New Year Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: best70

PMI-PBA PMI Professional in Business Analysis Questions and Answers

Questions 4

A business analyst has incorporated all the relevant feedback from stakeholders in the business analysis plan.

Which next step should the business analyst take?

Options:

A.

Start documenting requirements.

B.

Obtain approval on the plan.

C.

Store the document for safe keeping.

D.

Start implementing the project.

Buy Now
Questions 5

A company is working on implementing a software application. They are converting their complex, in-house processes into the new system. The business analyst has been asked to analyze the processes.

Which technique should be followed?

Options:

A.

Interface analysis

B.

Requirements traceability

C.

MoSCoW

D.

Feasibility analysis

Buy Now
Questions 6

Prior to the design phase, the project team needs to conduct a requirements review with the customer. To prepare for the review, it would be best for the team to:

Options:

A.

prepare a test procedure for the product to discuss at the requirements review.

B.

start designing the product to impress the customer with the amount of progress achieved early in the project.

C.

evaluate the requirements and highlight those that cannot be met or need to be deferred.

D.

request a contract amendment to delete any requirements from the contract that will be difficult to meet.

Buy Now
Questions 7

A business analyst is working on a project to update the user interface for a legacy procurement system. An end user raises concerns that the new solution will not support their core business processes.

How could the business analyst address the end user's concerns about the new interface?

Options:

A.

Consult the stakeholder register to evaluate if the user has authority to influence the project.

B.

Develop a prototype to gather functional requirements.

C.

Develop a use case package to support the user interface.

D.

Document the business data objects using an entity relationship diagram.

Buy Now
Questions 8

A business analyst from Company A has been assigned a project to document and identify requirements for a new commercial software implementation. The first step is to break down the business analysis deliverables into activities and tasks. Then, the business analyst

will add an estimate of the time needed to complete the work.

Which type of estimation technique is the business analyst using?

Options:

A.

Delphi

B.

Bottom-up

C.

Analogous

D.

Parametric

Buy Now
Questions 9

An organization is evaluating the possibility of conducting business internationally. Which factors should be investigated at the onset of the initiative?

Options:

A.

Deliverables to be produced

B.

Impacts on requirements baseline

C.

External dependencies

D.

Change control processes

Buy Now
Questions 10

A new project is in the planning phase. What should the business analyst consider with regard to planning the requirements change process?

Options:

A.

How requirement changes will impact the requirements baseline

B.

How requirement changes will be implemented

C.

How requirement changes will impact the validation plan

D.

How requirement changes will be communicated

Buy Now
Questions 11

The business analyst is seriously concerned about the possibility of differing interpretations of data items mentioned in the requirements documents. Which course of action should the business analyst take to minimize the risk of misunderstanding?

Options:

A.

Plan a peer review of the requirements specification.

B.

Ask the development teams for a formal acceptance of the requirements specification.

C.

Write a data dictionary that accompanies the requirements specification.

D.

Hold a workshop with the development teams to explain the details of the requirements specification.

Buy Now
Questions 12

The test team is reviewing requirements that were written for Project A. They are having difficulty determining if the test results meet the project needs.

Which project artifact could the test team review to help identify acceptance criteria?

Options:

A.

Project scope

B.

Use cases

C.

RACI chart

D.

Delphi outcome

Buy Now
Questions 13

The project team has all the document control process and versioning in place to capture the requirements changes. The team ensures that the change is documented in the scope document, resulting in the changed work breakdown schedule (WBS) and schedule. However, a key requirement was not implemented in the release.

Which is a possible reason why the requirement was not implemented?

Options:

A.

The requirements management plan was not updated with the change.

B.

The scope management plan was not updated with the change.

C.

The requirements traceability matrix was not updated with the change.

D.

The schedule management plan was not updated with the change.

Buy Now
Questions 14

A major stakeholder wants to know how the implementation of new features in the development of a product is progressing. Which of the following should be reported to the stakeholder?

Options:

A.

Distribution of project changes

B.

