Black Friday Special 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: best70

PK0-005 CompTIA Project+ Certification (2024) Questions and Answers

Questions 4

A developer focused on a single story during an entire sprint. The story was underestimated and, therefore, was not completed. Which of the following steps should the Scrum team take next?

Options:

A.

Assign more resources to complete similar stories in the future.

B.

Break the stories into workable items that can be completed within one sprint.

C.

Extend the sprint duration when required with the approval of the product owner.

D.

Release the current progress into production and carry over the rest of the code for the next sprint.

Buy Now
Questions 5

A project manager just found out that the equipment vendor selected for a project is bankrupt. The process of selecting a new vendor and signing a contract will significantly delay the project schedule. Which of the following should the project manager do first?

Options:

A.

Consult with the legal department.

B.

Update the issue log.

C.

Start a new RFP immediately.

D.

Perform a PERT analysis.

Buy Now
Questions 6

One of the key steps in controlling changes lo software is obtaining approval. Which of the following statements best describes the reason for this key objective?

Options:

A.

To send the appropriate customer notifications

B.

To avoid a negative impact on other software functionalities

C.

To ensure adequate resources are in place to implement the change

D.

To confirm that the software is a business priority

Buy Now
Questions 7

Which of the following best represents the project impact to a company's brand value?

Options:

A.

The project is compliant with local and state laws and becomes the standard for new projects.

B.

The project promotes new initiatives to expand its benefit to other communities.

C.

The project exceeds the sales quota for the third quarter and raises the bar for next periods.

The project meets the expected milestones and finishes on time and within budget.

Buy Now
Questions 8

During a complex, multiyear project, a PM must discern which project tasks overlap so resources can be allocated appropriately. Which of the following is best for determining this information?

Options:

A.

PERT chart

B.

Milestone chart

C.

Gantt chart

D.

Budget burndown chart

Buy Now
Questions 9

Which of the following BEST illustrates how team members with different roles should interact on the team?

Options:

A.

SOW

B.

WBS

C.

RACI

D.

PERT

Buy Now
Questions 10

Which of the following can be used to determine whether a sample product is within an acceptable range?

Options:

A.

Scatter diagram

B.

Velocity chart

C.

Control chart

D.

Fishbone diagram

Buy Now
Questions 11

Due to multiple changes, the sign-off for the project scope baseline is delayed. The project sponsor has restricted the budget for this project. Which of the following should the project manager MOST likely do to move forward?

Options:

A.

Communicate with the affected stakeholders.

B.

Initiate a formal change request to modify the cost

C.

Adjust the scope to stay within the cost.

D.

Set a new cost using a lightweight estimation method.

Buy Now
Questions 12

Defects associated with project deliverables have been reported. The project team needs to find the cause of the defects. Which of the following tools should the project team use to find the cause?

Options:

A.

Kanban board

B.

Pareto chart

C.

Ishikawa diagram

D.

Decision tree

Buy Now
Questions 13

An software engineer is applying new updates to a program in a sandbox environment. Which of the following risk strategies best describes this practice?

Options:

A.

Transfer

B.

Mitigate

C.

Avoid

D.

Accept

Buy Now
Questions 14

A project manager is currently meeting with a vendor who completed the project work. All invoices associated with the project have been paid. Which of the following best describes the project manager's objective for the vendor meeting?

Options:

A.

Reassigning resources

B.

Removing access

C.

Closing contracts

D.

Evaluating the project

Buy Now
Questions 15

Which of the following would be MOST beneficial to do before a call to ensure all meeting items are addressed and the correct participants attend?

Options:

A.

Assign action items to attendees.

B.

Distribute an agenda.

C.

Email the minutes from the previous meeting.

D.

Schedule a convenient time.

Buy Now
Questions 16

Which of the following software programs would be best to use to store information related to business transactions?

Options:

A.

Record management system

B.

Customer relationship management

C.

Enterprise resource planning

D.

Content management system

Buy Now
Questions 17

A demo presentation for a global project was not as successful as expected because the development team misinterpreted which features needed to be incorporated. Which of the

following has the project manager identified?

