New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: best70

Prince2-Foundation PRINCE2 7 Foundation written Exam Questions and Answers

Questions 4

In which step of the Issue management’ technique should Superseded versions be archives?

Options:

A.

Implementing changes

B.

Assessing issues

C.

capturing issues

D.

Deciding on changes

Buy Now
Questions 5

According to the 'manage by exception’ principle, which statement about tolerances is CORRECT?

Options:

A.

Whenever authority is delegated to the project manager, the project board should set tolerances for the stage

B.

Whenever there is a forecast to exceed a tolerance, it should be escalated to the project board

C.

Whenever there is a forecast to exceed a tolerance, it should be resolved at the next monthly project board meeting

D.

Whenever authority is delegated to the team manager, the focus should be on delivering within time and cost tolerances

Buy Now
Questions 6

How does product-based planning help to determine the project approach?

Options:

A.

By Identifying the outputs that the project trust deliver

B.

By planning in detail how to deliver the outputs over a more predictable time scale

C.

By managing constraints to the planned completion date for the project

D.

By dividing the delivery of the project's outputs into stages which do not overlap

Buy Now
Questions 7

Why is change management important in a project?

Options:

A.

It provides clarity on how the culture of an organization needs to adapt over time

B.

It provides processes and management products to use when requesting a change

C.

It provides confidence that the project can meet is objectives and has continued business Justification

D.

It provides a controlled and bidirectional flow of information to key Influencers

Buy Now
Questions 8

The project manager needs to record what will make file Users satisfied with the final product

Where should the project manager record this?

Options:

A.

Quality register

B.

Project plan

C.

Project product description

D.

Quality management approach

Buy Now
Questions 9

The project manager needs to know whether the response to a threat to the project has been actioned.

Which should the project manager review?

Options:

A.

Risk register

B.

Product register

C.

Risk management approach

D.

Checkpoint report

Buy Now
Questions 10

The project manager heeds to prioritize several criteria that the project product must meet in order to be acceptable in which step of the ‘quality management technique should this occur?

Options:

A.

Gathering user inputs

B.

Accepting products

C.

Describing the quality management approach

D.

controlling quality

Buy Now
Questions 11

Which action should the project manager take during the 'assessing issues' step?

Options:

A.

Create an exception plan tor project board approval

B.

Gain project board feedback on the Issue priority

C.

Consider the impact of alternative options for resolution

D.

Determine the initial priority of the issue that has been raised

Buy Now
Questions 12

Identify the missing word in the following sentence.

An (?) is the result of change, normally affecting real-world behavior and circumstances:

Options:

A.

outcome

B.

exception

C.

output

D.

off-specification

Buy Now
Questions 13

How is uncertainty identified, assessed and controlled?

Options:

A.

By avoiding or reducing a threat

B.

By analysing the risk cause in detail

C.

By applying the risk practice

D.

By allocating a risk budget to the project

Buy Now
Questions 14

Which action should the project manager take when reviewing progress to assess the 'health' of a stage?

Options:

A.

Capture lessons that may assist in the monitoring and control of this project

B.

Review the quality of the relationships in the organizational

C.

Increase the frequency of event-driven controls to monitor stage progress

D.

Identify whether issues are resolved in a timely manner or left unmanaged

Buy Now
Questions 15

What is an advantage of dividing the project into stages?

Options:

A.

Detailed plans can be prepared closer to the time events will take place

B.

the project board can delegate management of the project to team managers

C.

The project can be authorized by the project manager on a stage by stage basis

D.

The project brief can be updated towards the end of each stage

Buy Now
Questions 16

How do issue management and change control relate to each other?

Options:

A.

Change control and Issue management are separate processes

B.

Issue management is part of change control

C.

change control is part of issue management

D.

issue management and change control are identical

Buy Now
Questions 17

Which should define how tools will be used to support the information needs of the project team?

Options:

A.

Digital and data management approach

B.

Quality management approach

C.

Issue management approach

D.

Commercial management approach

Buy Now
Questions 18

Which is a purpose of a quality register?

Options:

A.

To record cross-references to issues relating to the quality of the products

B.

To record the date a completed work package was received

C.

To provide the status of quality activities carried out for completed products

D.

To capture quality concerns about completed products

Buy Now
Questions 19

The project manager has created a list of tasks to produce the project's products.

Which step of the ‘organizational design and development’ technique should be informed ty this 1st?

Options:

A.

Design the project ecosystem

B.

