PMI-PBA PMI Professional in Business Analysis Questions and Answers

Questions 4

During the initial phase of a project, which technique could assist in identifying and categorizing the stakeholders?

Options:

A.

Business activity model

B.

RAC! matrix

C.

Power/interest grid

D.

Organization modeling

Buy Now
Questions 5

What can a business analyst use to track requirements documentation?

Options:

A.

Affinity diagram

B.

Data dictionary

C.

Business rules matrix

D.

Version control system

Buy Now
Questions 6

A stakeholder has rejected a project's deliverable because it does not meet the original business need. It is further determined that the deliverable does not meet the requirements identified in the baseline.

What is the best approach to resolve this issue?

Options:

A.

Meet with the customer and apologize for misunderstanding the business's need.

B.

Suggest re-estimating the requirement and following the change control process.

C.

Provide the stakeholder with a copy of the approved requirements baseline and move forward without making a change.

D.

Require development resources to work overtime to modify the deliverable to satisfy the stakeholder.

Buy Now
Questions 7

The business analyst is planning an approach to formally manage updates to requirements that may be requested by stakeholders.

What should the business analyst do?

Options:

A.

Develop a change control process.

B.

Obtain approval from the project sponsor.

C.

Document changes as they occur.

D.

Hold firm on scope and reject changes.

Buy Now
Questions 8

Which of the following would be the best practice in product validation?

Options:

A.

The measurement of the requirement should be based on the average of two or more evaluations.

B.

There should be two separate measurements for evaluating each functional requirement.

C.

Two or more testers should test the product using the same test cases so that their evaluations are consistent.

D.

The evaluation criteria should be the same as what was used to measure the requirement.

Buy Now
Questions 9

A firm implements SharePoint and the business analyst creates the requirements to develop a business analysis repository. In the requirements, the analyst describes a detailed workflow that includes appropriate stakeholders receiving email notifications of certain

activities. The SharePoint team needs to know which activities should trigger the notification workflow.

Which workflow trigger should the business analyst incorporate?

Options:

A.

Any change to the requirements matrix

B.

Changes to test cases traced to requirements

C.

Change through project life cycle

D.

Changes to stakeholder memberships

Buy Now
Questions 10

A business analyst created requirements for production of a product extract file for several systems. After reviewing the complex systems and dividing the processes into manageable tasks, the business analyst is able to identify the tasks required to implement the deliverable.

Which analysis technique has the business analyst used?

Options:

A.

Organization

B.

Decomposition

C.

Dependency

D.

Interface

Buy Now
Questions 11

The project team is working on test scripts to test a solution. Which source can be used for building tests of end-to-end business processes across business functions and systems?

Options:

A.

Prototype model

B.

Feature model

C.

Context diagram

D.

Use case

Buy Now
Questions 12

A sponsor requests a new requirement. The business analyst explains that most of the information needed for this requirement does not exist and that the requirement cannot be implemented. The business analyst recommends deferring the requirement until the needed information is available and then adding it to a subsequent project. The sponsor agrees.

What should the business analyst do next?

Options:

A.

Bring the subsequent project to the change control board (CCB).

B.

Ask the stakeholders to review the requirement before any other action is taken.

C.

Communicate that the status of this requirement has changed.

D.

Mark the requirement as complete so that it is not forgotten.

Buy Now
Questions 13

Through user acceptance testing, a software flaw was identified. What should the business analyst do next as part of the root cause analysis in order to analyze and resolve the discrepancy?

Options:

A.

Create a fishbone diagram.

B.

Create an interface analysis.

C.

Create a Delphi estimation.

D.

Create a functional decomposition.

Buy Now
Questions 14

When a change request is received, the business analyst is responsible for:

Options:

A.

analyzing the impact to the project schedule and budget.

B.

ensuring that change-related incidents are minimized in production.

C.

analyzing the impact on business and underlying systems.

D.

prioritizing and scheduling the changes requested.

Buy Now
Questions 15

The customer generated a design specification for a new product. What is the best action to take to establish an approved requirements baseline with the customer?

Options:

A.

