Easter Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: netbudy65

PSM-I Professional Scrum Master I Questions and Answers

Questions 4

During Sprint Planning the Product Owner and the Developers are unable to reach an

understanding about the highest order Product Backlog items. Because of this, the Developers

are unable to determine how many Product Backlog items they can forecast for the upcoming

Sprint However, the Product Owner and the Developers are able to agree on a Sprint Goal.

Which of the following actions should the Scrum Master support?

(choose the best two answers)

Options:

A.

Cancel the Sprint Send the entire team to an advanced Scrum training and then

start a new Sprint

B.

During the next Sprint Retrospective discuss why this happened and what

changes will make it less likely to recur.

C.

Continue the Sprint Planning event past its timebox until an adequate number ot

Product Backlog items are well enough understood for the Developers to make a

complete forecast Then start the Sprint

D.

Forecast the Product Backlog items that are most likely to meet the Sprint Goal

and create the Sprint Backlog. Conclude Sprint Planning and start the

development work. Continue to analyze, decompose, and create additional

functionality during the Sprint

E.

Ask everyone to take as much time as needed to analyze the Product Backlog

first, and then reconvene another Sprint Planning meeting.

Buy Now
Questions 5

How often should Scrum Team membership change?

Options:

A.

As needed, while taking into account a short term reduction in productivity.

B.

Never, because it reduces productivity.

C.

As needed, with no special allowance for changes in productivity.

D.

Every Sprint to promote shared learning.

Buy Now
Questions 6

Which two ways of creating Scrum Teams are consistent with Scrum's values?

(choose the best two answers)

Options:

A.

Bring all the people together and let them organize into Scrum Teams

B.

Managers personally re-assign current subordinates to new teams.

C.

Existing teams propose how they would like to go about organizing into the new

structure.

D.

Managers collaborate to assign individuals to specific teams.

E.

The Chief Product Owner determines the new team structures and assignments.

Buy Now
Questions 7

When does a Sprint conclude?

(choose the best answer)

Options:

A.

When the Product Owner decides enough has been delivered to meet the Sprint

Goal.

B.

When the Sprint Retrospective is complete.

C.

When all the tasks are completed by the Developers.

D.

When all Product Backlog items meet their Definition of Done.

Buy Now
Questions 8

What is the tactic a Scrum Master should use to divide a group of 100 people into multiple Development Teams?

Options:

A.

Create teams based on their skills across multiple layers (such as database, UI, etc.)

B.

Ask the Product Owner to assign the people to teams.

C.

Ask the developers to divide themselves into teams.

Buy Now
Questions 9

Which of the following are topics for the Developers to discuss at the Daily scrum as they inspect their progress toward the Sprint Goal?

(choose the best three answers)

Options:

A.

what have we learned since yesterday, and now should we modify our plan to increase our ability to meet the Sprint Goal?

B.

Are mere any impediments Clocking progress toward the sprint Goal?

C.

What will I be working on tomorrow?

D.

Are mere any decisions that need to be made to maintain progress toward the sprint Goal?

E.

Why were you late?

F.

How many hours Old I spend on the project yesterday

G.

win todays work negatively impact our ability to meet the sprint Goal for the Split following this one?

Buy Now
Questions 10

Which two of the following are appropriate topics for discussion during a Sprint Retrospective? (Choose two.)

Options:

A.

Identifying high priority process improvements for the next Sprint.

B.

The order of items in the Product Backlog.

C.

How the team collaborates.

D.

Documenting acceptance criteria for items in the next Sprint.

Buy Now
Questions 11

How much of the Sprint Backlog must be defined during the Sprint Planning event?

Options:

A.

Just enough tasks for the Scrum Master to be confident in the Development Team’s understanding of the Sprint.

B.

The entire Sprint Backlog must be identified and estimated by the end of the Sprint Planning meeting.

C.

Enough so the Development Team can create its best forecast of what is can do, and to start the first several days of the Sprint.

D.

Just enough to understand design and architectural implications.

Buy Now
Questions 12

Who creates the definition of “Done”?