Understand the organizational ecosystem

C.

Manage the ongoing changes to the project ecosystem

D.

Develop the project ecosystem

Buy Now
Questions 20

Identify the missing word in the following sentence.

[ ? ] is the measurable decline resulting from a negative outcome.

Options:

A.

An exception

B.

A dis-benefit

C.

An off-specification

D.

A risk

Buy Now
Questions 21

Which is a minimum requirement for applying the change theme?

Options:

A.

To identify whether an issue affects the continuation of the project

B.

To ensure each change is managed as an exception

C.

To produce a breakdown of the products to be produced

D.

To tailor all changes to improve the quality of the project

Buy Now
Questions 22

In which process is the work to be done assigned to a team manager?

Options:

A.

Directing a project

B.

Managing a stage boundary

C.

Controlling a stage

D.

Managing product delivery

Buy Now
Questions 23

What is documented in the project plan to support the 'manage by exception' principle?

Options:

A.

The project's tolerances for cost and time

B.

A project product's quality criteria

C.

The expected project benefits

D.

Activities to mitigate project risks

Buy Now
Questions 24

Which is a purpose of the 'directing a project' process?

Options:

A.

To create and authorize the project mandate

B.

To ensure that work on products allocated to the team is authorized and agreed

C.

To control the day-to-day running of the project

D.

To delegate day-to-day management of the project to the project manager

Buy Now
Questions 25

Which is a purpose of the quality theme?

Options:

A.

To check that the project is viable and achievable

B.

To ensure that the project outputs are agreed

C.

To ensure that formal issues are recorded

D.

To enable the project to be managed according to plan

Buy Now
Questions 26

The project manager reviews whether there has been a Change in the way team members relate to each other.

Which principle is the project manager applying as part of the 'people' element?

Options:

A.

Manage by stages

B.

Focus on products

C.

Tailor to suit the project context

D.

Learn from experience

Buy Now
Questions 27

Which process provides information for the project board to review an updated project plan?

Options:

A.

Initiating a project

B.

Controlling a stage

C.

Directing a project

D.

Managing a stage boundary

Buy Now
Questions 28

Which report must be used to inform the project board of a predicted deviation from agreed stage limits?

Options:

A.

End stage report

B.

Checkpoint report

C.

Highlight report

D.

Exception report

Buy Now
Questions 29

Which management level should approve a course of action if project-level tolerance is exceeded?

Options:

A.

Corporate, programme management or the customer

B.

Project board

C.

Project manager

D.

Team manager

Buy Now
Questions 30

Which is a purpose of the quality theme?

Options:

A.

To establish how the project will ensure that all products created meet their requirements

B.

To establish baselines against which any changes to products can be assessed

C.

To identify all the products of the project to ensure the scope has been adequately defined

D.

To determine the communication needs of the organization’s quality assurance function

Buy Now
Questions 31

Which is a purpose of the 'controlling a stage' process?

Options:

A.

To review the success of the project at the end of a management stage

B.

To agree work package acceptance and delivery requirements

C.

To produce regular highlight reports for the project board

D.

To re-plan the current stage and the project when requested

Buy Now
Questions 32

Which is a minimum requirement for applying the organization theme?

Options:

A.

The project's approach to engaging with its stakeholders must be defined

B.

Roles must be combined to reduce the number of individuals needed on the project

C.

During a procurement the senior supplier must be appointed from the customer organization

D.

The project team must change at each end stage of the project life cycle

Buy Now
Questions 33

Which describes a time-driven control?

Options:

A.

The dates for the project's end stage assessment included in the project plan

B.

The expected frequency of progress reports specified in a work package

C.

The expected dates for planned checks of specialist products included in a stage plan

D.

The planned exception assessment meeting to authorize a requested exception plan

Buy Now
Questions 34

The project board needs to confirm that there is enough information to initiate the project.

What should the project board review?

Options:

A.

Project brief

B.

Business case

C.

Benefits management approach

D.

Project plan

Buy Now
Questions 35

How should the "managing a stage boundary' process be used towards the end of a project's final delivery stage?

Options:

A.

To plan the activities of the closing a project' process

B.

To implement any exception plan requests from the project board

C.

To create a benefits management approach for corporate, programme management or the customer

D.

To review an issue received from a team manager

Buy Now
Questions 36

Who is responsible for documenting any tailoring of the business case theme?

Options:

A.

Executive

B.

Business project assurance

C.

Project manager

D.

