Pre-Summer Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: netbudy65

PMI-ACP PMI Agile Certified Practitioner (PMI-ACP) Questions and Answers

Questions 4

A member of the development team displays disrespectful behavior and continuously argues with colleagues. This is negatively impacting team morale.

Which action should the scrum master take to resolve this situation?

Options:

A.

Mitigate the new conflicts that appear and rely on the self-organization of the team.

B.

Escalate the issue to senior management to make a decision.

C.

Follow the organization's policies to remove the team member to boost team engagement.

D.

Attend daily coordination meetings and retrospectives with the agile coach.

Buy Now
Questions 5

Based on the backlog metrics in the chart what can explain the jump in points at the end of iteration 4?

Options:

A.

The team neglected to account for support and maintenance costs associated with other supported products

B.

The team discovered that previously accepted work could be greatly improved and added story points associated with thatwork.

C.

The team realized that some stories were underestimated relative to other stories and reestimated as needed

D.

The team learned that the product owner needed to increase the output in the next release

Buy Now
Questions 6

Why should an agile coach model agile principles and behaviors, become self-aware, and be present?

Options:

A.

To better listen, serve and help the team grow their strengths individually and as a team

B.

To convince people what they need to do

C.

To help better disguise the command and control approach

D.

To understand team dynamics and develop a high performing team

Buy Now
Questions 7

Following an upgrade, a software support team is overwhelmed by the number of tickets being submitted by end users. The team's manager is pushing the team to "work smart" by focusing on activities that deliver the most value in the least amount of time.

What should the team do?

Options:

A.

Work longer hours to complete more of the support backlog.

B.

Work support tickets in the order in which they were received.

C.

Place tickets on hold until the team completes an analysis of the backlog to identify and resolve systemic issues.

D.

Add members to the support team.

Buy Now
Questions 8

An experienced product owner presents the epics and corresponding stones during a release planning session with the established team. The executive sponsor asks the team when the features will be delivered.

What should the agile team do?

Options:

A.

Evaluate how much can be delivered based on the Scrum Master's estimation

B.

Identify a set of user stones based on the team's velocity

C.

Initiate an estimation session

D.

Consult historical data for project completion

Buy Now
Questions 9

While struggling to take ownership of delivery an agile team fails to keep up with its sprint commitments What should the agile coach do?

Options:

A.

Work with the sponsor to develop team expectations

B.

Provide the customer with a list of deliverables and obtain agreement

C.

Encourage the team to more frequently interact with all stakeholders

D.

Work on finishing upfront product design rather than comprehensive documentation

Buy Now
Questions 10

A Scrum Master would like to provide information to key stakeholders on the daily resource and project activities. Which tool should the Scrum Master use to provide these updates?

Options:

A.

Shared vision statement and sprint goal

B.

Release burnup chart

C.

Velocity metrics

D.

Iteration burndown chart

Buy Now
Questions 11

Several new stakeholders are concerned about being asked to review a product demo before it is complete. How should the agile coach explain to the stakeholders the value of working this way?

Options:

A.

The product owner may act as the stakeholders' proxy at the demo and that the stakeholders do not need to be directly involved with the team.

B.

The demo will show whether or not the team understands the level of effort required to complete the project.

C.

The stakeholders will learn whether or not the implementation has worked by getting immediate feedback so they can correct their assumptions for the next sprint.

D.

The stakeholders will be better positioned to evaluate whether or not the resources expended by the organization are worthwhile.

Buy Now
Questions 12

An agile coach is working with a team that serves clients making product requests by phone. During a daily commitment and replanning meeting, a team member states that they were unable to resolve a client request because they lacked sufficient product knowledge.

What should the agile coach do?

Options:

A.

Facilitate a team discussion to identify knowledge gaps and determine the best way to address them.

B.

Ask the line manager to assign the team member with the required technical knowledge.

C.

Meet with the team member's line manager to discuss their development plan.

D.

Provide the team member with training in any lacking areas.

Buy Now
Questions 13

An e-commerce company acquired a tool to customize subject line generation for marketing campaigns. In sprint planning, the team discussed integrating this tool with the customer relationship management system.

Which mitigation strategy is most appropriate to ensure the final product meets the business objectives? (Refer to the Risk Register Exhibit)

Options:

A.

Conduct thorough requirements analysis and validation.

B.

Allocate experienced developers and perform code reviews.

C.

Plan for sufficient support resources post-deployment.

D.

Develop comprehensive testing involving the quality assurance team.

Buy Now
Questions 14

A project manager is working on a user story about migrating to a new version of a database but is unsure of the dependencies. What can the product owner request from the team to understand the risks?

Options:

A.

Refinement meeting

B.

Daily standup meetings

C.

Retrospective

D.

Spike

Buy Now
Questions 15

A software project is being implemented by a small, colocated team. What should the project manager do to keep the team focused and engaged with the high level of requirements?

Options:

A.

Arrange afternoon touchpoints where the team can discuss what they have done during the day

B.

Request that the project sponsor is present during daily standugs to increase commitment from the team.

C.

Send out daily activity tasks to each member of the team, mitigating the risk of tasks being forgotten.

D.

Make use of a kanban board so that the team will have a clear view of the work in progress (WIP) for the release.

Buy Now
Questions 16

A business analyst has been assigned to optimize a process to deliver healthcare services to patients in a clinic. In creating a value stream map, what will the business analyst’s key observations include?

Options:

A.

Process breakdowns and workflow

B.

Wait times and cycle times

C.

Process maps and story points

D.

Activity sequences and earned value (EV)

Buy Now
Questions 17

A development team is working on the implementation of a human resources (HR) solution. The team has decided to work together with different business units to deliver value early and often.

Which agile values are being practiced in this scenario?

Options:

A.

The importance of customer-centric product development practices over product-centric approaches.

B.

Deliver working software often with a preference for shorter timescales and changing requirements

C.

The belief that contributions and interactions are more important to success than processes and tools.

D.

The best architectures, requirements, and designs emerge from self-organizing teams.

Buy Now
Questions 18

After seeing the planned features (or an upcoming release, a customer notes that a vitally important and complex one is missing. The team estimates that this feature significantly exceeds its average velocity. How can this issue be resolved?

Options:

A.

Break down the feature into smaller parts, and commit to completing the minimum viable product.

B.

Complete the iteration to which they have already committed, and include the feature in the next release.

C.

Change the planned features lo include only the vitally important one.

D.

Extend the iteration to complete the feature.

Buy Now
Questions 19

An agile leader notices that a team member is becoming very quiet and disengaged in meetings. What should the agile leader do to identify team members' personalities and motivators?

Options:

A.

Use the DISC framework with each team member.

B.

Use MoSCoW ratings to keep people engaged.

C.

Hire a SAFe coach to provide encouragement.0 Employ BDUF to help with providing structure to meetings

Buy Now
Questions 20

What should a team do when they complete all sprint goals earlier than expected?

Options:

A.

Begin working on an item in the backlog

B.

Ask the scrum master to select an item from the backlog on which to work

C.

Ask the product owner to select an item from the backlog on which to work

D.

Jointly decide with the scrum master on an item from the backlog on which to work

Buy Now
Questions 21

An agile project manager notices that the product owner manages team members' day-to-day tasks in a way that distracts them from their core responsibilities. In addition, the team believes that their questions on product backlog prioritization are not being answered on time.

What should the agile project manager do?

Options:

A.

Discuss and address this in the iteration retrospective.

B.

Let the product owner know it is the project manager's responsibility to drive a team's tasks.

C.

Discuss the roles and responsibilities of the project team with the product owner

D.

Ask the product owner to work extra hours to answer the team's questions

Buy Now
Questions 22

An agile coach is facing a dilemma: On one hand, there is a requirement that is vital and will consume all capacity of the team. On the other hand, there are some chore-related tasks that will improve the team's ability to produce results. The team insists on implementing these tasks since they will increase efficiency.

What should the agile coach do?

Options:

A.

Characterize chores as low priority since they do not add obvious value to the product

B.

Delegate chore-related tasks to another team.

C.

Escalate the issue to the shareholders/steering committee.

D.

Get the product owner and team to meet to prioritize the work.

Buy Now
Questions 23

On what should an agile team work to achieve predictable flow?

Options:

A.

Small user stories

B.

Simple acceptance criteria

C.

Lean features

D.