Create a requirements traceability matrix for review and approval by the customer.

B.

Create a requirements baseline approval form for the customer to review and approve.

C.

Request that the customer create a baseline of the requirements in the contract specification.

D.

Perform a variance analysis on the design specification and report the results to the customer.

Buy Now
Questions 16

A business analyst conducts an initial review to define scope. The analysis includes the review of the business case, project goals, and objectives to obtain the necessary and required context. Based on that information, the business analyst determines that this is a large project with multiple interfaces which could cost the company money that was not initially included in the budget.

What characteristics of the project are needed to determine the approach so that the business analyst can validate whether they will

need to have a discussion about the budget?

Options:

A.

Selected project life cycle

B.

Business analysis deliverables to be produced

C.

Type of elicitation activities to be conducted

D.

Decision on the type of models to be used

Buy Now
Questions 17

In order to reduce product and project risk for a large, complex project, a business analyst is asked to help develop a change process that includes formal authorization and tracking throughout the life cycle of the project. The business analyst needs a capability that will help ensure that the product conforms to approved requirements, changes can be documented, and the status of each change can be

reported.

What should the business analyst use?

Options:

A.

Configuration management system

B Work breakdown structure

B.

Traceability matrix

C.

Context models

Buy Now
Questions 18

Which of the following is a method for requirements change control?

Options:

A.

Communication management

B.

Scope analysis

C.

Requirements management

D.

Baselining

Buy Now
Questions 19

How should a business analyst determine whether a solution satisfies business requirements?

Options:

A.

By reviewing the results of user acceptance testing

B.

By evaluating the solution against the project charter

C.

By conducting a brainstorming session with end users

D.

By reviewing the traceability matrix

Buy Now
Questions 20

A company wants to improve the service to its customers by reducing complaint response time by 40%. To achieve this goal, it is necessary to redesign and optimize their internal processes and support it with a new product. The client thinks that disruption and short-term loss of productivity is inevitable.

Where can the business analyst best reflect the intangible costs associated with this change?

Options:

A.

In the requirements specification document

B.

In the business case

C.

In the pay-back analysis

D.

In the balanced score card chart

Buy Now
Questions 21

A company has developed a new product for a customer. The customer provided a specification, but the company did not produce the system requirements in the verification matrix.

The customer is having difficulty determining if the product is meeting the requirements during the test event because the:

Options:

A.

customer did not adequately review the test procedure before the test.

B.

test engineer is not communicating effectively with the customer.

C.

requirements in the technical specification are unclear and ambiguous.

D.

customer cannot make this determination until the entire test is complete.

Buy Now
Questions 22

A company is working on implementing a software application. They are converting their complex, in-house processes into the new system. The business analyst has been asked to analyze the processes.

Which technique should be followed?

Options:

A.

Interface analysis

B.

Requirements traceability

C.

MoSCoW

D.

Feasibility analysis

Buy Now
Questions 23

A business analyst is leading a project to implement automated order entry software at a local pizza restaurant. The business analyst has very little information about the project: the ordering process takes too long and often ends in incorrect orders.

What step should the business analyst take next?

Options:

A.

Schedule a requirements gathering sessions with the manager of the ordering department.

B.

Request information on the current ordering process and compare it with other companies.

C.

Identify testing resources to support the implementation.

D.

Select the software to implement and start working with the technical resources.

Buy Now
Questions 24

A business analyst and stakeholders have completed documentation of the acceptance criteria for the requirements of a new vehicle leasing database. A concern is raised that some of the key performance indicators may not validate the desired benefits of the implementation.

What should the business analyst do to ensure that the business need can be validated?

Options:

A.

Document an assumption.

B.

Document a constraint.

C.

Document a defect.

D.

Document a business rule.

Buy Now
Questions 25

What is a standardized, effective, and efficient way to manage changes to project documentation?

Options:

A.

A configuration verification and audit system

B.

A requirements traceability matrix

C.

A configuration management system

D.