Corporate management

Buy Now
Questions 37

How are team managers involved in tailoring PRINCE2 suit the project?

Options:

A.

Team managers are accountable for the tailoring of the work packages

B.

Team managers may advice on tailoring to improve the management of work packages

C.

Team managers should not be involved in tailoring PRINCE2

D.

Team managers should document the tailoring of the work packages

Buy Now
Questions 38

Where can people who join a project after initiation quickly and easily find information about how the project is being managed?

Options:

A.

Project brief

B.

Project initiation documentation

C.

Project mandate

D.

Project product description

Buy Now
Questions 39

Why is it necessary to apply the 'defined roles and responsibilities' principle?

Options:

A.

Because the people involved in a project should know what is expected of them

B.

Because the project management team should be cross-functional

C.

Because the user and supplier interests should be involved on a need-to-know basis

D.

Because the project manager should represent all the stakeholders of the project

Buy Now
Questions 40

What statement describes how the project manager should ensure effective communication within a project?

Options:

A.

Use a more structured approach to communication with co-located teams, then remote teams

B.

Rely on regular reporting by team managers to determine whether the work Is on track

C.

Involve 3 small group of key stakeholders when defining the project to reduce the amount of communication

D.

Focus on publishing standard messages to key influencers throughout the project

Buy Now
Questions 41

Which is a minimum requirement when applying the 'risk' theme?

Options:

A.

To identity and ring-fence an explicit risk budget within the project's budget

B.

To describe the probability impact grid in the risk management approach

C.

To appoint project assurance to maintain the risk register during initiation

D.

To assess if risks might have a material impact on business justification

Buy Now
Questions 42

According to the ‘continued business justification’ principle, what should happen to the funds when a project can no longer be justified?

Options:

A.

They should be returned to corporate, programme management or customer

B.

They should be used to create an alternative business case for the project

C.

They should be transferred back to the project board to reassign

D.

They should be used to deliver a reduction in the scope of the project

Buy Now
Questions 43

In which step of the 'planning' technique should a team manager break down the cost of delivering a work package?

Options:

A.

Preparing estimates

B.

Defining and analyzing the products

C.

Organizing work packages

D.

Preparing a schedule

Buy Now
Questions 44

What should the benefits management approach define?

Options:

A.

What actions will be taken to ensure the project's outcomes are achieved

B.

What will be used to record the effectiveness of the project's approaches

C.

How the project has progressed against its plans

D.

The suitability of the project management team structure

Buy Now
Questions 45

What is a goal of the 'implement' step within the recommended risk management procedure?

Options:

A.

To prepare specific management responses to identified risks

B.

To monitor the effectiveness of actioned risk responses

C.

To estimate the risk to the project in terms of probability and impact

D.

To communicate information related to the risks faced by the project

Buy Now
Questions 46

Which statement about the length of management stages in a project is CORRECT?

Options:

A.

A higher level of major risk will require a stage to be longer

B.

Stage length is influenced by project board availability

C.

A higher level of major risk will require a stage to be shorter

D.

Use of management stages represents a time driven control

Buy Now
Questions 47

How can the risk culture of 3n organization make decision-making less effective?

Options:

A.

By using statistical modelling be understand the Impact of risks and their likelihood

B.

By establishing a risk budget to make funding risk responses actions easier

C.

By Individuals adopting an attitude that leads them to ignore threats to objectives

D.

By Involving stakeholders in assessing the likelihood and impact of each risk

Buy Now
Questions 48

Identify the missing words in the following sentence.

PRINCE2 requires that the business case is formally verified by [?] at stage boundaries.

Options:

A.

corporate, programme management or the customer

B.

the project board

C.

the project manager

D.

the change authority

Buy Now
Questions 49

How does applying the ‘focus on products’ principle help to ensure that stakeholder expectations are met?

Options:

A.

By providing a common understanding of the products required

B.

By providing the tolerances for the project manager’s objectives

C.

By providing roles descriptions for the project management team

D.

By providing the justification for the project

Buy Now
Questions 50

How does the ‘managing product delivery’ process achieve its purpose?

Options:

A.

By agreeing requirements for how project work should be undertaken

B.

By producing highlight reports to enable the project board to oversee the work

C.

By requiring the project manager to produce and monitor team plans

D.

By escalating issues and risks that cannot be resolved within stage tolerance

Buy Now
Questions 51

Which is part of quality control?

Options:

A.

Undertaking quality reviews

B.