Lean backlogs

Buy Now
Questions 24

A team member on a new scrum project previously provided support to another application Due to issues with that application, the team member's former supervisor continues assigning them tasks related to that project. The new project's scrum master includes this issue in the risk register.

What should the scrum master do next?

Options:

A.

Monitor the threats and risks while allowing the team member to multitask on both projects

B.

Assign more resources to the sprints to compensate for the absences of the team member

C.

Ensure that the threats and risks are communicated and addressed

D.

Assign fewer stories to the sprints so that the team member can still meet sprint goals

Buy Now
Questions 25

An agile team is working on a new product. To ensure that all unknown issues are clarified before committing to the scope the team plans to work only on spike user stories for the next three sprints

What should the agile coach do in this situation?

Options:

A.

Ensure that the spikes identify the risks early in the project to increase the chances of success

B.

Ensure that the business sponsor accepts the proposal and agrees to fund the additional spike sprints.

C.

Recommend that, in the first sprint, user stories with higher priority be executed in addition to the spike

D.

Support the decision because release planning will be improved, and the product backlog can be better groomed after allspikes are executed

Buy Now
Questions 26

During the retrospective meeting, it is revealed that an external dependency is causing a reoccurring impact. The impact is that an external team is not providing a fix or a stable testing environment. The scrum master has been unable to resolve this after escalating the situation to upper management several times.

What should the scrum master do now?

Options:

A.

Guide the development team to accept and adapt to the existing situation by finding sustainable workarounds.

B.

Assure that the development team plans the scope of work with this risk absorbed in the estimation.

C.

Establish a communications channel with the external team and monitor the implementation of the external task.

D.

Collect empirical data and influence upper management to be accountable for end-to-end. cross-team delivery.

Buy Now
Questions 27

An agile team is unable to complete all its planned sprint user stories, which results in a decrease of its planned sprint velocity. What should the team do?

Options:

A.

Re-estimate the sprint's completed stories to increase and adjust the sprint's velocity.

B.

Increase the duration of the next sprint to accommodate the incomplete user stories and maintain velocity.

C.

Work with the product owner to create a spike with another agile team.

D.

Re-estimate the incomplete stories for the next sprint because its relative size has changed.

Buy Now
Questions 28

A product owner with experience in a predictive approach wants the team to develop very detailed schedules and cost estimates for the next 10 sprints. What should the Scrum Master do?

Options:

A.

Suggest the product owner start by focusing on the next 2 sprints instead of 10

B.

Spend the first few sprints to develop detailed schedules and budgets

C.

Invite the product owner to the retrospective to explain the team's approach to schedule and budget

D.

Explain that detailed project schedules and budgets are not artifacts in agile projects

Buy Now
Questions 29

During a retrospective, team members suggest process improvement ideas. The agile team lead knows that, while many of these ideas are different from standard practices, a few of them are good. What should the agile team lead do?

Options:

A.

Require the team to try only those ideas that will ensure success.

B.

Allow the team to try ideas, but remind them that results will be reviewed by high-ranking executives.

C.

Associate idea successes and failures with the team's incentive plan to ensure accountability.

D.

Encourage the team to try the ideas, even if failure may be the outcome.

Buy Now
Questions 30

Roadmaps are defined as covering a rolling 12 months. When creating a product roadmap in an agile environment, what factor should the agile lead take into consideration?

Options:

A.

Just-in-time (JIT) refinement

B.

Stories to be released in each sprint

C.

Infrastructure updates

D.

Funding decisions

Buy Now
Questions 31

An agile project has three more iterations before the release. There is a lot of report functionality to be created and defects to be cleared. During a daily scrum, a team member suggests a timebox spike to find a more efficient way to deliver reports.

What should the project leader do?

Options:

A.

Encourage the team to self-organize and determine how to best complete their existing work and this spike.

B.

Encourage the team to complete their just existing work since the team velocity indicates they are already struggling to meet the release goal.

C.

Direct the team to defer the spike until the next release and add the action on the backlog for prioritization.

D.

Direct the team to work on the spike immediately given the importance of reporting functionality to complete the iteration.

Buy Now
Questions 32

An agile project team has team members with varying technical skills. Due to recent events that adversely impacted customer satisfaction, management mandated that Kaizen should be given more focus to ensure the quality in product delivery.

Kaizen is a prime concept of which agile practices?

Options:

A.

Standup meetings. Extreme Programming (XP), relative estimating

B.

Build quality in, visualize workflow, fail fast

C.

Standup meetings, retrospective meetings, continuous improvement

D.

Collaborate, regular builds, inspections

Buy Now
Questions 33

The team is working to build a new Al model that will summarize and create presentation materials for executive leaders from external and internal content. The team believes there is value in increasing the scope of work as it will benefit the organization.

Which two actions should the product owner take first? (Choose two.)

Options:

A.

Determine the cost and resource requirements.

B.

Create a spike to determine the dependencies.

C.

Create a change request to formalize the requirements.

D.

Seek executive approval on the approach.

E.

Determine the purpose and value proposition on the approach.

Buy Now
Questions 34

During its first sprint, a new scrum team realizes that it has insufficient team members with test automation skills to effectively complete its stories. What should the team do?

Options:

A.

Cross-train some members in the automation framework to broaden their capacity with that skill

B.

Ask the product owner to add team members to boost this particular skill set

C.

Send a member to automation framework training when funds are available

D.

Avoid using test automation by swarming on the testing tasks and using manual testing

Buy Now
Questions 35

The team is considering committing to 44 story points for the upcoming sprint. Based on the

velocity chart, what advice should the scrum master offer the team?

Options:

A.

Reduce the commitment to 40 story points to ensure a higher chance of meeting the commitment.

B.

Maintain a commitment of 46 story points, representing the most frequently completed velocity.

C.

Increase the commitment to 48 story points to push the team toward higher performance.

D.

Commit to 44 story points as it aligns with the team's average velocity for completed story points.

Buy Now
Questions 36

Midway through a two-week sprint, an agile team realizes that the features cannot be delivered within the sprint. The team determines that another week will be required to complete all committed features.

What should the team do?

Options:

A.

Plan for overtime, and include the effort as part of the estimation.

B.

Increase team velocity to deliver more story points.

C.

Identify the reason for over-commitment to the sprint and create an action plan for the following sprint.

D.

Add resources to assist with sprint execution.

Buy Now
Questions 37

Trend analysis shows that velocity is significantly higher than predicted and the release can be completed one month ahead of schedule. The team recommends changing the end date to reflect this.

What should the agile practitioner do?

Options:

A.

Jointly meet with the team and product owner to discuss options and determine the end date

B.

Announce that the team has exceeded the predicted velocity and that the end date will be earlier than planned

C.

Ask the product owner to include additional features in the product backlog, then replan subsequent iterations

D.

Ask the team to decrease velocity to meet contractual obligations and document this decision

Buy Now
Questions 38

A customer has difficulty explaining how the highest priority feature will work. What should the agile project manager do?

Options:

A.

Create a time-boxed spike story to reduce the technical risk of the feature.

B.

Commence an iteration 0 for the customer and the team to investigate the feature.

C.

Facilitate the decomposition of the feature epic into more manageable user stories.

D.

Facilitate a just-in-time exploration of the functionality by the customer and the team.

Buy Now
Questions 39

A project's product owner asks the scrum master to facilitate the estimation activity. The scrum master then meets with the team and the product owner to clarify the user stories. Following the meeting, the team assembles and provides individual user-story estimates.

What technique did the team use?

Options:

A.

Lessons learned

B.

Wideband Delphi

C.

Formal point counting

D.

Planning poker

Buy Now
Questions 40

A servant leader is leading a high-visibility project to deliver a new product. The servant leader has been able to build a cross-functional team and create a team space where the team is collocated. The servant leader started receiving frequent visits from a company director, who continually asks a specific team member questions about project progress. The conversations are distracting the team from their goal.

What should the servant leader do?

Options:

A.

Coach the company director on agile approaches and good practices.

B.

Ask the product owner to speak to the director because their visits are delaying the project.

C.

Ask the director and team member to leave the room so they can have a private conversation.

D.

Coach the team member on how to report progress to directors and executives.

Buy Now
Questions 41

An organization strives hard to accelerate value delivery by improving product design, development, and transition activities. What ways of working should the organization discontinue to become an effective player?

Options:

A.

Leverage continuous feedback from customers to seamlessly align delivery with requirements.

B.