Options:

A.

Technological factors

B.

Poor sample data

C.

Language barriers

D.

Scope creep

Buy Now
Questions 18

During the project execution phase, Ann, a project manager, received an email from the project sponsor asking for an additional work package to be added to the project scope due to new legislation.

INSTRUCTIONS

Review the email with the latest updates sent by the project sponsor and respond in

the following order:

1. Select the best tool for tracking the server migration progress.

2. Select the new critical path.

3. Select the correct number of engineers required for the server migration phase.

If at any time you would like to bring back the initial state of the simulation, please click

the Reset All button.

Select the Appropriate Tool:

Select the new critical path.

Option A

Option B

Option C

Options:

Buy Now
Questions 19

A project manager has decided to outsource portions of a project and will conduct a separate procurement. In which of the following phases does this task occur?

Options:

A.

Planning

B.

Initiating

C.

Controlling

D.

Executing

Buy Now
Questions 20

During a brainstorming meeting, a project manager identifies multiple techniques that will help the project team ensure confidence and alignment with the project scope and goals. Which of the following plans is the project manager creating?

Options:

A.

Procurement

B.

Communication

C.

Quality assurance

D.

Risk

Buy Now
Questions 21

A project team wants to compare two potential vendors' costs and risks for completing project tasks. Which of the following visualizations will best facilitate this analysis?

Options:

A.

Scatter diagram

B.

Decision tree

C.

Pareto chart

D.

Histogram

Buy Now
Questions 22

A project is moving into the user acceptance testing phase. Several resources will be needed to execute different steps in the testing plan. Which of the following would be the best tool to allow the resources to remain at their desks and only react when needed?

Options:

A.

Ticketing system

B.

Videoconference

C.

Simple messaging system

D.

Corporate social media

Buy Now
Questions 23

A project manager provided details regarding the completion of the following tasks:

Vendor selection took less time than planned.

Equipment procurement took less time than estimated.

Equipment installation went according to schedule.

Which of the following should the project manager update?

Options:

A.

Change log

B.

Project Gantt

C.

Issue log

D.

Requirements traceability matrix

Buy Now
Questions 24

A project manager and team are currently in the planning phase of a project. Which of the following should the team do during this phase?

Options:

A.

Identify and assess stakeholders.

B.

Hold daily status meetings.

C.

Remove access and plan the project sign-off.

D.

Review assumptions and constraints for input to the risk register.

Buy Now
Questions 25

A project manager makes a company-wide announcement about the successful completion of a project and thanks team members. Which of the following is the project manager doing?

Options:

A.

Bringing attention to the project sponsor

B.

Sharing lessons learned

C.

Collecting feedback

D.

Celebrating the team's hard work

Buy Now
Questions 26

A project team needs a tool to store information that is captured throughout the life cycle of a project. The information should be stored in a centralized location that is easily accessible to all stakeholders and will provide search functionality. Which of the following tools should be used?

Options:

A.

Secure folder

B.

Real-time, multiauthoring editing software

C.

Digital whiteboard

D.

Wiki knowledge base

Buy Now
Questions 27

After months of recruiting, a team finally found the right candidate for a very specific coding language assignment. Due to this delay, the team has a tight timeline without any float. A day before the candidate is scheduled to join the team, the project manager realizes the candidate has a non-compete agreement from the previous employer. Which of the following should the project manager do?

Options:

A.

Withdraw the offer to the candidate and raise this as a risk.

B.

Ignore a potential lawsuit since this is a critical project.

C.

Use a third-party company for the contract to legally avoid responsibility.

D.

Have a meeting with the project sponsor to discuss the situation.

Buy Now
Questions 28

A project manager wants to schedule a troubleshooting session for team members who are located in Germany and California. Which of the following is most important for the project manager to consider when setting up the session?

Options:

A.

Cultural differences

B.

Technological factors

C.

Time zones

D.

Language barriers

Buy Now
Questions 29

A global franchise requests that a company provide a solution to unify its operation worldwide. Additionally, the company would like the solution to provide operation reports in real time without asking the country franchise manager for these reports. Which of the following cloud models would the company suggest to the global franchise?