Requirements status during the project development cycle

C.

Number of requirements approved vs. number of requirements rejected

D.

Number of requirements tested and approved

Buy Now
Questions 15

The sales team of a company has won a time-and-material project. The business analyst discovers that the sales team has underestimated the required budget and schedule.

Which course of action should the business analyst take?

Options:

A.

Refrain from working on the project and request that the customer cancel the contract.

B.

Accept the contract, and then notify the customer about the potential for a cost overrun.

C.

Accept the contract, and deliver only the requirements that fit within the budget and schedule.

D.

Develop a requirements baseline document and use it to negotiate the scope in the contract.

Buy Now
Questions 16

A business analyst has received a test result report that shows evidence of defective functionality. The business analyst checks the test result again and verifies that the functionality behaves according to the requirements.

At this point, the business analyst should first:

Options:

A.

verify that the test case is incorrect.

B.

let the users decide if the test result 1s acceptable.

C.

change the requirement according to the test result.

D.

ask the tester to perform the test again.

Buy Now
Questions 17

Once the requirements are compared to internal and external quality standards, what should the business analyst do next?

Options:

A.

Set the priority of the requirements.

B.

Communicate the requirements to stakeholders.

C.

Ensure that the requirements are validated.

D.

Baseline the requirements.

Buy Now
Questions 18

A business analyst has started a project for a system enhancement. In order to determine how the requirements will be approved, the business analyst schedules a meeting with the stakeholders to discuss the proposed approval process.

Which measure of effective decision making allows the business analyst to finalize the process for requirement approval?

Options:

A.

The requirements verification process is documented.

B.

The requirements elicitation process is documented.

C.

The requirements validation process is documented.

D.

The requirements approval process is documented.

Buy Now
Questions 19

A stakeholder wants to modify an existing feature. Which of the following would be used to determine the scope of the change on the product?

Options:

A.

Project schedule and cost baseline

B.

Requirements traceability matrix

C.

Requirements attributes table

D.

Sequence diagram

Buy Now
Questions 20

A business analyst is attempting to elicit requirements on a current project. The business subject matter experts (SMEs) from various departments in the company question how the solution will work with their various systems. Which modeling technique should the business analyst use to depict how the solution will work with all of the company's systems?

Options:

A.

Data modeling

B.

B. Interface modeling

C.

Rules modeling

D.

Enterprise modeling

Buy Now
Questions 21

Projects have been managed well and completed on schedule and on budget. However, successful completion of the projects has not improved the company’s performance and profitability.

Which of the following should have been implemented to ensure that the projects would improve the company’s performance and profitability?

Options:

A.

review with appropriate stakeholders

B.

A project management plan

C.

A risk plan

D.

A strategies and goals analysis

Buy Now
Questions 22

A company is pleased with its delivered solution and reports that it has heard only minimal complaints for the first three months of use.

How can the business analyst determine how well the solution meets the business case?

Options:

A.

Conduct a user survey.

B.

Ask the sponsor for feedback.

C.

Survey the project.

D.

Compare the results of day-in-the-life (DITL) testing and integration testing.

Buy Now
Questions 23

The requirements traceability matrix should primarily be used to:

Options:

A.

identify the risks associated with dependent requirements.

B.

define a convention to map the requirements to their sources.

C.

ensure that all requirements have been met.

D.

address the responsibility owner for each requirement.

Buy Now
Questions 24

Which document best provides the boundaries for product development?

Options:

A.

Scope definition

B.

Requirements baseline

C.

Project plan

D.

Scope document

Buy Now
Questions 25

The business managers had clearly stated that the delivered website must simultaneously accommodate millions of users around the globe. However, within the first week of the production launch, the website crashes frequently.

This situation could have been averted if:

Options:

A.

quality attributes were captured and tested.

B.

critical business requirements were accommodated and tested.

C.

nonfunctional requirements were identified and tested.

D.

essential product requirements were captured and tested.