Define software functionality by relying on the developers' experience designing similar system

C.

Engage end users in user acceptance testing to ensure the product meets their expectations.

D.

Educate end users and other stakeholders to understand desired outcomes through user stories.

Buy Now
Questions 42

The transition of a monthly news publication from paper to digital is planned to start in the next few weeks. There is a debate between the product owner and the development team about the initial features to be made available and the first five stages of implementation.

What should the scrum master do to address this situation?

Options:

A.

Request more clarification from the client relations team.

B.

Ask the team to define the minimum marketable feature

C.

Tell the team to proceed with coding the items as currently defined.

D.

Encourage open discussions to help the team reach agreement

Buy Now
Questions 43

In a scrum team, who should be responsible for the budget and release plans?

Options:

A.

The scrum master assigns someone on the team to handle the budget, and the product owner is responsible for release plans

B.

The finance department is responsible for budget, and the product owner is responsible for release plans

C.

The scrum team as a whole, as they are self-organizing and share accountability

D.

The product owner is responsible for both the budget and the release plans

Buy Now
Questions 44

A new agile team member notices that the team's current process involves excessive documentation. What should the new team member do?

Options:

A.

Teach the team the appropriate agile principle, obtain consensus, and drive adoption.

B.

Allow another team member to prepare those documents that do not appear to bring value.

C.

Notify the project manager about other documentation techniques, and identify which documents bring value and which do not.

D.

Follow the existing process to avoid conflicts.

Buy Now
Questions 45

A new agile project manager accepts an assignment to manage a well-established team Many team members have worked together on this product for several years During a meeting, the project manager notices that team members offer little vocal interaction, yet all required tasks are completed on time

What type of behavior does this describe?

Options:

A.

Synchronous

B.

Collaborative

C.

Passive-aggressive

D.

Random

Buy Now
Questions 46

A team is transitioning from a predictive approach to an agile approach Historically, the team has delivered work products that did not meet customer expectations.

What agile practice can help the team to alleviate this?

Options:

A.

Test-driven development (TDD)

B.

Clear definition of done and regular demos

C.

Collaborative team planning games

D.

Consistent team velocity

Buy Now
Questions 47

To create the project vision, an agile team has scheduled an initial meeting with their customer representative. What should the team bring to this meeting?

Options:

A.

A list of templates to be used to create the project vision

B.

A list of project stakeholders and user stories

C.

A checklist for future acceptance tests for project deliverables

D.

A list of questions for the team and customer representative

Buy Now
Questions 48

DRAG DROP

All the developers on a project team are working offshore in a different time zone, resulting in many issues. Match the issues to the agile practitioner's recommendations for resolutions below. (Drag the Problems/Issues on the left to the box in the center, corresponding to the correct Recommendations for Resolution on the right)

Options:

Buy Now
Questions 49

An agile team identifies that their velocity is lower than predicted, and that their previous forecasts in the product roadmap are wrong. The team is worried that they will be unable to meet a critical release date without corrective action.

What should the team do?

Options:

A.

Collaborate with the product owner to reprioritize the product backlog, thus ensuring that more features will be completed before the release.

B.

Ask the team lead to calculate the team's target velocity according to the project plan, and assign additional resources to increase capacity.

C.

Focus on velocity and schedule concerns during the retrospective to inspect, adapt, and improve the process and plans.

D.

Reestimate the backlog items from the release, ensuring that contingency is included to set stakeholder expectations.

Buy Now
Questions 50

A scrum master is working with a team on a complex software project that is scheduled to run for 2 years with a series of product releases. The scrum master is responsible for planning the project for the next 6 months and has advised planning the project up front.

What should the scrum master do?

Options:

A.

Add the releases into a roadmap with milestones and activities.

B.

Identity dedicated tasks and activities with regular feedback loops.

C.

Deliver in small and continuous iterative releases.

D.

Identify the requirements' schedule within set time scales.

Buy Now
Questions 51

An agile practitioner is working on a project to migrate data from computer systems to another location. To accomplish this task, they need to run four activities sequentially that different teams are performing. The teams are migrating two systems per day, but the agile practitioner thinks that three systems should be done per day.

What can be done to improve process efficiency?

Options:

A.

Use burndown charts to find gaps. delays, and constraints in the current process and develop a plan to reduce or remove them.

B.

Use value stream mapping to find gaps, delays, and constraints in the current process and develop a plan to reduce or remove them.

C.

Use Pareto analysis to find gaps, delays, and constraints in the current process and develop a plan to reduce or remove them.

D.

Use root cause analysis to find gaps, delays, and constraints in the current process and develop a plan to reduce or remove them.

Buy Now
Questions 52

An agile team's client has been asked to expedite the delivery of the next release. By delivering one month early, the company can generate USS40.000 more than expected for the quarter. What should the agile team do?

Options:

A.

Adhere to the new deadline and immediately advise the client that the schedule has been expedited.

B.

Advise the client that it is best to continue as planned rather than introduce unforeseen risks by expediting the schedule.

C.

Submit a change request to the client with a 50% increase in charges due to the new potential profit.

D.

Request additional resources to meet the expedited deadline and obtain training for the new resources.

Buy Now
Questions 53

When introducing agile processes to a company, a quality assurance (QA) manager resists and believes that the switch to agile will remove quality controls and documents How should the agile practitioner address this concern?

Options:

A.

Educate the QA manager that in agile quality is integrated from the beginning to end of the project

B.

Write backlog items that include QA as part of the description

C.

Ask for the current QA documents and incorporate them into the technical debt backlog

D.

Ask the product owner to write tests and QA controls into the acceptance criteria

Buy Now
Questions 54

A project is starting and the type of work is complex and suitable for agile in assessing the team members, it appears that co-location would be a challenge.

What should the agile practitioner do?

Options:

A.

Select and implement collaboration tools to augment team interactions

B.

Provide each geographical area with their own product owner and divide the work between the teams

C.

Increase the number of requirements documents and ensure they are clearly communicated

D.

After several sprints, calculate velocity based on primary team location and use secondary team as reserve

Buy Now
Questions 55

In a project to develop a supply-and-demand scenario planning tool, the team aims to streamline development and rapidly deliver features. Which approach best supports quick feature delivery while maintaining quality? (Refer to An Excerpt from the Quality Management Plan)

Options:

A.

Implementing a systematic approach to automate integration, testing, and deployment activities

B.

Increasing the frequency of stakeholder meetings to gather feedback on feature priorities

C.

Leveraging regular reviews, feedback loops, and lessons learned to adjust at key milestones

D.

Organizing training sessions for end users to ensure effective utilization of the planning tool

Buy Now
Questions 56

While working on a sprint for a software development project, the team is unsure of how the feature should be designed. The project sponsor recommends developing a prototype of the user interface to discover more about this feature.

Why is the project sponsor making this suggestion?

Options:

A.

The information gathered will help the team improve the allocation of resources in developing the most important features.

B.

The project sponsor believes that the agile team is not adding in the most important features during this sprint.

C.

The users can help the team understand if the feature adds value, avoiding the risk of building the wrong product.

D.

The users will start using the software sooner, and the team can start working on the next iteration.

Buy Now
Questions 57

The lead developer informed the team that they have learned of some possible integration challenges in creating customer dashboards using the architecture the team has chosen. What should an agile practitioner do?

Options:

A.

Conduct an architectural spike immediately to decide how the functionality will be determined.

B.

Work with the product owner to avoid the risk by determining if their requirements could be met with reporting or a similar functionality.

C.

Continue the priority defined by the product owner on the backlog for the functionality they determined to be the highest priority.

D.

Identify this as a risk, decide on the response, and prioritize spike to determine the solution on the product backlog.

Buy Now
Questions 58

A project manager noticed that a team member had been a consistently high performer until a few months ago. Recently, the team member seems distracted and is not performing well.

How should the project manager handle a review with the team member?

Options:

A.

Talk to the team member about project deliverables and how poor performance is unacceptable.

B.

Discuss performance with the team member on the project deliverables and provide constructive feedback.C Inform the learn member that this project is complex and consider moving them to another project

C.

Extend support to the team member as this is the first project in which the team member underperformed.

Buy Now
Questions 59

A development team, new to scrum, questions the need to collect metrics on team performance. While learn members understand velocity and burn down, they feel that once velocity becomes settled it is needless to keep track.

What should the agile coach tell the team?

Options:

A.

