If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?
Identify the missing word(s) in the following sentence, PRINCE2 recommends three levels of [?] to reflect the needs of the different levels of management involved in a project,
Which PRINCE2 integrated element includes the good practices which determine whether a project is genuinely being managed using PRINCE2?
Which of the following take place before the initiation of a project?
1. Appoint the Executive
2. Capture requirements
3. Develop the Project Brief
4. Develop the detailed Business Case
In which product does a Project Manager define the time and cost tolerances for the work to be done by a Team Manager?
Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?
Identify the missing word(s) in the following sentence.
Following initiation, the Controlling a Stage process is used to manage and control each [ ? ] of a project.
What should influence the Project Board's decision whether to delegate its Project Assurance responsibilities?
Which theme defines the accountability for realization of the project's benefits?
What theme establishes the mechanisms to judge whether a project is worthwhile investing in?
Identify the missing words in the following sentence. The role of [ ? ] is responsible for carrying out a risk response action to respond to a particular risk.
Identify the missing word in the following sentence. The risk response type [ ? ] can be used to respond to a threat and an opportunity
Which theme addresses the need to have a strategy for communicating with stakeholders?
Which is assumed to be a customer's responsibility in the PRINCE2 customer/supplier environment?
What product records any time tolerances agreed between the Project Manager and Team Manager?