholders: only the Product Owner meets with stakeholders
The CEO asks the Development Team to add a “very important” item to a Sprint that is in progress. What should the Development Team do?
When multiple Scrum Teams are working on a single product, what best describes the Definition of Done?
(choose the best answer)
During the Sprint. Me Scrum Master's role is to do which two of the following: (choose the best two answers)
As the Sprint Planning meeting progresses, the Development Team sees that the workload is greater than they can handle. Which two are valid actions? (Choose two.)
The CEO asks the Developers to add a "very important" item to a Sprint that is in progress.
What should the Developers do?
(choose the best answer)
user documentation is part of your Definition of Done. However, there are not enough technical
writers for all teams. Your Scrum Team does not have a technical writer. What should the
Scrum Team do?
(choose the best answer)
Which two things are appropriate for a Scrum Master to do if the Development Team doesn’t have the engineering tools and infrastructure to completely finish each selected Product Backlog item? (Choose two.)
One of the Scrum events is the Daily Scrum. What are two intended outcomes of the Daily Scrum?
(choose the best two answers)
How much work must a Development Team do to a Product Backlog item it selects for a Sprint?
Who should make sure everyone on the scrum Team does their tasks for the sprint? (choose the best answer)
How much work Is required of the Developers to complete a Product Backlog Item selected during the Sprint Planning?
(choose the best answer)
A Scrum Team has been working on a product for nine Sprints. A new Product Owner comes in, understanding he is accountable for the Product Backlog. However, he is unsure about his responsibilities. Which two activities are part of the Product Owner role according to Scrum? (Choose two.)
How should a Scrum Team deal with non-functional requirements?
(choose the best answer)
Which two things should the Development Team do during the first Sprint? (Choose two.)
Which two things should the Development Team do during the first Sprint? (Choose two.)
Who does the work to make sure Product Backlog items conform to the Definition of Done?
(choose the Best answer)
The CEO asks the Developers to add a "very important" item to a Sprint that is in progress.
What should the Developers do?
(choose the best answer)
Who is accountable for tracking the remaining work toward the Sprint Goal? (Choose the best answer.)
True or False A scrum Master fulfills the same role as a traditional Project Manager
Which output from Sprint Planning provides the Development Team with a target and overarching direction for the Sprint?
The Definition of Done serves which three purposes?
(choose the best three answers)
An organization has decided to adopt Scrum, but management wants to change the terminology to fit with terminology already used. What will likely happen if this is done? (Choose the best answer.)
You are the Scrum Master of a new, to be developed product. Development is going to require 45 people. What is a good first question for you to suggest the group thinks about when forming into teams?
Choose two responsibilities of a self-organizing Development Team. (Choose two.)
In accordance with Scrum theory, how should a group of 100 people be divided into multiple Development Teams?
For the purpose of transparency, when does Scrum say a new increment of working software must be available?
At the end of a Sprint Product Backlog item worked on during the Sprint does not meet the definition of “Done”. What two things should happen with the undone Product Backlog item? (Choose two.)
What happens if the Development Team cannot complete its work by the end of the Sprint?
What techniques could the Scrum Master use when the Scrum Team gets caught in an internal disagreement
about which agile practices to apply? (Choose the best two answers.)
One of the Scrum events is the Daily Scrum. What are two intended outcomes of the Daily Scrum? (Choose two.)
At the seventh Sprint Review, the stakeholders are disappointed and angry. They have determined that the product or system being built will not meet their needs and will cost more than they are willing to spend. What factors likely led to this? (Choose two.)
How do you know that a Scrum Team is cross-functional? (Choose the best answer.)