Continuing to track velocity allows functional managers to assess whether or not the team is performing at the desired rate.

B.

The trends will show how the team performs against other scrum teams in the organization.

C.

Tracking velocity will provide a baseline for the team to see how their continuous improvement efforts are working.

D.

Tracking velocity will document and communicate team health to the stakeholders.

Buy Now
Questions 60

A team member has spent 5 days on a spike and the first set of experiments has not been successful. The issue is the development team member has determined a short-term rather than a long-term solution.

What should the project leader do?

Options:

A.

Assign the spike to another resource to continue research for the long-term solution

B.

Re-establish the spike; encourage experimentation and collaborate with the team

C.

Stop experimentation and negotiate the short-term solution with the customer

D.

Schedule a root-cause analysis with the development team on the main issues with the spike

Buy Now
Questions 61

As part of the organizational change, all project teams within the digital channel’s portfolio have been directed to move from 3-week iterations to 2-week iterations. The development team is frustrated as they think there will not be enough time to test. The product owner does not like this change as it will increase the number of ceremonies.

Which two actions should the scrum master take? (Choose two.)

Options:

A.

Proactively engage the resource managers to lead the team and provide the required support.

B.

Request the enterprise coach and human resources support the team with the transition.

C.

Document the pros and cons and review with stakeholders to determine the dependencies.

D.

Protect the team from disruptions and seek an exemption for status quo.

E.

Assess the impacts of the change and brainstorm potential solutions.

Buy Now
Questions 62

A scrum team has conducted regular retrospectives to discuss immediate concerns and the implementation of improvement actions. Despite this, after a few iterations, the same concerns resurface. What should the team have done to improve retrospective outcomes?

Options:

A.

Invited subject matter experts (SMEs)

B.

Conducted problem detection to determine root causes

C.

Measured and reported the outcome of improvement actions to the team

D.

Kept track of all current issues in a log. and then reviewed their progress at the end of every iteration

Buy Now
Questions 63

On an agile project, it is important to identify and engage business stakeholders throughout the project and to ensure the team understands the stakeholders' business needs. Which option supports this idea?

Options:

A.

A project charter should be established and reviewed throughout the project life cycle to ensure the accurate documentation of stakeholders' interests and expectations.

B.

A product backlog should be created to list the project requirements from all of the project stakeholders.

C.

An Agile Manifesto should be created to document the project stakeholders, their desired outcomes, and identified risks.

D.

A user story should be created for all key stakeholders to list their individual business objectives and needs.

Buy Now
Questions 64

A development team for a small company experiences long delays between product completion and release for validation and testing. The company is concerned that this will impact its ability to compete in the marketplace

What analysis should the team use to understand the issues?

Options:

A.

Risk management

B.

Variance and trend

C.

Kano model

D.

Fishbone diagram

Buy Now
Questions 65

During an interview for an agile team lead for a global company, a candidate is asked: "How do you ensure your project is aligned with the stakeholders' priorities?"

How should the candidate respond?

Options:

A.

Engage the change management team to determine prioritization of the backlog.

B.

Allow the stakeholders to decide on the priority and build the backlog.

C.

The entire team should discuss and prioritize the backlog factoring in stakeholder input.

D.

Only the agile team lead and team need to decide how to prioritize the project deliverables.

Buy Now
Questions 66

An agile coach has been hired to improve the performance and quality of developed software. The coach performed an analysis of the software and discovered an excessive number of escaped defects, leading to external failures.

How can the agile coach effectively address and correct defects in the software development process while maintaining predictability and keeping workloads within capacity?

Options:

A.

Work with the team to create explicit rules such as coding and quality standards and testing policies.

B.

Discipline the team members and institute status meetings with penalties for any future escaped defects.

C.

Hire more generalized specialists because the current team members cannot keep up with the pace.

D.

Apply work in process (WIP) limits so the developers are not pressured to release code that is problematic.

Buy Now
Questions 67

An agile project manager observes that the Scrum team is falling behind on the completion of a particular sprint. What should the agile project manager do?

Options:

A.

Facilitate by providing directions to the team about how they can get back on track.

B.

Request key stakeholders to extend the sprint to enable the team to complete their tasks on time.

C.

Ask the customers to help the team complete the testing on time to be able to finish their tasks on time.

D.

Understand the impediments and facilitate issue resolution to enable the team to succeed.

Buy Now
Questions 68

At the end of a product development phase, an agile project team confirms that all tests have passed. The product is released, but the customer complains that it is deficient. What should the project team have done prior to product release?

Options:

A.

Requested approval from the project sponsor

B.

Undertaken a review of all requirements

C.

Conducted an end-of-phase demonstration

D.

Performed a retrospective to validate project deliverables

Buy Now
Questions 69

An organization initiates a pilot project to introduce agile methodology for the successful delivery of projects. What should the project manager do to share this project's knowledge and learning with wider organizational business groups?

Options:

A.

Invite people from across the organization to attend daily stand ups

B.

Invite people from across the organization to attend retrospectives

C.

Invite people from across the organization to attend the release meeting and project retrospectives.

D.

Regularly meet with people across the organization to share the project's lessons learned and best practices

Buy Now
Questions 70

HOTSPOT

Organizations that implement agile project management focus on upgrading existing products and services through cost reductions, time savings, or quality enhancements for existing customers (i.e., operational agility). Organizations need to realize that the major financial gains from agile project management will result from the practice of what? (Select answer from dropdown)

Options:

Buy Now
Questions 71

An agile project manager has noticed their teams declining morale, mistrust, and isolation over the last 6 months of working on a project. What should the agile project manager do to enhance productivity and create a cohesive team culture?

Options:

A.

Develop a reward system related to position and years of experience.

B.

Clarify project goals and project contract constraints.C Promote cross-training and —entering among tea— members

C.

Introduce performance standards and evaluation methods.

Buy Now
Questions 72

An agile team discovers a new risk and identifies that its impact may be severe. What should an agile practitioner recommend?

Options:

A.

Add a goal to the current iteration to fully mitigate or control the risk.

B.

Balance risk reduction and value adding activities in the next iteration.

C.

Continue with the current plan to maintain team velocity.

D.

Update the risk register and seek direction from a risk specialist.

Buy Now
Questions 73

An agile project manager is working on a project to develop a customer service website. The project manager is organizing a workshop to plan the next release: To add the feature of receiving and resolving customer complaints. Which two actions should the project manager ask the team members to take before the workshop? (Choose two.)

Options:

A.

Prepare an effort estimation for each story based on their technical expertise.

B.

Compile a list of ideas to improve the velocity of the team so they can plan more story points in the next sprint.

C.

Prepare a list of tasks required to accomplish the goal and the order in which they should be executed.

D.

Read and identify user stories from the backlog that will contribute to accomplishing the goal.

E.

Consider the possible risks of each selected user story and the value they add for the final user.

Buy Now
Questions 74

An agile team is having difficulties in obtaining the participation of a true user to be a part of their team. In the absence of a true user, the development manager steps in to act as a proxy for the user.

What can the agile team do to improve value delivery in the absence of a true user?

Options:

A.

Improve the velocity of each iteration.

B.

Add a variety of skilled programmers and expert testers to the team.

C.

Reduce the length of each iteration.

D.

Add a variety of users, such as business analysts and domain experts, to the team.

Buy Now
Questions 75

An agile practitioner is in the process of refining requirements. The requirements keep changing based upon with whom the agile practitioner speaks.

What should the agile practitioner do in this situation?

Options:

A.

Ask the scrum master to help reduce the rate of change.

B.

Work with the agile coach to document the requirements in a collaborative way.

C.

Work with the stakeholder directly rather than go through different layers of people.

D.

Work with the development team to confirm the requirements.

Buy Now
Questions 76

A scrum master of a team that is new to Scrum wants to share the purpose of the daily coordination meeting. What should the scrum master tell the team?

Options:

A.

The purpose of the daily coordination meeting is for the scrum master to be able to follow up on the sprint plan. The team should explain what may be impeding them from reaching the sprint goal.

B.

According to the Scrum guide, the daily coordination meeting is part of the Scrum framework. The purposes of this meeting are to enable the scrum master to verify the team is on track and to escalate impediments.

C.

The daily coordination meeting is an effective way for the development team to follow up on progress toward the sprint goal and discuss anything that may hinder their work. It is a way to actively manage risks and dependencies.

D.