Buy Now
Questions 26

The best way to ensure the integrity of requirements is to:

Options:

A.

implement version control, maintain a history of requirements changes, and track the status of each requirement.

B.

use a requirements management tool, measure requirements volatility, and maintain a history of requirements changes.

C.

establish a change control board, track the status of each requirement, and use a requirements management tool.

D.

establish a requirements baseline, establish a change control board, and label each requirement uniquely.

Buy Now
Questions 27

In order to reduce product and project risk for a large, complex project, a business analyst is asked to help develop a change process that includes formal authorization and tracking throughout the life cycle of the project. The business analyst needs a capability that will help ensure that the product conforms to approved requirements, changes can be documented, and the status of each change can be

reported.

What should the business analyst use?

Options:

A.

Configuration management system

B Work breakdown structure

B.

Traceability matrix

C.

Context models

Buy Now
Questions 28

A business analyst is working on a highly complex project and has elicited a large number of requirements from stakeholders in several departments. Due to the large number of requirements, the stakeholders have determined that they would like to prioritize them to minimize a potentially large scope.

Which technique could the business analyst use to manage requirements?

Options:

A.

MoSCoW

B.

SMART goals

C.

RACI models

D.

Storyboarding

Buy Now
Questions 29

A document is being created that will detail the customer's needs for a product and will include a functional model, a data model, and a glossary of terms. This document is called a:

Options:

A.

standard operating manual.

B.

business case.

C.

project charter.

D.

requirements specification.

Buy Now
Questions 30

Which tool provides combined functionality for business analysis and quality assurance activities?

Options:

A.

Functional specification tool

B.

Requirements traceability tool

C.

System use case modeling tool

D.

Solution quality assurance tool

Buy Now
Questions 31

A business analyst is preparing a requirements management plan and needs to define a method to deal with a complex project with stakeholders who find it difficult to articulate their needs. Which method would best minimize requirements risk?

Options:

A.

Questionnaires

B.

Group decision making

C.

Stakeholder analysis

D.

Prototyping

Buy Now
Questions 32

The customer and the business analyst are collaborating in the development of a solution scope. It is important for the customer to:

Options:

A.

communicate changes to requirements only when they are completely defined.

B.

spend the time required to provide, clarify, and elaborate requirements.

C.

challenge assessments of the cost and feasibility of requirements.

D.

perform an alternatives analysis for requirements implementation.

Buy Now
Questions 33

The software developers have delivered a completed solution. The quality assurance team has passed the solution. What should the business analyst do next?

Options:

A.

Evaluate the solution against the project charter.

B.

Conduct user acceptance testing.

C.

Evaluate the solution with the sponsor(s).

D.

Conduct performance testing.

Buy Now
Questions 34

A business analyst needs to estimate the effort associated with project requirements. However, the lack of detail is concerning.

What technique could the business analyst use to help alleviate this concern?

Options:

A.

Decomposition model

B.

Context diagram

C.

Swimlane diagram

D.

Business analysis work plan

Buy Now
Questions 35

A new project is in the planning phase. The business owner believes that, since the timeline is aggressive, requirements elicitation should begin as soon as possible.

Which activity should the business analyst initiate before beginning requirements elicitation?

Options:

A.

Prepare the requirements traceability matrix.

B.

Define how the solution will be evaluated.

C.

Draft a high-level data model.

D.

Document how the relevant systems interact.

Buy Now
Questions 36

The project team is working on the requirements specifications for a new product. The team reached a decision on which requirements will be included in the next release. A third of the stakeholders endorse one approach while no other approach achieved more than a quarter of the vote.

Which decision role was used?

Options:

A.

Majority

B.

Plurality

C.

Consensus

D.

Unanimity

Buy Now
Questions 37

A business analyst is working on a project to implement a new call management system for a help desk. They expected the average time interval to answer a call to decrease over time, but the interval has increased instead.

Which technique should the business analyst use to investigate the problem?

Options:

A.

Interviews

B.

Root cause analysis

C.

Observation

D.