Writing product descriptions

C.

Providing assurance that the project is being conducted properly

D.

Documenting the customer's quality expectations

Buy Now
Questions 52

Which role is responsible for creating Checkpoint Reports?

Options:

A.

Senior Supplier

B.

Team Manager

C.

Change Authority

D.

Project Support

Buy Now
Questions 53

Which is a purpose of the Directing a Project process?

Options:

A.

Create and authorize the project mandate

B.

Ensure that work on products allocated to the team is authorized and agreed

C.

Control the day-to-day running of the project

D.

Delegate day-to-day management of the project to the Project Manager

Buy Now
Questions 54

Which is a recommended quality review team role?

Options:

A.

Project Manager

B.

Assurance

C.

Project Support

D.

Administrator

Buy Now
Questions 55

Which process is triggered towards the end of the final stage when all the assigned work has been completed?

Options:

A.

Managing a Stage Boundary

B.

Managing Product Delivery

C.

Closing a Project

D.

Controlling a Stage

Buy Now
Questions 56

Which step in the issue and change control procedure considers alternative options for responding to an issue that is being managed formally?

Options:

A.

Capture

B.

Examine

C.

Propose

D.

Decide

Buy Now
Questions 57

Which is NOT considered when defining risk tolerance?

Options:

A.

A Project Board's attitude towards risk taking

B.

The allocated risk budget

C.

An organization's risk appetite

D.

The amount of risk a Project Board considers acceptable

Buy Now
Questions 58

Identify the missing words in the following sentence. A project is [ ? ] organization that is created for the purpose of delivering business products.

Options:

A.

a corporate

B.

a temporary

C.

an external

D.

a technical

Buy Now
Questions 59

Who should use the information in a Lessons Report to refine, change and improve the standards within a quality management system?

Options:

A.

Corporate group

B.

Project Board

C.

Project Assurance

D.

Executive

Buy Now
Questions 60

Identify the missing word in the following sentence. A member of the Project Board is responsible for [ ? ] assurance.

Options:

A.

quality

B.

supplier

C.

risk

D.

product

Buy Now
Questions 61

Which of the following statements about the Project Initiation Documentation are true?

1. The Project Initiation Documentation is used to ensure that a sound basis exists before the Project Board authorizes a project.

2. The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project.

Options:

A.

Only 1 is true

B.

Only 2 is true

C.

Both 1 and 2 are true

D.

Neither 1 or 2 are true

Buy Now
Questions 62

What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?

Options:

A.

Configuration Item Record

B.

Quality Register

C.

Highlight Report

D.

Checkpoint Report

Buy Now
Questions 63

Which is a task of product-based planning?

Options:

A.

Identify activities and dependencies

B.

Write the Project Product Description

C.

Prepare the Work Packages

D.

Produce Product Status Accounts

Buy Now
Questions 64

Which is an objective of the Initiating a Project process?

Options:

A.

Develop the corporate quality management system as part of the Project Initiation Documentation

B.

Prepare the plans for the subsequent stages

C.

Summarize how the organization's project management method will be tailored for the project

D.

Request authority from corporate management to deliver the project

Buy Now
Questions 65

Which of the following statements about the Closing a Project process are true?

1. The Closing a Project process provides a fixed point for the receipt of completed Work Packages for the work performed in the final stage.

2. The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved.

Options:

A.

Only 1 is true

B.

Only 2 is true

C.

Both 1 and 2 are true

D.

Neither 1 or 2 are true

Buy Now
Questions 66

How many management stages should a PRINCE2 project consist of?

Options:

A.

Start up stage, initiation stage and at least one other management stage to cover the remainder of the project

B.

Start up stage, at least one other management stage to cover the remainder of the project and a closing stage

C.

Initiation stage and at least one other management stage to cover the remainder of the project

D.

Start up stage, initiation stage and a closing stage

Buy Now
Questions 67

Which of the following statements about quality assurance and Project Assurance is true?

Options:

A.

Project Assurance is the responsibility of the corporate organization; quality assurance is the responsibility of the Project Board

B.

Project Assurance is independent of the Project; quality assurance is only independent of the Project Manager

C.

Project Assurance may be delegated within a project; quality assurance must be undertaken by the Project Board

D.

Project Assurance ensures compliance to standards within the project environment; quality assurance ensures compliance across the organization

Buy Now
Questions 68

Which statement about stages is true?

Options:

A.

Management stages should be of the same duration

B.