Options:

A.

The Scrum Master as he/she is responsible for the Development Team’s productivity.

B.

The Scrum Team, in a collaborative effort where the result is the common denominator of all members’ definition.

C.

The Product Owner as he/she is responsible for the product’s success.

D.

The development organization (or Development Team if none is available from the development organization).

Buy Now
Questions 13

A Sprint Retrospective should be held:

Options:

A.

At the end of each Sprint.

B.

At the beginning of each Sprint.

C.

Only when the Scrum Team determines it needs one.

D.

At the end of the last Sprint in a project or a release.

Buy Now
Questions 14

A properly functioning Scrum Team will have at least one Release Sprint and may well have several.

Options:

A.

True

B.

False

Buy Now
Questions 15

A Scrum Master is introducing Scrum to a new Development Team. The Development Team gas decided that a Sprint Retrospective is unnecessary. What action should the Scrum Master take?

Options:

A.

Call a meeting between the Development Team and senior management.

B.

Comply with the decision of the self-organizing team.

C.

Consult with the Product Owner to see how he/she feels about the situation.

D.

Begin facilitating productive and useful Sprint Retrospectives.

Buy Now
Questions 16

If burndown charts are used to visualize progress, what does a trend line through a release burndown chart indicate?

Options:

A.

The evolution of the cost spent on the project.

B.

When all work will be completed to the Scrum Team can be released for other work.

C.

When the work remaining will likely be completed if nothing changes on the Product Backlog or the Development Team.

D.

When the project will be over if the Product Owner removes work that is equal in effort to any new work that is added.

Buy Now
Questions 17

When is it most appropriate for a Scrum Team to change the definition of “Done”?

Options:

A.

During Spring Planning.

B.

Prior to starting a new Sprint.

C.

During the Sprint Retrospective.

D.

Prior to starting a new project.

Buy Now
Questions 18

What is the accountability of the Product Owner during Sprint 0? (Choose the best answer.)

Options:

A.

There is no such thing as Sprint 0.

B.

Gathering, eliciting, and analyzing the requirements that will be inserted into the Product Backlog.

C.

Make the complete project plan to commit date, budget, and scope to the stakeholders.

D.

Determine the composition of the Development Teams so they have the capacity to deliver the completed

forecast.

E.

Make sure enough Product Backlog items are refined to fill the first 3 Sprints.

Buy Now
Questions 19

A Scrum Master is working with a Development Team that has members in different physical locations. The Development Team meets in a variety of meeting rooms and has much to do logistically (for example, set up conference calls) before the Daily Scrum. What action should the Scrum Master take?

Options:

A.

Allow the Development Team to self-manage and determine for itself what to do.

B.

Set up the meeting and tell the Development Team that is how it will be done.

C.

Ask the Development Team members to alternate who is responsible for meeting setup.

D.

Inform management and ask them to solve it.

Buy Now
Questions 20

When multiple teams work together on the same product, each team should maintain a separate Product Backlog.

Options:

A.

True

B.

False

Buy Now
Questions 21

You have just been hired by a company new to Scrum. Your management has assigned you to

be the Scrum Master of six new Scrum Teams. These teams will build one product Select two

conditions you should strive tor in this scenario.

(choose the best two answers)

Options:

A.

There should be six Product Owners, one tor each Scrum Team.

B.

There should be six Product Owners, reporting to a Chief Product Owner.

C.

The product has one Product Backlog.

D.

Each Scrum Team should have a separate Product Backlog.

E.

There should be only one Product Owner.

Buy Now
Questions 22

What it the main reason for the Scrum Master to be at the Daily Scrum?

Options:

A.

To gather status and progress information to report to management.

B.

To write down any changes to the Sprint Backlog, including adding new items, and tracking progress on the burn-down.

C.

He or she does not have to be there; he or she only has to ensure the Development Team has a Daily Scrum.

D.

To make sure every team member answers the three questions.

Buy Now
Questions 23

Every Scrum Team should nave:

(choose the best answer)

Options:

A.