A change control board

Buy Now
Questions 26

Company A has set aside capital to invest in an upgrade to their scheduling system. Documentation of the current structure was presented to the business analyst. However, the description of certain steps is not documented clearly, and the business analyst has not been allowed to inspect the existing system. During elicitation, the business analyst asked questions of the schedulers as they performed functions in order to gain an understanding of the process.

Which type of elicitation technique did the business analyst use in this instance?

Options:

A.

Active observation

B.

Participatory observation

C.

Interview

D.

Simulation

Buy Now
Questions 27

Which technique or tool is used to obtain acceptance of the delivered product?

Options:

A.

Expert judgment

B.

Facilitated workshops

C.

Inspection

D.

Contextual inquiry

Buy Now
Questions 28

Which of the following is a properly written requirement statement?

Options:

A.

The pot shall be lightweight and heat up quickly.

B.

The pot shall be usable in the oven or on the stove.

C.

The pot shall be manufactured in the following colors: yellow, red, brown, blue.

D.

The pot shall prominently display the company brand.

Buy Now
Questions 29

What should the business analyst do to ensure that all requirements meet a quality checklist before the development and testing phase?

Options:

A.

Validate the requirements deemed important by the stakeholders.

B.

B. Obtain approval from engineering for partial testing of the requirements.

C.

Negotiate with the client to standardize the requirements.

D.

Assign a verification method to each requirement.

Buy Now
Questions 30

During validation of a project solution, the business analyst discovers that a requirement has been altered. Instead of placing the company logo in the upper-left corner of the window, it is displayed in the upper-right corner. When the business analyst asks the developer about the change, the developer says that one of the stakeholders asked directly for the change.

Which corrective action should the business analyst take?

Options:

A.

Ask the developer to correct the logo as stated in the requirement.

B.

Confront the stakeholder that requested the change.

C.

Follow the change control process as defined in the business analysis plan.

D.

Discuss the change in the next stakeholder meeting.

Buy Now
Questions 31

Which tool is the most appropriate to aid in development of measurable and actionable requirements for a new project?

Options:

A.

Network diagram

B.

Use case diagram

C.

Entity relationship diagram

D.

Activity-on-node diagram

Buy Now
Questions 32

How can a business analyst show progressive iterations of product development to stakeholders after the requirements baseline has been approved?

Options:

A.

Create prototype proof-of-concept models.

B.

Conduct requirement walkthrough sessions.

C.

Review performance data with the project sponsor.

D.

Talk to distinct testing groups to check testing status.

Buy Now
Questions 33

A stakeholder requests to add new critical requirements the day before the scheduled baseline requirements approval meeting. The stakeholder insists that these requirements must be taken into account despite time and budget constraints.

What is the most effective way to manage this situation?

Options:

A.

Discuss the change with stakeholders during the baseline approval meeting and ask them to approve the new baseline.

B.

Ask for more resources to manage this change and justify these additional resources with the value the change will give to

the company.

C.

Share the new requirements with all stakeholders and ask them to submit their comments before the meeting.

D.

Postpone the baseline approval meeting, analyze the impact, and schedule a new meeting to discuss dependencies and

priorities with stakeholders.

Buy Now
Questions 34

Which of the following techniques is used to identify ambiguous or unverifiable requirements?

Options:

A.

Fishbone analysis

B.

Resource checklist

C.

Traceability matrix

D.

Team peer review

Buy Now
Questions 35

The quality function deployment is best suited to assist in the process of:

Options:

A.

relating the product features to customer value.

B.

quality control by determining the control charts and the run charts.

C.

quality assurance by structuring the quality audits.

D.

controlling the effects between the quality functions.

Buy Now
Questions 36

Company A is working on implementing a new platform with multiple stakeholders. The business analyst has gathered the requirements and established a baseline. However, scope creep is a persistent problem.

What could the business analyst have established to help manage this situation?

Options:

A.

Change control process

B.

Configuration management system

C.

Communication plan

D.

Sponsor signoff

Buy Now
Questions 37

A business analyst has been assigned to a project that will design and build two new bridges and, at the same time, redesign a failing bridge for a local structural engineering company. All three bridges must be constructed and meet all safety requirements before flood season next spring.