Options:

A.

laaS

B.

XaaS

C.

PaaS

D.

SaaS

Buy Now
Questions 30

A project team gathers weekly to review its progress. Which of the following is the project manager MOST likely to have prepared to ensure team members who are absent remain informed about assignments?

Options:

A.

Status report

B.

Project plan

C.

Change log

D.

Meeting minutes

Buy Now
Questions 31

A project manager is monitoring team performance by comparing committed versus completed work. The project manager creates the following:

Which of the following most likely represents the number of items in the backlog?

Options:

A.

23

B.

5

C.

10

D.

15

Buy Now
Questions 32

A global franchise requests that a company provide a solution to unify its operation worldwide. Additionally, the company would like the solution to provide operation reports in real time without asking the country franchise manager for these reports. Which of the following cloud models would the company suggest to the global franchise?

Options:

A.

laaS

B.

XaaS

C.

PaaS

D.

SaaS

Buy Now
Questions 33

A project manager is coordinating multiple teams of six people that will each provide feedback for a new product. The teams are recording their opinions, which may be used to define the final product that is sent to mass production. Which of the following best describes this technique?

Options:

A.

Demonstration

B.

Workshop

C.

Brainstorming

D.

Focus group

Buy Now
Questions 34

A PM has identified all the resources involved in a project. The next step is to identify which resources are responsible for which tasks. Which of the following should be used to document this information?

Options:

A.

RFI

B.

RACI

C.

WBS

D.

SOW

Buy Now
Questions 35

Which of the following contract types in project procurement has the highest risk for the buyer?

Options:

A.

Time and material

B.

Cost-plus

C.

Fixed-price

D.

Unit price

Buy Now
Questions 36

Project stakeholders have asked the team to use Scrum to run a software implementation project. Which of the following is most likely to take place during a Scrum ceremony?

Options:

A.

Reviewing project blockers

B.

Defining roles and responsibilities

C.

Establishing a project schedule

D.

Determining a project budget

Buy Now
Questions 37

Which of the following would be the NEXT document a project manager should update once the need to procure goods and/or services is identified?

Options:

A.

Memorandum of understanding

B.

Request for information

C.

Statement of work

D.

Non-disclosure agreement

Buy Now
Questions 38

An opportunity emerged in the middle of a project life cycle. Which of the following is the BEST action for the project manager to take?

Options:

A.

Exploit the risk.

B.

Accept the risk.

C.

Avoid the risk.

D.

Transfer the risk.

Buy Now
Questions 39

Which of the following BEST describes how an organization should coordinate management of multiple related projects?

Options:

A.

Apply the SDLC process.

B.

Establish a program.

C.

Consult the CCB.

D.

Use different frameworks

Buy Now
Questions 40

A project manager has been very diligent in maintaining the version control for the documentation of requirements. Which of the following tools is the project manager using?

Options:

A.

Multiauthoring software

B.

Word processor

C.

Real-time polling

D.

Conferencing platforms

Buy Now
Questions 41

A project coordinator has started a new project and is reviewing the following characteristics provided by the customer:

• Two developers

• High uncertainty about existing systems

• Risk of frequent requirement changes

• Tight deadlines

Which of the following project methodologies would be best to use in this situation?

Options:

A.

PRINCE2

B.

Scrum

C.

SAFe

D.

XP

Buy Now
Questions 42

A company is implementing a new radar system from July to September. The project manager knows these months are the peak hurricane season for this region. Which of the following should the project manager develop to mitigate the risk to the project?

Options:

A.

Data plan

B.

Contingency plan

C.

Rollback plan

D.

Recovery plan

Buy Now
Questions 43

During a gate review meeting, the deliverable was rejected by the customer.

INSTRUCTIONS

Review the dashboard.

• Part 1: Drag and drop each task, placing them in the correct order based on the project change control process.

• Part 2: Select the proper document(s) to be updated.

If at any time you would like to bring back the initial state of the simulation, please click the Reset All button.