One Lead Developer and no more than 8 other members.

B.

The competencies and skills needed to deliver an Increment in a Sprint

C.

At least one representative from each major department, such as, Quality Assurance, Development, and Marketing.

Buy Now
Questions 24

Multiple Scrum Teams working on the same product or system all select work from the same Product Backlog.

Options:

A.

True

B.

False

Buy Now
Questions 25

When does the second Sprint start?

Options:

A.

Once the architectural changes for the second Sprint have been approved by the senior architect.

B.

After the Product Backlog for the second Sprint has been selected.

C.

Immediately after the first Sprint.

D.

After the customer completes acceptance testing of the first Sprint.

Buy Now
Questions 26

How should Product Backlog items be chosen when multiple Scrum Teams work from the same Product Backlog?

Options:

A.

The Scrum Team with the highest velocity pulls Product Backlog items first.

B.

The Development Teams pull in work in agreement with the Product Owner.

C.

The Product Owner should provide each team with its own Product Backlog.

D.

Each Scrum Team takes an equal numbers of items.

E.

The Product Owner decides.

Buy Now
Questions 27

True or False Developers do not meet with stakeholders: only the Product Owner meets with stakeholders

Options:

A.

True

B.

False

Buy Now
Questions 28

Why is the Daily Scrum held at the same time and same place?

Options:

A.

The consistency reduces complexity.

B.

The place can be named.

C.

The Product Owner demands it.

D.

Rooms are hard to book and this lets it be booked in advance.

Buy Now
Questions 29

The CEO asks the Development Team to add a “very important” item to a Sprint that is in progress. What should the Development Team do?

Options:

A.

Add the item to the current Sprint and drop an item of equal size.

B.

Add the item to the current Sprint without any adjustments.

C.

Inform the Product Owner so he/she can work with the CEO.

D.

Add the item to the next Sprint.

Buy Now
Questions 30

When multiple Scrum Teams are working on a single product, what best describes the Definition of Done?

(choose the best answer)

Options:

A.

The Scrum Masters from each Scrum Team define a common Definition of Done.

B.

Each Scrum Team defines and uses its own. The differences are discussed and reconciled during a hardening Sprint.

C.

When multiple Scrum Teams are working together on a product, they must mutually

define and comply with the same Definition of Done.

D.

Each Scrum Team uses its own, but must make their definition clear to all other teams so the differences are known.

Buy Now
Questions 31

During the Sprint. Me Scrum Master's role is to do which two of the following: (choose the best two answers)

Options:

A.

Facilitate inspection and adaptation opportunities as requested or needed

B.

Coaching the team members in self-management

C.

Ensure the Product Owner attends all scrum events.

D.

Escalate team conflicts to functional line managers

E.

Monitor the progress of the Developers

F.

Assign tasks with the Scrum team.

Buy Now
Questions 32

As the Sprint Planning meeting progresses, the Development Team sees that the workload is greater than they can handle. Which two are valid actions? (Choose two.)

Options:

A.

Recruit additional Development Team members before the work can begin.

B.

The Development Team ensures that the Product Owner is aware, starts the Sprint, and monitors progress.

C.

Cancel the Sprint.

D.

Remove or change selected Product Backlog items.

E.

The Development Team works overtime during this Sprint.

Buy Now
Questions 33

Which does a self-organizing Development Team choose?

Options:

A.

Sprint length.

B.

How to best accomplish its work.

C.

Stakeholders for the Sprint Review.

D.

When to release, based on its progress.

E.

Product Backlog ordering.

Buy Now
Questions 34

The Product Owner must release each Increment to production.

Options:

A.

When it makes sense.

B.

To make sure the Development Team is done every Sprint.

C.

Whenever the product is free of defects.

D.

Without exception.

Buy Now
Questions 35

The CEO asks the Developers to add a "very important" item to a Sprint that is in progress.

What should the Developers do?

(choose the best answer)

Options:

A.

Add the item to the Sprint Backlog for the next Sprint.

B.

Add the item to the top of the Product Backlog.

C.