The use of technical stages is mandatory

C.

The use of management stages is mandatory

D.

Management stages are driven by specialist teams

Buy Now
Questions 69

From whom does a Team Manager obtain approval for a completed product?

Options:

A.

Project Manager

B.

Project Support

C.

The authority defined in the Product Description

D.

Senior Supplier

Buy Now
Questions 70

Which is part of quality control?

Options:

A.

Document the project's acceptance criteria in the Project Product Description

B.

Define the quality responsibilities of those involved in the production of the products

C.

Produce quality records to show that the planned quality activities have been carried out

D.

Maintain the corporate organization's quality management system

Buy Now
Questions 71

Which two roles are linked by the Managing Product Delivery process?

Options:

A.

Corporate or programme management and Project Board

B.

Project Board and Project Manager

C.

Project Manager and Team Manager

D.

Team Manager and external supplier

Buy Now
Questions 72

If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?

Options:

A.

Checkpoint Report

B.

Highlight Report

C.

Issue Report

D.

Product Status Account

Buy Now
Questions 73

Which is a difference between management and technical stages?

Options:

A.

Management stages require planning and technical stages do not

B.

Technical stages can overlap and management stages cannot

C.

Management stages deliver products and technical stages do not

D.

Technical stages require resources and management stages do not

Buy Now
Questions 74

Which risk response type is appropriate to respond to an opportunity?

Options:

A.

Accept

B.

Fallback

C.

Exploit

D.

Transfer

Buy Now
Questions 75

Which is an objective of the Managing Product Delivery process?

Options:

A.

Sign-off completed Work Packages

B.

Ensure the Business Case is kept under review

C.

Report progress to the Project Board

D.

Ensure that work on products is authorized and agreed with the team

Buy Now
Questions 76

Which is the base product against which the Project Board can assess progress, issues and ongoing viability questions?

Options:

A.

Project Brief

B.

Project Initiation Documentation

C.

Project mandate

D.

Benefits Review Plan

Buy Now
Questions 77

Which is a typical core activity within configuration management?

Options:

A.

Issue management

B.

Quality inspection

C.

Identification

D.

Preparation

Buy Now
Questions 78

Which is a true statement about PRINCE2 event-driven controls?

Options:

A.

Event-driven controls take place at predefined periodic intervals

B.

Event-driven controls are produced at the frequency defined in a Work Package

C.

Event-driven controls are used for decision making

D.

Checkpoint Reports are event-driven controls

Buy Now
Questions 79

How many roles make up the Project Board?

Options:

A.

One

B.

Two

C.

Three

D.

Four

Buy Now
Questions 80

Which characteristic of a project reflects that there are different perspectives and motivations for customers and suppliers?

Options:

A.

Change

B.

Cross-functional

C.

Unique

D.

Risk

Buy Now
Questions 81

Which is one of the six aspects of project performance that needs to be managed?

Options:

A.

Progress

B.

Change

C.

Risk

D.

Security

Buy Now
Questions 82

Which should be funded from a change budget?

Options:

A.

The Starting up a Project process

B.

A fallback plan

C.

An agreed change to the scope of a project

D.

A change to a plan, within allocated tolerances, due to poor estimating

Buy Now
Questions 83

Which is an objective of the Directing a Project process?

Options:

A.

Create and authorize the project mandate

B.

Provide management control and direction

C.

Control the day-to-day running of the project

D.

Provide accurate progress information to the Project Manager

Buy Now
Questions 84

Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?

Options:

A.

Those with a financial interest in the project

B.

Those who will manage the project on a day-to-day basis

C.

Those who will specify the desired outputs of the project

D.

Those who will create the project's outputs

Buy Now
Questions 85

According to the guidance for effective quality management, when should the requirements for a product be captured?

Options:

A.

When the project team realizes that the product is needed

B.

When the project team needs to test the product

C.

When the project team needs to know whether the product has been approved

D.

When the project team needs to know how the product will be delivered

Buy Now
Questions 86

What is a purpose of the ‘organizing practice?

Options:

A.

To define who is responsible for which project activities

B.

To compare the team's actual achievements against the team plan

C.

Ta understand what the users require of the project

D.

To assess modifications raised by team members

Buy Now
Questions 87

How should the ‘progress’ practice be used?

Options:

A.

To define how the products will be delivered to enable control

B.

To predict whether the benefits will exceed the costs

C.

To identify opportunities that may make the project more successful

D.