The daily coordination meeting is held to verify that people are working on the right things. The whole Scrum team should be able to answer these questions: What did I do yesterday, what will I do today, and what can stop me from making progress?

Buy Now
Questions 77

A project team's standups often run over the allotted time as members attempt to resolve issues. With a large team, this is leading to productivity impacts and bringing complaints from some members that the meetings are wasting their time when they are not directly involved in an issue’s resolution.

How can the project leader help to manage the team's time?

Options:

A.

Set up individual status meetings and find ways to make sure issues are resolved in advance so that time is not wasted for all team members during the standups

B.

Add time to the standups to accommodate issue-resolution discussions so that everyone is up to date on the decisions made

C.

Change the standups to weekly status meetings with a longer duration to allow team members to resolve issues collaboratively

D.

Ask team members to raise issues during standups and then discuss resolution options with specific members in separate conversations

Buy Now
Questions 78

Some members of an agile project team work remotely, so it is difficult to have regular face-to-face backlog grooming sessions. How should the agile practitioner ensure that the team is able to reduce miscommunication and rework in this environment?

Options:

A.

Understand the physical and virtual communication needs of the team and plan agile events based on the majority of the team members' needs.

B.

Escalate with senior management and ensure that everyone on the project team is physically colocated for all planned agile events.

C.

Invest in technology-collaboration tools to enable effective communication and ensure a common understanding of the scope, issues, and solutions.

D.

Recognize the different communication styles of the stakeholders and take a vote on the best approach that will work for the team.

Buy Now
Questions 79

A diverse team can sometimes create misunderstandings and conflict, leading team members to isolate. How can an agile project manager promote effective communication and collaboration among team members with diverse backgrounds and perspectives?

Options:

A.

Reduce emotions by emphasizing areas of agreement rather than areas of difference.

B.

Create a shared vision for the team and use techniques to increase empathy and positive interaction.

C.

Coach the team to focus on areas of agreement and the company's profitability.

D.

Confront the team and follow the formal procedures as described in the project management plan.

Buy Now
Questions 80

Midway through an iteration an agile team learns that a team member will be unavailable for the next two iterations. As a high-performance team, what should the team do?

Options:

A.

Raise an impediment that resource tasks will be blocked and notify the product owner

B.

Ask the delivery manager for a temporary resource

C.

Ask the scrum master to assign that team member's tasks to the next available resource

D.

Assume the team member's tasks to meet iteration goals and notify the product owner

Buy Now
Questions 81

A project team is currently working on sprint seven of a release that is estimated to require twelve sprints to complete. The team has reviewed the stories for this sprint and discovered that it will require rework from previous sprints.

What should the scrum master do?

A project team is currently working on sprint seven of a release that is estimated to require twelve sprints to complete. The team has reviewed the stories for this sprint and discovered that it will require rework from previous sprints.

What should the scrum master do?

Options:

A.

Ask the product owner to revisit the scope of the release and revise it so that the team can keep the current commitment schedule.

B.

Ask the team to find a workaround so that they can continue with the current project management plan.

C.

Advise the team to continue working on the sprints as the release plan has been set.

D.

Ask the team to estimate the amount of rework needed so that adjustments can be made to both the project and release plan.

Buy Now
Questions 82

The productivity of an agile team has fallen significantly in the last sprint. The team members have not mentioned any impediments but seem to be fatigued.

What should the agile practitioner do?

Options:

A.

Discuss the issue with the team at the next daily standup meeting.

B.

Discuss the issue with the team at a special meeting for this purpose.

C.

Discuss the issue with the project stakeholders at a special meeting for this purpose.

D.

Discuss the issue with the team at the next project retrospective.

Buy Now
Questions 83

An agile coach is working on a software development project. Their team is approaching the sprint deadline, but their client is requesting to include additional features that will bring added value.

What should the agile coach do to address this requirement?

An agile coach is working on a software development project. Their team is approaching the sprint deadline, but their client is requesting to include additional features that will bring added value.

What should the agile coach do to address this requirement?

Options:

A.

Explain to the client that the sprint deadline is approaching and the feature can be included in the next iteration.

B.

Remind the team and the client of the importance of assessing the risks of these features before deciding to include them

C.

Negotiate with the team to add the additional features in this sprint because they are important requirements.

D.

Ask the client for an extension of the deadline to enable delivery of this sprint with the additional features.

Buy Now
Questions 84

What is the first thing an agile development team should do when planning an iteration?

Options:

A.

Assign the tasks to one team member.

B.

Separate the stories into tasks.

C.

Estimate the stories' tasks.

D.

Help establish the next sprint's goal.

Buy Now
Questions 85

What should the agile practitioner know about tracking velocity?

Options:

A.

A team with an average velocity of 50 is twice as efficient as a team with an average velocity of 25.

B.

A team with an average velocity of 50 is equally as efficient as a team with an average velocity of 25.

C.

A team that consistently meets its planned velocity is more efficient than a team that consistently exceeds its planned velocity.

D.

A team that consistently meets its planned velocity is less efficient than a team that constantly exceeds its planned velocity.

Buy Now
Questions 86

A team lead reviews processes and identifies bottlenecks that prevent the teams from quickly delivering minimum viable products (MVPs). Which responsibility falls within the context of servant leadership?

Options:

A.

Facilitate the team's agile retrospective meeting

B.

Guard the team against external distractions

C.

Escalate points of conflict the team cannot resolve

D.

Identify the sequence for developing stories within an iteration

Buy Now
Questions 87

A product owner feels that the last sprint failed to sufficiently deliver what was valuable to their organization's overall project goals. What should the scrum master mention at the next retrospective?

Options:

A.

Solutions to project problems that were built into the last sprint

B.

Problems that arose

C.

Solutions that saved the organization the most time and money

D.

Problems that were solved

Buy Now
Questions 88

An agile team often fails to deliver its sprint goal. At a sprint retrospective, the more experienced team members complain that the less experienced team members are working too slowly. This creates tension in the team.

What should the scrum master do to remove this tension?

Options:

A.

Ask human resources for a training budget so the less experienced team members can increase their skill level and work more efficiently.

B.

Have an individual meeting with the experienced team members and ask them to be more empathic when the less experienced members tail to deliver.

C Remind the team that they are jointly responsible for their deliverables and should consider the different competency levels when agreeing to sprint goals

C.

Initiate a meeting with the team and ask them to decompose the product backlog items further so they become clearer and easier to deliver on time.

Buy Now
Questions 89

A client states that a product is not being built as requested How should the agile team address this?

Options:

A.

Conduct an internal review to validate functionality before shipping

B.

Audit the quality control process to ensure that the product adheres to requirements

C.

Lengthen iterations to ensure there is sufficient time to build functionality

D.

Hold product review sessions with the client to obtain product acceptance

Buy Now
Questions 90

What is the risk of using agile in a distributed team?

A Frequent integration of work produced

B. Lack of shared knowledge of user stories

C. Need for more locations to learn agile

D. Unclear team structure

Options:

Buy Now
Questions 91

An agile project manager is planning the initial scope, schedule and cost range estimates on a new project. The team will be using Kanban to control work.

What metrics should the team use to measure performance?

Options:

A.

Lead time, throughput and due date performance

B.

Work in progress limits Kanban board, and time boxes

C.

Work item types, sprint cadences, and defect classes

D.

Burndown charts, scatter diagrams, and throughput

Buy Now
Questions 92

A large, corporate organization is forced to hire new team members in a geographically remote location from the current team. The manager of the department is concerned about the team not being colocated.

What behavior would indicate the team is not working well together?

Options:

A.

Team members are sending more emails to the team.

B.

The duration of feedback cycles has increased.

C.

The velocity has increased by having the new team work on items.

D.

New team members requested to move meetings due to time differences.

Buy Now
Questions 93

The amount of information captured in the project's defects is varying within the development team. Team members are becoming frustrated with the defect quality inconsistencies and the frequent clarification required.

What should be done to address the issue?

Options:

A.

Stop the current iteration to discuss defect quality issues and explore solutions.

B.

Discuss and explore solutions in the next planning meeting and take corrective actions as required.

C.

Generate insights at the next retrospective and adjust processes as decided by the team.

D.

Assign corrective actions to the backlog for the team to identify the mandatory defect information.

Buy Now
Questions 94

The vice president (VP) of an organization has been asked by the chief information officer (CIO) to have their teams to embrace an agile approach to projects. The VP, however, often insists teams use a more predictive approach to project management which allows the project managers to do what they like.