Add the item to the current Sprint Backlog and begin work immediately since the

request came from the CEO.

D.

Add the item to the current Sprint and drop an item of equal size.

E.

Discuss the item with the other members of the Scrum Team so the team can

decide what to do.

Buy Now
Questions 36

user documentation is part of your Definition of Done. However, there are not enough technical

writers for all teams. Your Scrum Team does not have a technical writer. What should the

Scrum Team do?

(choose the best answer)

Options:

A.

The Developers on the Scrum Team should write the user documentation

B.

Wait until you have a technical writer on your Scrum Team to take care of this.

C.

Form a separate team of technical writers that will work on an on-demand basis tor

the various Product Owners. Work order will be first in, first out.

D.

Let the user documentation remain undone and accumulate until after the last

development Sprint. It will then be done by any available technical writers.

Buy Now
Questions 37

Which two things are appropriate for a Scrum Master to do if the Development Team doesn’t have the engineering tools and infrastructure to completely finish each selected Product Backlog item? (Choose two.)

Options:

A.

Coach the Development Team to improve its skills, tools, and infrastructure over time and adjust the Definition of “Done” accordingly.

B.

Encourage the Product Owner to accept partially “Done” increments until the situation improves.

C.

Refocus the current Sprint on establishing the Development Team’s infrastructure instead of delivering an increment.

D.

Declare the Development Team not ready for Scrum.

E.

Have the Development Team establish a Definition of “Done” that is actually possible to achieve given current circumstances.

Buy Now
Questions 38

One of the Scrum events is the Daily Scrum. What are two intended outcomes of the Daily Scrum?

(choose the best two answers)

Options:

A.

Identification of impediments that may prevent the Developers from achieving the Sprint Goal.

B.

An update of completed tasks and of the remaining work so the Scrum Master

can plan the next day.

C.

An updated Scrum board to make Sprint progress transparent for the

stakeholders.

D.

A shared understanding of the most important work to be undertaken next to

achieve the best possible progress toward the Sprint goal.

E.

A status report for the upper management indicating what each individual has done, will be doing, and what is impeding him/her.

Buy Now
Questions 39

How much work must a Development Team do to a Product Backlog item it selects for a Sprint?

Options:

A.

A proportional amount of time on analysis, design, programming, testing, and documentation.

B.

As much as it can fit into the Sprint. Any remaining work will be transferred to a subsequent Sprint.

C.

All development work and at least some testing.

D.

As much as it has told the Product Owner will be done for every Product Backlog item it selects in conformance with the definition of “Done”.

Buy Now
Questions 40

Which of the following are roles on a Scrum Team? (Choose all that apply.)

Options:

A.

Users

B.

Scrum Master

C.

Product Owner

D.

Development Team

E.

Customers

Buy Now
Questions 41

Who should make sure everyone on the scrum Team does their tasks for the sprint? (choose the best answer)

Options:

A.

The Project Manager

B.

The Product Owner

C.

The Scrum Master

D.

The Scrum Team

E.

All of the above

Buy Now
Questions 42

Scrum has a role called “Project Manager”.

Options:

A.

True

B.

False

Buy Now
Questions 43

What are three benefits of self-organization? (Choose three.)

Options:

A.

Increased creativity.

B.

Increased rule compliance.

C.

Increased accuracy of estimates.

D.

Increased self-accountability

E.

Increased commitment.

Buy Now
Questions 44

How much work Is required of the Developers to complete a Product Backlog Item selected during the Sprint Planning?

(choose the best answer)

Options:

A.

All development work and at least some testing.

B.

as much as is required to meet the Scrum Team's Definition of Done.

C.

A proportional amount of time on analysis, design development and testing

D.

As much as they can fit into the Sprint, with remaining work deferred to the next Sprint

Buy Now
Questions 45

A Scrum Team has been working on a product for nine Sprints. A new Product Owner comes in, understanding he is accountable for the Product Backlog. However, he is unsure about his responsibilities. Which two activities are part of the Product Owner role according to Scrum? (Choose two.)