How would the business analyst define the scope of this project?

Options:

A.

Perform a work breakdown structure.

B.

Perform a feasibility study.

C.

Perform process modelling.

D.

Perform a structured walkthrough.

Buy Now
Questions 38

A new project is in the planning phase. What should the business analyst consider with regard to planning the requirements change process?

Options:

A.

How requirement changes will impact the requirements baseline

B.

How requirement changes will be implemented

C.

How requirement changes will impact the validation plan

D.

How requirement changes will be communicated

Buy Now
Questions 39

A business analyst is assigned to the lead analyst role for a project. This project is one of the largest in the history of the company and includes several components and complex interfaces. The system in development will be used by a wide variety of stakeholders.

Which tool should the business analyst use to trace the large number of requirements that will be generated by this project?

Options:

A.

Data dictionary

B.

Configuration management system

C.

Sequence diagram

D.

D. Process model

Buy Now
Questions 40

The business analyst has completed the requirements gathering and documentation processes in developing a baseline document. Several signoffs are needed. During the joint review process with the key stakeholders, the stakeholders announce that they are still not ready to sign off due to a communication gap.

Which technique should the business analyst have followed to ensure consensus?

Options:

A.

The business analyst should have performed a complete review of each requirement with one of the stakeholders’ peers before the meeting.

B.

The business analyst should have performed a complete review of each requirement with the key stakeholders prior to the meeting.

C.

The business analyst should have reviewed the requirements of the project sponsor first before reviewing other requirements.

D.

The business analyst should have invited the key stakeholders to the meeting.

Buy Now
Questions 41

What are some of the components of a requirements management plan?

Options:

A.

Requirements definition, functional and non-functional requirements, and decision-making process

B.

Requirements work plan, requirements definition, and traceability matrix template

C.

Requirements work plan, prioritization process, and traceability matrix template

D.

Requirements definition, requirements attribute template, and traceability matrix template

Buy Now
Questions 42

After reviewing a business case, project goals, and objectives, a business analyst determines that the organization prefers taking an exploratory approach to finding the solution that best meets the business need. Which approach best aligns with the business need for this organization?

Options:

A.

Plan-driven approach

B.

Waterfall approach

C.

Analytical approach

D.

Change-driven approach

Buy Now
Questions 43

A new product was designed and delivered to the customer. The product exceeded customer expectations but did not meet the baseline budget for the product. What could be the issue?

Options:

A.

Risks identified in the risk management plan were not addressed properly.

B.

There is no issue since the product exceeded the customer expectations.

C.

The sponsor approved the release of the product without reviewing the budget.

D.

Requirements were not properly traced and monitored.

Buy Now
Questions 44

Which of the following is the best approach to enable developers and product owners to be in constant communication so that changes or issues that occur during development are exposed and discussed as they develop?

Options:

A.

Iterative

B.

Waterfall

C.

Linear

D.

Agile

Buy Now
Questions 45

The business managers had clearly stated that the delivered website must simultaneously accommodate millions of users around the globe. However, within the first week of the production launch, the website crashes frequently.

This situation could have been averted if:

Options:

A.

quality attributes were captured and tested.

B.

critical business requirements were accommodated and tested.

C.

nonfunctional requirements were identified and tested.

D.

essential product requirements were captured and tested.

Buy Now
Questions 46

A business analyst has captured all of the requirements from the various stakeholders within the organization and has compiled them into a complete list. After reviewing the list of requirements with the stakeholders, it is determined that the list of requirements is too large and will exceed the allotted budget.

Which tool or technique should the business analyst use with the stakeholders to prioritize the requirements to determine which requirements are approved, deferred, or rejected?

Options:

A.

SMART Goals

B.

Moscow Analysis

C.

SWOT Analysis

D.

Timeboxing Analysis

Buy Now
Questions 47

Several interviews with stakeholders to develop an inventory management system in a new architectural environment have revealed a significant concern about system and architectural stability. In which tool should the business analyst include this attribute to ensure that the requirement meets the acceptance criteria?

Options:

A.