Process modeling

Buy Now
Questions 38

What can a business analyst use to track requirements documentation?

Options:

A.

Affinity diagram

B.

Data dictionary

C.

Business rules matrix

D.

Version control system

Buy Now
Questions 39

During the initial phase of a project, which technique could assist in identifying and categorizing the stakeholders?

Options:

A.

Business activity model

B.

RAC! matrix

C.

Power/interest grid

D.

Organization modeling

Buy Now
Questions 40

A new business analyst has taken over on a project that is in the development phase. The project manager is looking for an update on requirements status.

What should the business analyst use to help communicate the status?

Options:

A.

Project charter

B.

Communication plan

C.

Business analysis plan

D.

Traceability matrix

Buy Now
Questions 41

A system enhancement project has been initiated to address the concerns of an external group of stakeholders not included in the first release. What should be done to ensure stakeholder satisfaction with the enhancement?

Options:

A.

Request that the project manager identify all affected project stakeholders.

B.

Provide all signed-off project documentation to the stakeholders for information purposes only.

C.

Engage all stakeholders early in the requirements gathering phase to define acceptance criteria.

D.

Solicit feedback and add requirements to the project backlog.

Buy Now
Questions 42

A company uses a prioritization range of 1-10, in which 10 represents the highest or best. According to the information from the table, which option should the business analyst recommend?

Options:

A.

1

B.

2

C.

3

D.

4

Buy Now
Questions 43

The human resources, engineering, and marketing departments have provided feedback on the business needs for a new product. After analyzing the feedback from the three departments, it would be best to:

Options:

A.

vote on the product's highest-value business needs.

B.

negotiate to best meet each department's objectives.

C.

collaborate on a product scope that aligns with the company’s objectives.

D.

delegate the decision to be made by the product sponsor.

Buy Now
Questions 44

The business analysts have concluded a requirements elicitation workshop. They now need to define rationale for each requirement.

Which of the following pairs of items would be important to include in the rationale?

Options:

A.

Reasons and assumptions

B.

Product vision and operational relationships

C.

Stakeholder impact and design decisions

D.

Functional relationships and work breakdown structure code

Buy Now
Questions 45

A project affects the marketing unit and procurement unit. The project manager gives the business analyst an overview of the project for the first time.

What should the business analyst do immediately after the discussion?

Options:

A.

Schedule time with the process owners.

B.

Put the information into a project plan.

C.

Develop an issues log.

D.

Assess the risks for the project.

Buy Now
Questions 46

A business analyst has elicited, documented, and verified the requirements, discovering that there are not enough resources to deliver all the requirements. Which technique should the business analyst employ to rectify the issue?

Options:

A.

Hold a brainstorming workshop to build the rationale for the requirements.

B.

Perform traceability to find out where the requirements originated.

C.

Survey stakeholders on their likes and dislikes about the requirements.

D.

Ask stakeholders to vote on the requirements.

Buy Now
Questions 47

Which technique or tool is used to obtain acceptance of the delivered product?

Options:

A.

Expert judgment

B.

Facilitated workshops

C.

Inspection

D.

Contextual inquiry

Buy Now
Questions 48

The business analyst generated a design specification for a new product. What is the best type of formal review to conduct with the customer to establish an approved requirements baseline?

Options:

A.

Test readiness review

B.

Production readiness review

C.

System requirements review

D.

Critical design review

Buy Now
Questions 49

What should the business analyst do to ensure that all requirements meet a quality checklist before the development and testing phase?

Options:

A.

Validate the requirements deemed important by the stakeholders.

B.

B. Obtain approval from engineering for partial testing of the requirements.

C.

Negotiate with the client to standardize the requirements.

D.

Assign a verification method to each requirement.

Buy Now
Questions 50

A company is developing a new product for a customer and is required to verify and validate the product against the customer's acceptance test plan and requirements. The product was successfully verified against the acceptance test criteria, but the customer

does not believe that the product meets the requirements.

This occurred because the customer's acceptance test plan:

Options:

A.

was not included in the work breakdown structure.