Options:

A.

Ensuring that the most valuable functionality is produced first, at all times.

B.

Interacting with stakeholders.

C.

Providing the Development Team with detailed specifications.

D.

Describing features as Use Cases.

E.

Creating detailed functional test cases.

Buy Now
Questions 46

Who creates the Definition of Done?

(choose the best answer)

Options:

A.

The Scrum Master

B.

The Product Owner

C.

The scrum Team

D.

The Developers

Buy Now
Questions 47

Every Scrum team must have a Product Owner and Scrum Master.

Options:

A.

True. Outcomes affected by their participation and availability.

B.

False. A Product Owner can be replaced by a business analyst in the Development Team.

C.

False. A Scrum Master is only required when asked for by the Development Team.

D.

True. Each must be 100% dedicated to the Scrum Team.

Buy Now
Questions 48

How should a Scrum Team deal with non-functional requirements?

(choose the best answer)

Options:

A.

Manage them during the Integration Sprint prior to the Release Sprint.

B.

Assign them to the lead developers on the team.

C.

Ensure every Increment meets them.

D.

Make sure the release department understands these requirements, but it is not the

Scrum Team's responsibility.

Buy Now
Questions 49

During a Sprint Retrospective, for what is the Scrum Master responsible?

Options:

A.

Prioritizing the resulting action items.

B.

Participating as a Scrum team member and facilitating as requested or needed.

C.

Acting as a scribe to capture the Development Team’s answers.

D.

Summarizing and reporting the discussions to management.

Buy Now
Questions 50

Which two things should the Development Team do during the first Sprint? (Choose two.)

Options:

A.

Make up a plan for the rest of the project.

B.

Analyze, describe, and document the requirements for the subsequent Sprints.

C.

Develop at least one piece of functionality.

D.

Define the major product features and release plan architecture

E.

Create an increment of potentially releasable software.

Buy Now
Questions 51

Which three of the following are time-boxed events in Scrum? (Choose three.)

Options:

A.

Release Testing.

B.

Release Retrospective.

C.

Sprint Retrospective.

D.

Sprint Planning.

E.

Sprint Testing.

F.

Sprint 0.

G.

Daily Scrum.

Buy Now
Questions 52

Which two things should the Development Team do during the first Sprint? (Choose two.)

Options:

A.

Make up a plan for the rest of the project.

B.

Analyze, describe, and document the requirements for the subsequent Sprints.

C.

Develop at least one piece of functionality.

D.

Analyze, design, and describe the complete architecture and infrastructure.

E.

Create an increment of potentially releasable software.

Buy Now
Questions 53

Who does the work to make sure Product Backlog items conform to the Definition of Done?

(choose the Best answer)

Options:

A.

The Quality Assurance Team

B.

The Scrum Team

C.

The Product Owner

D.

The Scrum Master

E.

The Developers

Buy Now
Questions 54

The CEO asks the Developers to add a "very important" item to a Sprint that is in progress.

What should the Developers do?

(choose the best answer)

Options:

A.

Add the item to the top of the Product Backlog.

B.

Add the item to the current Sprint Backlog and begin work immediately since the

request came from the CEO.

C.

Add the item to the Sprint Backlog for the next Sprint.

D.

Discuss the item with the other members of the Scrum Team so the team can

decide what to do.

E.

Add the item to the current Sprint and drop an item of equal size.

Buy Now
Questions 55

Who is accountable for tracking the remaining work toward the Sprint Goal? (Choose the best answer.)

Options:

A.

The Developers.

B.

The Scrum Master.

C.

The Product Owner.

D.

The Project Manager.

Buy Now
Questions 56

True or False A scrum Master fulfills the same role as a traditional Project Manager

Options:

A.

True

B.

False

Buy Now
Questions 57

Which of the following are true about the Product Owner role? (Choose two.)

Options:

A.

The Product Owner is one person.

B.

The Product Owner is accountable for ordering the Product Backlog.

C.

Multiple people can share the Product Owner role on a Scrum Team.

D.

The Product Owner role can be played by a committee or a team of people.