To deliver change which will benefit people in their day-to-day work

Buy Now
Questions 88

in the ‘starting up a project’ process, what is the PRINCE? name for a ‘request for proposal’ received by an external supplier?

Options:

A.

Project mandate

B.

Project brief

C.

Work package

D.

Project approach

Buy Now
Questions 89

In which step of the 'risk management technique should the organization's environment be considered?

Options:

A.

Identify

B.

Assess

C.

Plan

D.

Implement

Buy Now
Questions 90

The project manager needs to monitor the progress of the stage.

Which combination of management products should the project manager review?

Options:

A.

Checkpoint reports AND work package descriptions

B.

Project plan AND project log

C.

Project plan AND work package descriptions

D.

Highlight report AND checkpoint report

Buy Now
Questions 91

The project manager reviews the project product description to identify the detailed requirement for each product.

In which step of the quality management technique should the project manager do this review?

Options:

A.

Gathering user inputs

B.

Accepting products ay

C.

Describing the quality management approach

D.

Controlling quality

Buy Now
Questions 92

Identify the missing ward in the following sentence.

PRINCE2 uses the team [2] to cover all people required to allocate their time to the project.

Options:

A.

project team

B.

project management team structure

C.

project bard

D.

project assurance

Buy Now
Questions 93

When should the project baseline be updated in order ta meet the purpose of the 'issues' practice?

Options:

A.

When a request for change is recorded on the issue register

B.

When a business opportunity has been recognized

C.

When the project manager receives a request for change

D.

When a change has been approved by the change authority

Buy Now
Questions 94

What is the BEST reason to perform the risk practice?

Options:

A.

To ensure risks are assigned to people who will own and action them satisfactorily

B.

To establish a supportive risk culture to enable decision-making

C.

To ensure stop-go decisions at stage boundaries are risk-informed

D.

To identiDfy and manage risks to project objectives

Buy Now
Questions 95

Which details the identified threats and Opportunities related in the project?

Options:

A.

Risk management approach

B.

Project plan

C.

Risk register

D.

Business case

Buy Now
Questions 96

Which describes a management activity within a project?

Options:

A.

Encouraging a project team to continue working on a particularly challenging product

B.

Discussing project objectives with key stakeholders during a requirements gathering workshop

C.

Agreeing a work package with a team manager to deliver products within agreed tolerances

D.

Seeking feedback from team members to ensure they are still aligned to the project's objectives

Buy Now
Questions 97

How is Uncertainty Identified, assessed and controlled?

Options:

A.

By avoiding or reducing a threat

B.

By analysing the risk cause in detail

C.

By applying the risk practice

D.

By allocating a risk budget to the project

Buy Now
Questions 98

The project manager needs to understand what makes the outputs acceptable to the users.

In which step of the 'planning' technique should this occur?

Options:

A.

Defining and analysing the products

B.

Organizing work packages

C.

Preparing estimates

D.

Preparing a schedule

Buy Now
Questions 99

Which is a definition of management?

Options:

A.

Directing the execution of project tasks as agreed for the project

B.

Away of working that characterises a group of people

C.

Being accountable to the business for the success of the project

D.

The party responsible for commissioning the project

Buy Now
Questions 100

Which principle should ensure that a project remains aligned with the objectives of the investing organizations?

Options:

A.

Focus on products

B.

Manage by exception

C.

Tailor to suit the project

D.

Ensure continued business justification

Buy Now
Questions 101

Which TWO are objectives of the 'managing a stage boundary" process?

1. To confirm to the project board that there are no products outstanding for the stage

2. To ensure that expectations are managed via accurate reporting to the project manager during a stage

3. To ensure that the project management team is not distracted by delivering additional products during the stage

4. To request the project board to approve work to start on the next stage

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 102

Which term is defined as a product that will not meet is quality specifications?

Options:

A.

Off-specification

B.

Request for change

C.

Concern

D.

Problem

Buy Now
Questions 103

The project manager needs to plan the reviews to confirm whether the expected measurable improvements have been achieved.

Which management product should the project manager produce?

Options:

A.

Benefits management approach

B.

Business case

C.

Quality management approach

D.

End project report

Buy Now
Questions 104

Which TWO are objectives of the closing a project: process?

1. To ensure the benefit reviews enable the project benefits to the confirmed

2. To update the business case so that the project hoard can decide whether to continue with the project

3. To ensure that the project team deliver the products to quality expectations

4. To hand over any open threats to operations

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 105

How is the tailoring approach defined for a project?