Stakeholder satisfaction survey

B.

Interface analysis

C.

Process modeling

D.

Sectiead Traceability matrix

Buy Now
Questions 48

Which tool can be used to analyze how the system responds to various combinations of input conditions with the probability of each outcome?

Options:

A.

Decision tree

B.

Functional decomposition

C.

Expected monetary value

D.

Weighted criteria

Buy Now
Questions 49

A company is pleased with its delivered solution and reports that it has heard only minimal complaints for the first three months of use.

How can the business analyst determine how well the solution meets the business case?

Options:

A.

Conduct a user survey.

B.

Ask the sponsor for feedback.

C.

Survey the project.

D.

Compare the results of day-in-the-life (DITL) testing and integration testing.

Buy Now
Questions 50

A few months into a project, the business analyst determines that the costs are exceeding the perceived benefits. The business analyst wants to address the possible risks of having to cancel the product.

Which of the following documents should be used?

Options:

A.

Stakeholder impact matrix

B.

Business analysis plan

C.

Project charter

D.

Business case

Buy Now
Questions 51

In the middle of a project, a new requirement was added to the scope. The business analyst must determine if any impacts, dependencies, or risks are associated with the addition to the scope.

What task should the business analyst perform in order to identify these impacts?

Options:

A.

Manage solution scope.

B.

Manage requirements traceability.

C.

Manage requirements prioritization.

D.

Manage assumptions and constraints.

Buy Now
Questions 52

The test team is reviewing requirements that were written for Project A. They are having difficulty determining if the test results meet the project needs.

Which project artifact could the test team review to help identify acceptance criteria?

Options:

A.

Project scope

B.

Use cases

C.

RACI chart

D.

Delphi outcome

Buy Now
Questions 53

After implementation of the product, the customer reports defects. What is the best course of action to take?

Options:

A.

Compare reported defects with user acceptance test results.

B.

Escalate the issue to the project manager since the acceptance was given by the customer.

C.

Do nothing since the solution is now the responsibility of the operations manager.

D.

Involve the end users and plan a new round of acceptance tests to check the gaps.

Buy Now
Questions 54

A business analyst has incorporated all the relevant feedback from stakeholders in the business analysis plan.

Which next step should the business analyst take?

Options:

A.

Start documenting requirements.

B.

Obtain approval on the plan.

C.

Store the document for safe keeping.

D.

Start implementing the project.

Buy Now
Questions 55

Which of the following can be used to determine if requirements align to the product's objectives?

Options:

A.

Five Whys

B.

Activity network diagrams

C.

Context diagrams

D.

Business use cases

Buy Now
Questions 56

A business analyst is ready to begin requirements elicitation; however, stakeholders are not available to participate for another two weeks. Which elicitation technique should the business analyst use during this time?

Options:

A.

Cost-benefit analysis

B.

Benchmarking

C.

Brainstorming

D.

Document analysis

Buy Now
Questions 57

The software developers have delivered a completed solution. The quality assurance team has passed the solution. What should the business analyst do next?

Options:

A.

Evaluate the solution against the project charter.

B.

Conduct user acceptance testing.

C.

Evaluate the solution with the sponsor(s).

D.

Conduct performance testing.

Buy Now
Questions 58

A business analyst is attempting to elicit requirements on a current project. The business subject matter experts (SMEs) from various departments in the company question how the solution will work with their various systems. Which modeling technique should the business analyst use to depict how the solution will work with all of the company's systems?

Options:

A.

Data modeling

B.

B. Interface modeling

C.

Rules modeling

D.

Enterprise modeling

Buy Now
Questions 59

When a business analyst uses subject matter experts to define roles and identify influencers, which project artifact is created or updated?

Options:

A.

Stakeholder register

B.

RACI matrix

C.

SWOT analysis

D.

Stakeholder management plan

Buy Now
Questions 60

Which technique allows the collection of the maximum number of ideas on a subject from a group without considering the validity or practicality of the ideas?

Options:

A.

Brainstorming

B.

Interviewing

C.

Prototyping

D.

Surveying

Buy Now