Buy Now
Questions 58

Who determines how work is performed during the Sprint?

Options:

A.

Architects.

B.

The Development Team.

C.

The Scrum Master.

D.

Subject matter experts.

E.

Development Team managers.

Buy Now
Questions 59

Which output from Sprint Planning provides the Development Team with a target and overarching direction for the Sprint?

Options:

A.

The Sprint Backlog.

B.

The Sprint Goal

C.

The release plan.

D.

Sprint Review minutes.

Buy Now
Questions 60

Who is on the Scrum Team? (Choose all that apply.)

Options:

A.

Scrum Master

B.

Product Owner

C.

Development Team member

D.

Project Manager

E.

None of the above

Buy Now
Questions 61

The Definition of Done serves which three purposes?

(choose the best three answers)

Options:

A.

Create a shared understanding of when work is complete.

B.

Guide the Developers on how many Product Backlog items to select for the

Sprint.

C.

Increase transparency.

D.

Describe the work that must be mostly done before the Sprint is allowed to end.

E.

Describe the purpose, Objective, and timebox Of each Scrum event.

Buy Now
Questions 62

An organization has decided to adopt Scrum, but management wants to change the terminology to fit with terminology already used. What will likely happen if this is done? (Choose the best answer.)

Options:

A.

Without a new vocabulary as a reminder of the change, very little change may actually happen.

B.

The organization may not understand what has changed within Scrum and the benefits of Scrum may be lost.

C.

Management may feel less anxious.

D.

All answers apply.

Buy Now
Questions 63

Who starts the Daily Scrum?

Options:

A.

The person coming in last. This encourages people to be on time and helps to stay within the time-box.

B.

Whoever the Development Team decides should start.

C.

The person who has the token.

D.

The Scrum Master. This ensures that the Development Team has the meeting and stays within the time-box.

E.

The person who last broke the build.

Buy Now
Questions 64

You are the Scrum Master of a new, to be developed product. Development is going to require 45 people. What is a good first question for you to suggest the group thinks about when forming into teams?

Options:

A.

How will we make sure all teams have the right amount or expertise?

B.

What is the right mixture of senior and junior people on each team?

C.

Who are going to be the team leads?

D.

Who are the subject matter experts on each team?

Buy Now
Questions 65

Choose two responsibilities of a self-organizing Development Team. (Choose two.)

Options:

A.

Reorder the Product Backlog.

B.

Pull Product Backlog items for the Sprint.

C.

Do the work planned in the Sprint Backlog.

D.

Increase velocity.

E.

Report daily progress to stakeholders.

Buy Now
Questions 66

Which statement best describes a Product Owner’s responsibility?

Options:

A.

Optimizing the value of the work the Development Team does.

B.

Managing the project and ensuring that the work meets the commitments to the stakeholders.

C.

Directing the Development Team.

D.

Keep stakeholders from distracting the Development Team.

Buy Now
Questions 67

In accordance with Scrum theory, how should a group of 100 people be divided into multiple Development Teams?

Options:

A.

Understanding the product, the product vision and the rules of the Scrum framework, the group divides itself into teams.

B.

It doesn’t really matter because you can rotate the teams every Sprint to spread knowledge.

C.

Check with the allocation department to see who has worked together before and make these the first teams.

D.

Create a matrix of skills, seniority, and level of experience to assign people to teams.

Buy Now
Questions 68

For the purpose of transparency, when does Scrum say a new increment of working software must be available?

Options:

A.

After the acceptance testing phase.

B.

Before the release Sprint.

C.

Every 3 Sprints.

D.

At the end of every Sprint.

E.

When the Product Owner asks to create one.

Buy Now
Questions 69

At the end of a Sprint Product Backlog item worked on during the Sprint does not meet the definition of “Done”. What two things should happen with the undone Product Backlog item? (Choose two.)

Options:

A.

If the stakeholders agree, the Product Owner can accept it and release it to the users.

B.

Put it on the Product Backlog for the Product Owner to decide what to do with it.

C.