B.

did not have measurable and testable requirements.

C.

was not formally accepted by the company.

D.

was incomplete and missing requirements.

Buy Now
Questions 51

When modeling processes or analyzing tasks, business rules can be uncovered by asking about:

Options:

A.

tasks that overlap with each other.

B.

work that may be performed out of sequence.

C.

reasons for choosing a particular course of action.

D.

task transitions that hinder organizational performance.

Buy Now
Questions 52

A business analyst is reviewing a discrepancy report after a test session. The discrepancy report has revealed a defect that the business analyst must address.

Which of the following criteria should the business analyst use to identify the appropriate response to the defective test result?

Options:

A.

Inspect the requirements traceability matrix to verify if the requirement is connected to a use case.

B.

Determine if the defect is in the solution developed, in the original requirement, or in the test case.

C.

Verify that the corresponding requirement was appropriately signed off by the requesting stakeholder.

D.

Perform an impact analysis and open a change request to include the revised requirement in the next baseline.

Buy Now
Questions 53

After reviewing a business case, project goals, and objectives, a business analyst determines that the organization prefers taking an exploratory approach to finding the solution that best meets the business need. Which approach best aligns with the business need for this organization?

Options:

A.

Plan-driven approach

B.

Waterfall approach

C.

Analytical approach

D.

Change-driven approach

Buy Now
Questions 54

The document that defines the process for managing requirements revisions is the:

Options:

A.

project management plan.

B.

change management plan.

C.

communications management plan.

D.

scope management plan.

Buy Now
Questions 55

After implementation of the product, the customer reports defects. What is the best course of action to take?

Options:

A.

Compare reported defects with user acceptance test results.

B.

Escalate the issue to the project manager since the acceptance was given by the customer.

C.

Do nothing since the solution is now the responsibility of the operations manager.

D.

Involve the end users and plan a new round of acceptance tests to check the gaps.

Buy Now
Questions 56

After completing the requirements, the project manager and business analyst realize that the project scope is not feasible in the projected schedule. The business analyst needs to review the amount of work the team is capable of delivering based on the approved project schedule.

Which prioritization technique should the business analyst use?

Options:

A.

Time-boxing

B.

SWOT analysis

C.

Weighted ranking

D.

Multivoting

Buy Now
Questions 57

When a change request is received, the business analyst is responsible for:

Options:

A.

analyzing the impact to the project schedule and budget.

B.

ensuring that change-related incidents are minimized in production.

C.

analyzing the impact on business and underlying systems.

D.

prioritizing and scheduling the changes requested.

Buy Now
Questions 58

The quality function deployment is best suited to assist in the process of:

Options:

A.

relating the product features to customer value.

B.

quality control by determining the control charts and the run charts.

C.

quality assurance by structuring the quality audits.

D.

controlling the effects between the quality functions.

Buy Now
Questions 59

A business analyst for Company A has been assigned to a three-year project to assist health insurance Company B with implementing and testing a new set of medical codes. The business analyst has identified many stakeholders who will participate in the project. For example, Company A will designate technical staff to write and code the requirements and provide a testing team to test the new

functionality. The senior director of Company B will require weekly progress updates. The project manager from Company A will create

project plans, schedule meetings, and provide meeting minutes.

In the scenario above, what is the role of the technical staff and testing team from Company A?

Options:

A.

Accountable

B.

Consult

C.

Responsible

D.

Inform

Buy Now
Questions 60

Last year, a company registered a high number of complaints about its customer service. Which of the following tools or techniques can help to identify the high-priority changes needed to improve that service?

Options:

A.

A work breakdown structure analysis of the service

B.

A Pareto analysis

C.

A flowchart of the service

D.

A cause-and-effect diagram

Buy Now
Exam Code: PMI-PBA
Exam Name: PMI Professional in Business Analysis
Last Update: Dec 21, 2024
Questions: 200

PDF + Testing Engine

$249

Testing Engine

$225

PDF (Q&A)

$199