Options:

A.

The project board approves the approach

B.

The project board documents the approach

C.

Project assurance approves the approach

D.

Project assurance documents the approach

Buy Now
Questions 106

Why is a project brief produced?

Options:

A.

To act as a trigger for the 'starting up a project' process

B.

To record the how the project will communicate with its stakeholders

C.

To provide a full and firm foundation for the initiation of a project

D.

To be used by the project board as a basis for reviewing the progress of a project

Buy Now
Questions 107

According to PRINCE2, which characteristic is necessary for an effective project board?

Options:

A.

An ability to delegate

B.

An attention to detail

C.

A calm management style

D.

A 'problem-solving' approach

Buy Now
Questions 108

Which of the following refers to the actions identified to bring a situation to a level where exposure to a risk is acceptable?

Options:

A.

Risk category

B.

Risk description

C.

Risk response

D.

Risk status

Buy Now
Questions 109

What plan is created, and submitted for approval, during the Managing a Stage Boundary process?

Options:

A.

Team Plan

B.

Stage Plan

C.

Benefits Review Plan

D.

Project Plan

Buy Now
Questions 110

Which is a purpose of a Risk Register?

Options:

A.

Capture risks that may occur during the project

B.

Record how risk management activities will be undertaken on the project

C.

Record the risk tolerance for the project

D.

Capture issues which are impacting on the delivery of the project objectives

Buy Now
Questions 111

Which should be provided by a project mandate?

Options:

A.

Terms of reference

B.

Detailed Business Case

C.

Stage tolerances

D.

Initiation Stage Plan

Buy Now
Questions 112

Which are purposes of the quality theme?

1. To implement continuous improvement during the project

2. To establish how the project will ensure that products created will be acceptable to key stakeholders

3. To ensure that the project is desirable and achievable

4. To identify, assess and control uncertainty

Options:

A.

1 and 2

B.

2 and 3

C.

3 and 4

D.

1 and 4

Buy Now
Questions 113

What information about benefits management must be documented to meet the minimum requirements for applying the business case theme?

Options:

A.

The senior user's responsibilities for realizing benefits

B.

Statements of actual versus forecast benefits at reviews

C.

The management actions needed to ensure benefits are realized

D.

No specific documents related to benefits are necessary

Buy Now
Questions 114

Why is the 'learn from experience' principle applied to a project?

Options:

A.

To enable the project team to repeat successes from previous projects

B.

To enable the project team to develop a business case for the project

C.

To allow the project to be divided into management stages

D.

To enable the project team to use tolerances to delegate authority

Buy Now
Questions 115

Which activity takes place within the Managing a Stage Boundary process?

Options:

A.

Produce Highlight Reports

B.

Take corrective action within the limits of a stage's tolerance

C.

Produce an Exception Plan

D.

Authorize a Stage Plan for the next stage

Buy Now
Questions 116

Which product describes the method the project will use to engage with corporate, programme management or the customer?

Options:

A.

Quality management approach

B.

Communication management approach

C.

Change control approach

D.

Benefits management approach

Buy Now
Questions 117

Which is a purpose of the Risk Register?

Options:

A.

Describe the risk management techniques and standards to be applied to the project

B.

Act as a central record of information relating to the identified risks for the project

C.

Act as a repository for informal issues

D.

List the responsibilities for achieving an effective risk management procedure

Buy Now
Questions 118

What must be included in the risk management approach, as a minimum requirement for applying the risk theme?

Options:

A.

A description of the risk management procedure

B.

An explanation of the company's risk appetite

C.

The names of the assigned actionees for each risk

D.

Estimations of the likelihood and impact of risks

Buy Now
Questions 119

Which is a purpose of a quality register?

Options:

A.

To record the quality management approach for a product

B.

To issue a unique reference number for each product

C.

To detail the number and type of quality activities to be conducted

D.

To identify corrective actions that are required after an audit by quality assurance

Buy Now
Questions 120

Which process provides information for the project board to review a completed stage and confirm continued business justification?

Options:

A.

Controlling a stage

B.

Closing a project

C.

Directing a project

D.

Managing a stage boundary

Buy Now
Questions 121

Which process ensures that key roles and responsibilities are allocated before a decision is made to initiate a project?

Options:

A.

Managing Product Delivery

B.

Initiating a Project

C.

Managing a Stage Boundary

D.