Review the item, add the “Done” part of the estimate to the velocity and create a Story for the remaining work.

D.

Do not include the item in the Increment this Sprint.

Buy Now
Questions 70

What happens if the Development Team cannot complete its work by the end of the Sprint?

Options:

A.

The Sprint is extended and future Sprints use this new duration.

B.

The Sprint length holds and the Development Team continuously learns what is actually possible to do within a Sprint of this length.

C.

The Sprint is extended temporarily. Lessons are taken to ensure it doesn’t happen again.

Buy Now
Questions 71

Which are characteristics of the Daily Scrum?

(choose the best two answers)

Options:

A.

Its location and time remain constant

B.

Its purpose is to inspect progress toward the Sprint Goal and adapt the Sprint

Backlog.

C.

It is tree form and designed to promote conversatiom

D.

It is facilitated by the team lead.

E.

It is held first thing in the morning.

F.

It consists of the Scrum Master asking the team tor status.

Buy Now
Questions 72

A Scrum Team is only allowed to meet with stakeholders during Sprint Review.

Options:

A.

True

B.

False

Buy Now
Questions 73

What techniques could the Scrum Master use when the Scrum Team gets caught in an internal disagreement

about which agile practices to apply? (Choose the best two answers.)

Options:

A.

Involve the complete Scrum Team in making a decision.

B.

Use coaching techniques; such as open QUESTION NO:s and active listening.

C.

Ask an external agile coach what they recommend.

D.

Ask team members to take the issue up with to the company’s Human Resources department.

Buy Now
Questions 74

One of the Scrum events is the Daily Scrum. What are two intended outcomes of the Daily Scrum? (Choose two.)

Options:

A.

A shared understanding of the most important work to be undertaken next to achieve the best possible progress toward the Sprint goal.

B.

An update of completed tasks and of the remaining work so the Scrum Master can plan the next day.

C.

A status report for the upper management indicating what each individual has done, will be doing, and what is impending him/her.

D.

An updated Scrum board to make Sprint progress transparent for the stakeholders.

E.

New impediments for the Scrum Master to take care of.

Buy Now
Questions 75

The Sprint Review is mainly an inspect and adapt opportunity for which group?

Options:

A.

The Development Team and stakeholders.

B.

The Product Owner and Development Team.

C.

The Scrum Team and stakeholders.

D.

The Product Owner and management.

E.

The Development Team and management.

F.

The Product Owner and stakeholders.

Buy Now
Questions 76

What is the recommended size for a Scrum Team? (Choose the best answer.)

Options:

A.

At least 7.

B.

9

C.

10 or fewer.

D.

7 plus or minus 3.

Buy Now
Questions 77

What does it mean to say that an event has a time-box?

Options:

A.

The event must happen at a set time.

B.

The event must happen by a given time.

C.

The event must take at least a minimum amount of time.

D.

The event can take no more than a maximum amount of time.

Buy Now
Questions 78

At the seventh Sprint Review, the stakeholders are disappointed and angry. They have determined that the product or system being built will not meet their needs and will cost more than they are willing to spend. What factors likely led to this? (Choose two.)

Options:

A.

The Project Management Office (PMO) has not been engaged adequately.

B.

The Product Owner has not been keeping the stakeholders aware of the progress of the project.

C.

The stakeholders haven’t been using the Sprint Reviews to inspect and evaluate progress.

D.

The stakeholders were not allowed to enter the development area.

Buy Now
Questions 79

How do you know that a Scrum Team is cross-functional? (Choose the best answer.)

Options:

A.

Scrum Team has all the skills to create an increment by the end of every Sprint.

B.

A few of the Development Team members pair program and do Test Driven Development.

C.

There are no conflicts within the Scrum Team.

D.

Every member of the Scrum Team is able to perform every task.

Buy Now
Exam Code: PSM-I
Exam Name: Professional Scrum Master I
Last Update: Apr 18, 2025
Questions: 268

PDF + Testing Engine

$134.99

Testing Engine

$99.99

PDF (Q&A)

$84.99