Part 1:

Part 2:

Options:

Buy Now
Questions 44

Which of the following BEST identifies the intent and purpose of a project closeout report?

Options:

A.

To provide documentation of lessons learned

B.

To document variances from the initial project baseline

C.

To validate that a project has been successfully completed

D.

To release resources and terminate all access rights

Buy Now
Questions 45

During a quality analysis review, the causes of several issues have been highlighted. Which of the following should the project manager use to identify the MOST important causes?

Options:

A.

Ishikawa diagram

B.

Scatter diagram

C.

Pareto chart

D.

Decision tree

Buy Now
Questions 46

Given the following velocity chart:

Which of the following updates on the project status should the Scrum master provide to the senior management team?

Options:

A.

The project utilized all of its available reserve.

B.

The project has scope creep.

C.

The project deviated from the critical path.

D.

The project is trending ahead of schedule.

Buy Now
Questions 47

Which of the following would be best to utilize when managing communications for project teams across multiple time zones?

Options:

A.

Business collaboration tool

B.

Email

C.

Virtual meetings

D.

Enterprise CMS

Buy Now
Questions 48

A project manager has been informed that the delivery of required IT equipment will be delayed. Which of the following is the FIRST step the project manager should take?

Options:

A.

Make an impact assessment.

B.

Prepare a new purchase order.

C.

Select a new vendor.

D.

Create a risk register.

Buy Now
Questions 49

An IT intern was assigned to set up workstations as part of a project. The IT intern was very careful to do the task well and initially referred to notes while performing the task. By the end of the two-week rotation, the IT intern no longer needed the notes and completed more set-ups in less time. Which of the following MOST likely represents the observed relationship in this scenario?

A)

B)

C)

D)

Options:

A.

Option A

B.

Option B

C.

Option C

D.

Option D

Buy Now
Questions 50

Hackers are attempting to extract large amounts of data to sell on the dark web. Which of the following steps should a project manager take next to mitigate this risk?

Options:

A.

Update the issue log.

B.

Apply the contingency plan.

C.

Transfer the risk.

D.

Submit a change request.

Buy Now
Questions 51

Following the approval of a change by the CCB, which of the following should a project manager consider next when deploying a new networking device into an existing production environment?

Options:

A.

Maintenance window

B.

Risk assessment

C.

Operational security

D.

Validation check

Buy Now
Questions 52

A developer recommends modifying an existing portion of code that is not part of the scope and is causing low performance on the current solution. Which of the following actions should the project manager most likely take?

Options:

A.

Ask a developer to create a change request.

B.

Do nothing because recommendation is scope creep.

C.

Ask a developer to implement the recommendation.

D.

Communicate the change status.

Buy Now
Questions 53

A team currently has a schedule for each sprint that changes after every iteration. The team wants to set up a repeatable schedule that would create a consistent flow of tasks and deliverables after each iteration. Which of the following should be established to best meet this goal?

Options:

A.

Task log

B.

Cadence

C.

Milestones

D.

Work breakdown structure

Buy Now
Questions 54

A PM is working on a strategy to store records. Which of the following dements must be included in this plan? (Select TWO)

Options:

A.

Data management

B.

Issue management

C.

Work breakdown structure

D.

Document management

E.

Communication management

F.

Risk management

Buy Now
Questions 55

A project team needs to understand what needs to be done, who needs to complete the tasks, and when the tasks need to be completed. Which of the following artifacts would be the best to capture this information?

Options:

A.

SWOT

B.

Risk register

C.

Project schedule

D.

RAC

Buy Now
Questions 56

A few weeks before a project is scheduled to be completed, the client asks to add a new feature to the product that is being developed. The project manager analyzes the project schedule and determines the feature can be implemented quite easily without affecting the completion date. Which of the following should the project manager do first?

Options:

A.

Escalate the change to the CCB.

B.

Review the requested change.

C.

Document the change recommendations.

D.

Validate the implementation of the requested change.

Buy Now
Questions 57

Due to budgetary and time constraints, a PM scheduled a meeting with all stakeholders during the planning phase to review the requirements and come to an agreement on the minimum viable product that would be acceptable. Which of the following would be used to document this input?