Starting up a Project

Buy Now
Questions 122

When should the level of tailoring be defined?

Options:

A.

During the initiation stage

B.

When reviewing what has been learned to date

C.

As a response to issues and risks experienced

D.

Before the project is triggered by the project mandate

Buy Now
Questions 123

Which is an objective of the 'starting up a project' process?

Options:

A.

To approve the initiation stage

B.

To select the project mandate

C.

To define the project quality management approach

D.

To appoint the project management team

Buy Now
Questions 124

Which process provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification?

Options:

A.

Controlling a Stage

B.

Closing a Project

C.

Directing a Project

D.

Managing a Stage Boundary

Buy Now
Questions 125

Which level of management sets the project level tolerances?

Options:

A.

Project board

B.

Team manager

C.

Corporate, programme management or the customer

D.

Project manager

Buy Now
Questions 126

Which describes a risk event?

Options:

A.

The area of uncertainty in terms of the threat or opportunity

B.

The derivation or sources of a potential risk to the project

C.

The achievement of a milestone on the project plan

D.

The sequence of events and actions that will be put in place if a risk occurs

Buy Now
Questions 127

Which is a minimum requirement for applying the quality theme?

Options:

A.

To use lessons to inform quality planning

B.

To use the prescribed approach to quality management

C.

To use external quality standards for quality control

D.

To use user stories to inform the project product description

Buy Now
Questions 128

The application of which principle helps to define what should be included in a project?

Options:

A.

Defined roles and responsibilities

B.

Focus on products

C.

Manage by stages

D.

Continued business justification

Buy Now
Questions 129

To meet the minimum requirements for applying the progress theme, when must the business justification be reviewed?

Options:

A.

At the start of the project

B.

Throughout each stage

C.

When a change is raised

D.

In exception situations

Buy Now
Questions 130

Which theme estimates the cost of delivering the project?

Options:

A.

Business case

B.

Change

C.

Plans

D.

PROGEESS

Buy Now
Questions 131

Which is a purpose of a project brief?

Options:

A.

To act as a base document which enables the project board to assess progress

B.

To provide a sound basis for project initiation

C.

To define how the achievement of the project's benefits can be measured

D.

To provide a description of the means and frequency of communication

Buy Now
Questions 132

Which is an objective of the Starting up a Project process?

Options:

A.

Identify who will be responsible for creating the Project Plan

B.

Agree how the project will be monitored and controlled after initiation

C.

Authorize the Project Manager to proceed with the initiation stage

D.

Agree how issues and changes will be identified, assessed and controlled

Buy Now
Questions 133

Which is a purpose of the Risk theme?

Options:

A.

Establish a procedure to ensure every change is agreed by the relevant authority before it takes place

B.

Establish a cost-effective procedure to identify, assess and control uncertainty

C.

Establish mechanisms to control any unacceptable deviations from plan

D.

Establish mechanisms to manage risks at the corporate or programme level of an organization

Buy Now
Questions 134

Which describes risk probability?

Options:

A.

Level of risks which the project can tolerate before escalating to the Project Board

B.

Probable effect on the project delivering its objectives

C.

Timeframe within which the risk may occur

D.

A measure of the likelihood of the risk occurring

Buy Now
Questions 135

Which statement about time-driven controls is CORRECT?

Options:

A.

Time-driven controls are used for monitoring the progress of work packages and management stages

B.

Time-driven controls take place when specific events happen

C.

Time-driven controls are produced at the end of a stage

D.

An exception report is a time-driven control

Buy Now
Questions 136

What problem may occur if projects are not aligned with corporate business strategy?

Options:

A.

The control of projects may be poor

B.

The outputs may be of poor quality

C.

The objectives of different projects may overlap

D.

The project management approaches used may differ

Buy Now
Questions 137

Which product identifies how often stakeholders require information?

Options:

A.

Communication management approach

B.

Quality management approach

C.

Change control approach

D.

Risk management approach

Buy Now
Questions 138

Which is an objective of the 'managing a product delivery' process?

Options:

A.

To ensure the business case is regularly reviewed

B.

To assess whether the stage products have been approved

C.

To deliver the planned specialist products within tolerance

D.

To request authorization to start the next stage

Buy Now
Exam Code: Prince2-Foundation
Exam Name: PRINCE2 7 Foundation written Exam
Last Update: Dec 22, 2024
Questions: 461

PDF + Testing Engine

$134.99

Testing Engine

$99.99

PDF (Q&A)

$84.99