How should an agile team member coach the VP and teams be more effective?

Options:

A.

Coach the chief information officer (CIO) on implementation of agile benefits and expectations.

B.

Coach the teams on implementation of agile benefits and expectations.

C.

Coach the managers on implementation of agile benefits and expectations.

D.

ICoach the vice president (VP) on implementation of agile benefits and expectations.

Buy Now
Questions 95

After conducting the second retrospective with project stakeholders, the customer expresses frustration. The customer wants a more predictable roadmap for the delivery of features and functionalities.

How should the project manager respond to the customer?

Options:

A.

Explain to the customer that an agile approach requires re-prioritization at the beginning of each sprint, so it is not possible to provide a roadmap.

B.

Ask the customer to develop a roadmap the team can follow for future delivery.

C.

Work with the customer to understand which user stories will deliver the best business value, re-prioritize the backlog, and share it with the customer to provide release plans.

D.

Work with the product owner to develop a tentative roadmap for the customer but explain that it is always subject to change.

Buy Now
Questions 96

A globally distributed project team is using email and phone calls as the only way to share information. Delays in resolving issues often occur due to misinterpreted communications, leading to a lower team velocity.

What steps should the project leader take to improve knowledge sharing?

Options:

A.

Meet individually with each team member to identify the issues and relay information to the remaining members through status reports.

B.

Establish a live video feed between the dispersed teams to enable spontaneous engagement and collaboration on issues.

C.

Request that the customer co-locate the team to overcome the communication issues, as this is the only method to ensure agility.

D.

Inform the customer of the challenges and lower velocity of the project to accommodate for the slower delivery pace.

Buy Now
Questions 97

A newly formed, colocated team is participating in daily standups, but is otherwise working largely as individual contributors. This has resulted in misalignment of activities. Planned velocity is being met.

What should the agile practitioner do?

Options:

A.

Plan activities that will require the team to work collaboratively on a regular basis.

B.

Set collaboration metrics and evaluate individuals against those metrics.

C.

Request that line management add more collaborative team members to the team.

D.

Allow the team to continue with no interference as activities are being met.

Buy Now
Questions 98

New stakeholders are joining a project team where the agile coach will educate them about their roles and responsibilities. How should the stakeholders ensure their objectives are met by product delivery?

Options:

A.

Provide feedback for completed user stories.

B.

Define how the features will be implemented.

C.

Tell the team which features to include in the backlog.

D.

Write acceptance criteria for the user stories.

Buy Now
Questions 99

An agile team and a traditional development team are working together on a project. Each team exceeds expectations regarding deliverables: however, issues arise when the deliverables are integrated. What should the agile practitioner do?

Options:

A.

Foster stronger communication by hosting cross-organizational meetings between the two teams.

B.

Suggest merging the teams to avoid misunderstandings.

C.

Create stories from full technical specifications to avoid ambiguity.

D.

Co-locate the teams to encourage osmotic communication.

Buy Now
Questions 100

Stakeholders are unhappy because they have not been consulted on a user interface (UI) for a project that will have a significant impact on end users once it is launched. How should this situation be handled?

Options:

A.

The agile team should engage stakeholders regarding the proposed designs and ensure that sufficient engagement occurs throughout the project in an adaptive way.

B.

The agile practitioner should inform the stakeholders that the Ul has already been approved by the project team and the project sponsor, so the team is committed to staying the course.

C.

All stakeholders should go through the approved project charter and the business requirements document to reduce the number of late changes or requests.

D.

The stakeholders should contact the project sponsor to get the project halted until new requirements are agreed upon.

Buy Now
Questions 101

During backlog refinement, a team routinely creates tests to demonstrate to the customer that each acceptance criterion has been met. Most acceptance tests results are observable or demonstrable, but testing for one requirement is providing a challenge to the team. The requirement states that the home button should be recognizable and the team is unsure how to test this.

What should the team lead do?

Options:

A.

Determine if the home button is present and if it is shaped like a house, it is recognizable.

B.

Record the product owner's opinion on how they will know if the button is recognizable.

C.

Skip creating a specific test for Ibis particular requirement because it is too abstract

D.

Consult the design team as subject matter experts (SMEs) for criteria on what makes a button recognizable.

Buy Now
Questions 102

Unable to meet a sprint's committed velocity, an agile team approaches the agile coach to define the next sprint's velocity. What should the agile coach advise?

Options:

A.

Split each story into multiple stories to meet the desired velocity.

B.

Set the velocity to the delivered story points of the last sprint.

C.

Use different estimation methods for stories and defects to meet the desired velocity.

D.

Re-estimate by assigning more story points to smaller stories to increase the velocity.

Buy Now
Questions 103

An agile learn has only one database administrator with the necessary knowledge of database-related tasks. The project manager identifies the risk that if this person leaves, team velocity will significantly decrease.

What should the agile coach do?

Options:

A.

Start the hiring process for a new, equally skilled database administrator as a replacement.

B.

Move this database administrator to another team so that team members learn database-related tasks.

C.

Add another database administrator to balance the workload and aid with knowledge retention.

D.

Obtain agreement from the team that, on upcoming sprints, the database administrator will act only in an advisory capacity.

Buy Now
Questions 104

One of the overseas stakeholders on an agile project has not been actively involved in the project's development. What would be the first step to reengage the stakeholder?

Options:

A.

Increase the frequency of emails and/or try to call the stakeholder.

B.

Remind the stakeholder of their obligation to engage in the project.

C.

Talk to the stakeholder's superior so they can offer coaching and guidance on project involvement.

D.

Set up a meeting with the stakeholder to modify the working agreement and ensure future engagement.

Buy Now
Questions 105

An agile team is having a meeting with a customer to formulate the product requirements for the next iteration. The outcome of the meeting is a set of clear and detailed requirements.

What should the team do next?

Options:

A.

Run automated tests on the legacy functionality.

B.

Ask the customer to write tests that will be used to know when a story has been correctly developed.

C.

Start coding on the selected user stories to meet the requirements.

D.

Write tests that will be used to know when a story has been correctly developed.

Buy Now
Questions 106

During a project review, the team discovers customer feedback that would add scope. The project leader is concerned that the team will be unable to incorporate this feedback and still meet the product launch date.

What should the project leader do?

Options:

A.

Finalize the feedback in the form of a change request

B.

Limit the scope of the feedback to only those changes that the team can feasibly accommodate

C.

Encourage all feedback then work with the customer to prioritize work for future sprints

D.

Allow the team to decide what feedback to incorporate

Buy Now
Questions 107

During an iteration review, the agile team asserts that a product is complete because development and review were finished. The product owner disagrees, since the product has not been tested.

What should the agile practitioner do?

Options:

A.

Work with the agile team and product owner to agree on the definition of done

B.

Ask the project sponsor to determine whether the product is completed

C.

Plan another review after the product has been tested

D.

Add testing to the backlog, and have the product owner reprioritize

Buy Now
Questions 108

An agile coach advised a project manager to continuously improve their ability to support their team and remove any obstacles in the project's way. What role is the agile coach advising to the project manager to take on?

Options:

A.

Scrum master

B.

People manager

C.

Servant leader

D.

Squad leader

Buy Now
Questions 109

Team A is working on the second sprint of a product release Team B which is an interdependent team located on the same floor, requires extensive and frequent information to complete its sprint goal.

What should the agile team lead do?

Options:

A.

Create a central repository for information, and provide access to team B

B.

Use an information board that will be visible to all passing through the workspace

C.

Email all stakeholders with status updates

D.

Provide team B with the information on an "as needed" basis

Buy Now
Questions 110

An agile team delivered a feature in the last iteration. The product owner, who missed the planning and review meetings, was dissatisfied with the feature. The team conducted a retrospective and reviewed the user stories related it.

What should the agile team do next?

Options:

A.

Ensure that the product owner reviews the acceptance criteria for delivered user stories.

B.

Augment the quality assurance and continuous integration processes for delivery.

C.

Approach the relevant developers and testers regarding quality issues in upcoming iterations.

D.

Ask the product owner to define the entire scope of delivery two to three iterations in advance.

Buy Now
Questions 111

A team member has asked a question about the responsibilities of the product manager, QA, and the team regarding quality. What should the agile project manager advise?

Options:

A.

The entire team is responsible for quality and each team member is accountable for ensuring the success of every component.

B.