Options:

A.

Project change management plan

B.

Project management plan

C.

Project transition plan

D.

Project communication plan

Buy Now
Questions 58

A project is running over budget, and due to new legislation in the country, the company needs to release all its contractors on the project or hire them as full-time employees. Which of the following should the PM do next to comply with the new legislation?

Options:

A.

Use only full-time employees even if the project is delayed.

B.

Hire all team members to avoid any delay in the project.

C.

Close the contract and pay the contractors cash for the remainder of the project.

D.

Look for an overseas vendor to finalize the project work.

Buy Now
Questions 59

For an upcoming project kickoff. a PM is looking for a way to illustrate roles for major project activities. Which of the following would be the MOST useful option?

Options:

A.

Resource plan

B.

Organizational chart

C.

Project charter

D.

RACI chart

Buy Now
Questions 60

A new project has been assigned to a project manager. In order to move forward with the project charter, which of the following should the project manager work with to define the success criteria for the initiative?

Options:

A.

Lead architect

B.

Project sponsor

C.

Program manager

D.

Scrum master

Buy Now
Questions 61

As a part of a project, structured cabling activities have been outsourced to another company. The agreement is that work will take six weeks to complete and will be performed at different locations. Which of the following should the project manager do? (Select two).

Options:

A.

Purchase the materials.

B.

Assign the resources.

C.

Accept delays in the work.

D.

Approve the deliverables.

E.

Monitor the performance.

F.

Negotiate with the vendors.

Buy Now
Questions 62

During a status meeting, the development team reviews work and finds an unforeseen dependency on one of the critical project activities. As a result, the project will most likely be delayed. Which of the following actions should the project manager MOST likely perform?

Options:

A.

Work with the project scheduler to update the project timeline.

B.

Communicate to the stakeholders about the updated timeline.

C.

Ask the development team to fast-track upcoming activities.

D.

Add two resources so the critical activities will finish on time.

Buy Now
Questions 63

During the execution phase of a project, team members have been constantly disagreeing about the tasks they have been assigned. Which of the following is most likely the reason they are disagreeing?

Options:

A.

Some work packages are missing from the WBS.

B.

Information is missing from the RACI matrix.

C.

New knowledge bases were introduced.

D.

Team touch points are missing.

Buy Now
Questions 64

A PM is responsible for implementing a new customer relationship management system and has learned that the sales organization is reluctant to utilize the new system. The organization's reluctance could jeopardize the success of the project. Which of the following steps should be taken to understand the adoption issues and gain organizational acceptance of the initiative? (Select TWO).

Options:

A.

Train users on the proper use of the system.

B.

Escalate the issue to the CCB

C.

Hold sessions to understand user challenges.

D.

Track system usage and report user activity.

E.

Log the issue in the project risk register.

F.

Create a memorandum of acceptable use.

Buy Now
Questions 65

Which of the following is a quality assurance tool?

Options:

A.

Defining project goals

B.

Identifying the root cause analysis

C.

Assessing employee efficiency

D.

Assessing skill gaps

Buy Now
Questions 66

A procurement team analyzes solutions submitted from multiple vendors for the upcoming release of a required development service. The procurement team identifies a potential partnership. Which of the following would the procurement team most likely request?

Options:

A.

Quote

B.

Information

C.

Proposal

D.

Bid

Buy Now
Questions 67

Which of the following should be considered first when determining the privacy management for project data?

Options:

A.

Evaluating the current privacy protection program

B.

Understanding applicable privacy regulations

C.

Maintaining awareness of industry best practices

D.

Implementing security role-based controls

Buy Now
Questions 68

Which of the following should a project manager consult when deciding how to send updates regarding deliverables?

Options:

A.

Dashboard

B.

Status report

C.

Meeting minutes

D.

Communication plan

Buy Now
Questions 69

A project manager has been scheduling and facilitating project meetings, scribing the minutes, distributing the minutes, and sending agendas prior to upcoming meetings. However, the project manager is frustrated because action items are not being completed. Which of the following should the project manager do to alleviate these concerns?