The entire team is responsible for quality, but each team member's role may vary as stated in the definition of done (Do

C.

The entire team is responsible for quality and QA is responsible for surprises, gaps, and other intricacies that may have been overlooked.

D.

Quality is the responsibility of the entire team, and the product manager defines the functionality from end to end.

Buy Now
Questions 112

A team member on a self-directed team is concerned that a feature the customer wants is outside of what the team will be able to deliver. What should the team member do next?

Options:

A.

Escalate the concern to the project sponsor for necessary action

B.

Adjust the feature to make it work as needed

C.

Work directly with the customer to arrive at a suitable compromise

D.

Log this into the risk register and inform the team at the next standup meeting

Buy Now
Questions 113

A project is to be started with a team of nine existing and nine new members. The scrum master feels that the team is too large and wants to break it into three teams. The scrum master sets aconstraint that each team have an equal number of existing team members for knowledge sharing and experience.

What should the scrum master do to accomplish this?

Options:

A.

Ask the team members' functional managers for guidance on how to group the team members.

B.

Observe which team members are comfortable working together, then assign accordingly.

C.

Ensure that members begin to self-organize as small teams with efficiently distributed skills.

D.

Assign team members to their respective teams based on the skills known to the scrum master.

Buy Now
Questions 114

During a team meeting members who are subject matter experts (SMEs) mention that they are continuously working on repetitive tasks which has lowered motivation. What should the agile practitioner do?

Options:

A.

Organize a team-building activity to improve team morale

B.

Have team members work in pairs to learn from each other and develop new skills

C.

Ask team members to perform a value stream analysis of their activities.

D.

Add more resources to the team to help with the tasks

Buy Now
Questions 115

An agile project was underway for two months and delivered the expected value to the stakeholders. However, during a sprint review, a team member complained that the product owner constantly changes requirements and the member feels that this is blocking the team’s performance.

How can the scrum master handle this situation?

Options:

A.

Work with the product owner to include fewer features in the next sprint planning.

B.

Hire more team members to elevate the team's velocity to increase performance.

C.

Tell the team members that changes are natural and welcome if the project is delivering value.

D.

Schedule more meetings with the team and the product owner to refine the backlog constantly.

Buy Now
Questions 116

Case Study

An agile project lead for a company is leading a sales team who has committed to delivering new product functionality to the customer at the end of five sprints. The agile project lead performed initial planning with the team and with the team's support has committed to the scope and deadline.

Check in with the project in three stages to answer the associated questions.

How do two additional features and more story points added by the product owner impact the team's progress and ability to complete work within the iteration, considering the burndown rate of the team has not changed? (Refer to the Case Study and End of Sprint 3 Exhibit)

Options:

A.

The scope of the items in the backlog has been increased to reflect an increase in velocity.

B.

The backlog has been increased and the velocity of the project may no longer be on track.

C.

The team has committed to additional work added to the backlog and will increase velocity.

D.

The team did not complete the backlog items at the same velocity due to external issues

Buy Now
Questions 117

An organization wants to increase value delivery in its agile projects. What should the agile teams do?

Options:

A.

Perform analysis and development work, but no testing because that should be managed by another specialized team.

B.

Master available technology and tools to provide informative dashboards to the stakeholders.

C.

Work with product owners and turn product backlog items into potentially shippable product increments.

D.

Complete projects by their deadlines and share the budgets upfront with project sponsors.

Buy Now
Questions 118

A project manager is working on a database migration project to cloud services (Refer to Migration Strategy to Cloud Services table). The project team has accumulated significant technical debt over several sprints due to pressure to deliver features quickly. This debt is nowimpacting their ability to deliver new features, leading to a notable decline in product performance and customer satisfaction.

Identify the actions the team should take to effectively manage technical debt while consistently delivering high-value features that align with stakeholder expectations.

Options:

A.

Form a separate learn dedicated lo handling technical debt, allowing the current team to focus on new features to maintain a competitive advantage and stakeholder satisfaction.

B.

Include technical debt tasks in every sprint, treating them with the same level of priority as new features, and continuously review the impact on the project's overall goals.

C.

Ignore the technical debt foe now and focus exclusively on delivering new features so that the project can maintain a competitive advantage and stakeholder satisfaction.

D.

Dedicate multiple consecutive sprints solely to addressing technical debt, halting new feature development temporarily to minimize the impact on the project's overall goals.

Buy Now
Questions 119

What is a specific development practice that has been effective in implementing disciplined DevOps?

Options:

A.

Put the client first.

B.

Create a safe environment.

C.

Practice continuous delivery.

D.

Manage risk.

Buy Now
Questions 120

A software company is developing an accounting software system to market to customers. The team has been working on the project for six weeks and has great velocity. One of the major stakeholders approached the scrum master and asked for a bi-weekly status report because they feel they are not being properly updated.

How should the scrum master respond to this request?

A Inform the stakeholder that all updates are provided in the sprint review sessions and encourage them to attend

B. Create and update bi-weekly project status reports for the stakeholder who requested the report.

C. Escalate this to the stakeholder's supervisor because this is an unreasonable request.

D. Ignore the stakeholder's request and continue working on the project as they have been for the past six weeks.

Options:

Buy Now
Questions 121

A new product owner needs to manage the backlog of a high-visibility fast-moving project that is consuming a considerable amount of time What should the product owner do?

Options:

A.

Schedule regular meetings with the scrum team to write, groom and size user stories

B.

Focus on stories based on the highest number of story points to first address those items with the highest value

C.

Seek regular input from project stakeholders, and reflect this input in the backlog's priorities

D.

Schedule in-person monthly meetings with key stakeholders to review the project's progress

Buy Now
Questions 122

During the fourth sprint retrospective for an IT project, the team members develop a series of actions to improve problem solving in the next sprint. However, many team members are concerned that these actions will not be implemented, since there was no follow-up from the last retrospective meeting.

What should the scrum master do to improve team commitment to the recommendations from the retrospective meeting?

Options:

A.

Lead the team and help them to constantly improve the processes in the project.

B.

Be aggressive when working with the team to identity the root cause of the problems.

C.

Ensure each team member follows through all the improvement actions.

D.

Perform as a servant leader and let the team resolve the impediments of the project themselves.

Buy Now
Questions 123

An organization is using a predictive approach to managing projects. The executives like to see more deliverables in a short time and require that the milestones be achieved on time.

What value can the organization gain by moving to an iterative approach?

Options:

A.

New tools that deliver iterative and incremental work

B.

A more predictable delivery schedule and better quality

C.

Higher levels of activity-based planning and user histories

D.

Increased focus on the value and benefits delivered

Buy Now
Questions 124

During a retrospective, the team agrees that they have limited competence in using a newly introduced tool. What should the team do?

Options:

A.

Explore options for increasing knowledge in the next iteration's backlog.

B.

Experiment with the tool's usage by adding extra tasks in the current iteration.

C.

Propose alternative tools that the team is more competent using.

D.

Ask a tool expert to join the team and perform the relevant work.

Buy Now
Questions 125

Management decides to set up a new project to exploit an emergent market opportunity. Management suggests using an agile approach that is currently working for another project.

What should the agile leader do next?

Management decides to set up a new project to exploit an emergent market opportunity. Management suggests using an agile approach that is currently working for another project.

What should the agile leader do next?

Options:

A.

Conduct a workshop for all key stakeholders to analyze the case and decide on the proper approach.

B.

Suggest an approach that was successful in a previous project.

C.

Accept the manager's suggestion and avoid unnecessary conflicts and delays.

D.

Work with the team to analyze the market opportunity and create a tailored agile approach if needed

Buy Now
Questions 126

An infrastructure team had to revamp so downstream channels could consume data from the data lake, thereby improving operational efficiency for the end customers. Which primary components should the product manager consider while plotting performance and dependencies on the product roadmap?

Options:

A.

Product vision, business objectives, themes, timeframes, and disclaimers

B.

Product improvements, resource management, risk management, and deadlines

C.

Product goals, strategic objectives, major features, and release plans

D.

Features, stages of development, technology and infrastructure, dependencies, and risks

Buy Now
Questions 127

An agile lead is experienced with predictive and agile approaches. The agile lead was recently invited by human resources (HR) to be part of a learning team. During roundtable discussions with the project management team, the agile lead states: "I foster a safe environment for disagreement so my team feels empowered to move forward without obstacles."

What is the agile lead attempting to highlight?

Options:

A.

Ownership, because team members will be in charge of whatever happens during the project life cycle.

B.

Conflict is not productive and team members should resolve issues by themselves.

C.

Better decision-making, because the team is encouraged to join in constructive conflict.

D.

Leaders should incentivize conflict because it is inevitable in the workplace.

Buy Now
Questions 128

The customer asked the IT project manager to change a few specifications for the software being developed, which will affect the project budget. The financial sponsor is having difficulty approving changes to the budget that was already allocated to the project.

What should the project manager do next?

Options:

A.

Explain that agile principles mandate that there should be a contingency budget for agile projects.

B.

Request the team work overtime to get the work done on time and within the allocated budget.

C.

Encourage the product owner and team to analyze the impact of the changes and prioritize the backlog.

D.

Review the contract documentation with the customer to clarity the specific agreed upon budget amount.

Buy Now
Questions 129

An agile team lead noticed their team’s velocity was slowing down. They did not deliver a working software during the last iteration and there have been miscommunications between team members.

What should the agile team lead do at the end of this iteration?

Options:

A.

Focus on performance in the retrospective, then present performance indices and validate with the team.

B.

Start using feedback loops in every sprint to reevaluate project and team performance.C Emphasize business requirements and investigate the pair-programming approach

C.

Run a spike at the end of the sprint to investigate the issue and reduce project risk.

Buy Now
Questions 130

A large project team of 20 people from different functional areas has just been formed and the project starts next week. The team will be working on a regulated and strictly controlled pharmaceutical product but does not have subject matter expertise.

Which two actions should the scrum master take as priorities? (Choose two.)

A large project team of 20 people from different functional areas has just been formed and the project starts next week. The team will be working on a regulated and strictly controlled pharmaceutical product but does not have subject matter expertise.

Which two actions should the scrum master take as priorities? (Choose two.)

Options:

A.

Schedule a meeting to engage stakeholders to prepare for kickoff

B.

Schedule a meeting to agree to the goals for all future iterations.

C.

Guide the team to work collaboratively and share learnings.

D.

Organize a sprint planning meeting to define actions.

E.

Organize a meeting to outline roles and responsibilities.

Buy Now
Questions 131

Which of the following allows DevOps to enable and sustain a fast workflow from development into operations?

Options:

A.

A mindset shift to establish controls over all development and operations processes.

B.

Planned incremental iterations and a focus on people over processes.

C.

A culture of collaboration, tools, and processes to support continuous delivery.

D.

New tools that enable teams to continuously build, test, and integrate.

Buy Now
Questions 132

A member of a project's development team approaches the team lead and requests database administrator training. The team member believes that their inability to handle this work, and to rely on outside specialists, is impacting team velocity.

What should the agile team lead do?

Options:

A.

Send the member to training?

B.

Ask the outside specialists if database administration is required from the team

C.

Send one member to training only after asking the team if there is an issue with the current work flow

D.

Wait until all members of the team can attend training

Buy Now
Questions 133

An agile team is in their 2nd iteration planning session. During the session, they are debating on whether regression and integration testing should be part of every iteration or part of the hardening iteration.

What should the agile lead recommend?

Options:

A.

Integration testing with other upstream or downstream applications and all bug fixes should be done as part of the hardening iteration.

B.

Integration testing with other upstream or downstream applications should be done by the team as part of every iteration.

C.

Continuous integration and regression testing should be done by the team as part of every iteration.

D.

Regression testing should not be done by the team as part of every iteration but only as part of the hardening iteration.

Buy Now
Questions 134

An agile practitioner wants to communicate the effect of technical debt on the project What should the practitioner do?

Options:

A.

Post and discuss rises in the burn down chart

B.

Adjust story points to account for technical debt

C.

Log technical debt as an impediment

D.

Add refactoring tasks to all stories

Buy Now
Questions 135

What is the disadvantage of using velocity as a measure of team efficiency in agile approaches?

Options:

A.

Capacity planning will not be accurate.

B.

Inaccurate pressure on customers.

C.

Quality increases while output decreases.

D.

Delivery speed increases while morale decreases.

Buy Now
Questions 136

A product owner complains that some of the requirements identified several iterations ago have not been implemented. The product owner wants to know why the status of these requirements was not communicated.

What should the Scrum Master do?

Options:

A.

Point out that the team chose to work on other requirements to speed up the project

B.

Ensure that the product owner reviews the contents of the information radiator

C.

Ensure that the next sprint planning meeting reviews the satisfaction histogram

D.

Point out that it is the responsibility of the product owner to clarify requirements

Buy Now
Questions 137

Midway through a sprint, a scrum team member advises the team of a new requirement that may change the initial scope. What should the team do?

Options:

A.

Work on requirements that the product owner may have overlooked

B.

Record the scope creep in the change management log

C.

Add the new requirement to the product backlog

D.

Ask the scrum master to secure additional time and resources

Buy Now
Questions 138

During sprint planning the product owner wants the team to prioritize and deliver a number of features which have the highest business value. Due to technical dependencies, the team does not agree with the prioritization.

What should the project leader do?

Options:

A.

Encourage the product owner and team to reprioritize the features and select ones which can be delivered without any dependencies

B.

Encourage the team to continue with the current plan, do what they can. and carry forward the work not done to the next iteration

C.

Ensure the team captures the technical dependencies as issues within the backlog and prioritize based on value optimization

D.

Ensure that the required subject matter experts (SMEs) are engaged by the product owner to help with backlog prioritization

Buy Now
Questions 139

A member of a cross-functional project team is not able to attend regular status meetings and provide progress updates, which is impacting the productivity of the entire team. What should the product owner do to improve productivity?

Options:

A.

Discuss the issue to reduce the backlog based on decreased productivity of the team.

B.

Collect updates from each team member before the meeting and share them with all members.

C.

Ask the team member to update daily progress on the information radiators.

D.

Change the team velocity to show positive progress in shared information radiators.

Buy Now
Questions 140

An agile team has started to worry because lately they have seen an increase in the number of issues. There seems to be a large variance in the quality of the work items delivered. The team now realizes that a shared understanding of quality may not exist among team members.

What should the team do?

Options:

A.

The team should move to test-driven development as defects are not being detected during testing.

B.

The team should account for the increased problems in their velocity forecasts since unexpected changes occur in agile projects.

C.

The team should discuss their definition of done (DoD) and make changes to ensure there is common understanding of the acceptance criteria.

D.

The team's agile project manager should facilitate the development of a new, detailed test procedure that all team members must follow.

Buy Now
Questions 141

The product owner of an agile project is frustrated because the team is unable to deliver as many features as expected. The product owner asks the team to reduce test-automation levels, since the quality assurance team will test the product at project completion. The product owner expects that more features will be delivered in each iteration using this approach.

What should the agile practitioner do?

Options:

A.

Ask the opinion of key stakeholders and the client to ensure the correct approach is being used.

B.

Work with the team to use this approach and request a quality assurance iteration after every three iterations

C.

Propose to completely eliminate test automation, since this is a quality assurance function.

D.

Suggest merging the quality assurance and delivery teams to enhance each iteration's test-automation levels and reduce redundancy

Buy Now
Questions 142

An agile practitioner notices that team members are disengaged. As a result, the team's velocity has decreased. What should the agile practitioner do to get the team back on track?

Options:

A.

Escalate the issue to the project sponsor.

B.

Remove stories to increase velocity.

C.

Hold a standup to address the issue.

D.

Facilitate a team retrospective.

Buy Now
Questions 143

A new stakeholder has recently joined a project. During a meeting with the scrum master, the new stakeholder tries to understand the status of the project and the remaining tasks for completion.

How should the scrum master inform the new stakeholder?

Options:

A.

Show the stakeholder the latest release breakdown for the project.

B.

Invite the stakeholder to attend the next sprint review meeting.

C.

Show the stakeholder the progress radiators for the project.

D.

Invite the stakeholder to attend the next sprint planning meeting.

Buy Now
Questions 144

For what is the MoSCoW method used?

Options:

A.

Estimating story size

B.

Prioritizing stories

C.

Validating a product

D.

Tracking progress

Buy Now
Exam Code: PMI-ACP
Exam Name: PMI Agile Certified Practitioner (PMI-ACP)
Last Update: Mar 13, 2025
Questions: 482

PDF + Testing Engine

$134.99

Testing Engine

$99.99

PDF (Q&A)

$84.99