Options:

A.

Use a software tool during the meeting that can create a transcript of what is discussed.

B.

Have a standing agenda that is vague enough so that it can be used again.

C.

Delegate the roles and responsibilities to improve meeting management.

D.

Reprimand project team members for not completing assigned action items.

Buy Now
Questions 70

Two developers are discussing the design solution for a particular feature. The meeting is taking longer than expected, and the parties have been unable to reach an agreement. The project manager decides to take a break and continue the meeting on another day. Which of the following techniques is the project manager using?

Options:

A.

Avoiding

B.

Smoothing

C.

Forcing

D.

Compromising

Buy Now
Questions 71

During quality analysis, different team members are identifying multiple constraints. Which of the following tools should the project manager adopt first to help track and prioritize a resolution?

Options:

A.

Issue log

B.

Defect log

C.

Risk register

D.

Change log

Buy Now
Questions 72

A project team was instructed to refurbish old desktops. The following provides the details of the issues observed:

Which of the following issues should be addressed FIRST?

Options:

A.

Replace missing peripherals because this process can be easy and less costly.

B.

An old operating system issue has the most amount of occurrences.

C.

Damage to the monitor has the highest percentage.

D.

Address each issue as discovered to avoid rework.

Buy Now
Questions 73

A project manager needs to ensure that the products produced during the project meet the highest quality standards and that team members understand the importance of these standards. Which of the following should the project manager do?

Options:

A.

Train the team members.

B.

Assess the resource pool.

C.

Develop a QA plan.

D.

Create RACI matrix.

Buy Now
Questions 74

A business analyst has gathered information directly from the client and is currently working with the project manager to identify what to include in the document in order to finish it. Which of the following processes should the project manager do next?

Options:

A.

Validate the scope.

B.

Create the work breakdown structure.

C.

Define the scope.

D.

Collect the requirements.

Buy Now
Questions 75

Which of the following is required to provide a hardware installation with a Tier 5 redundancy level?

Options:

A.

Storage project

B.

Computer services project

C.

Database project

D.

Multitiered architecture project

Buy Now
Questions 76

During the project initiation phase, a project team has been identified. Which of the following is the NEXT step for the project manager?

Options:

A.

Determine budget constraints.

B.

Validate the business case.

C.

Update the project charter.

D.

Create a project schedule

Buy Now
Questions 77

Which of the following is a reason to use a SOW on a project?

Options:

A.

To find out the contact information for the vendors

B.

To review the list of stakeholders

C.

To ensure the team stays within the scope of the contract

D.

To give explicit instruction on how to execute the work

Buy Now
Questions 78

A project manager sent equipment to a global project team for testing purposes. Only 70% of the project team received the equipment for testing. Which of the following considerations is impacting the rest of the team?

Options:

A.

Quality assurance

B.

Organizational branding restrictions

C.

State privacy acts

D.

Country legal regulations

Buy Now
Questions 79

A key stakeholder recommends to a senior developer that a new feature be added. The new feature is not part of the current requirement documentation. Which of the following is MOST likely happening?

Options:

A.

Scope creep

B.

Collecting requirements

C.

Decision-making

D.

Project change

Buy Now
Questions 80

A project manager and team are reviewing a task that is supposed to take nine days to complete and cost $3,000. There is a 20% chance that an associated risk related to changing requirements could occur, resulting in rework that would add an additional five days and $1,000 in costs. Which of the following represents the total amount that should be budgeted for the task?

Options:

A.

9 days and $3,000

B.

10 days and $3,200

C.

12 days and $3,800

D.

14 days and $4,000

Buy Now
Questions 81

A piece of equipment has malfunctioned and is stalling the completion of a deliverable for a project. Which of the following should the project manager do next?

Options:

A.

Buy a replacement for the faulty equipment.

B.

Get the maintenance team to resolve the issue.

C.

Escalate the issue to the project sponsor.

D.

Rate the severity of the impact the issue has on the project.

Buy Now
Questions 82

Which of the following activities should a project manager perform during the closing phase? (Select three).

Options:

A.

Lessons learned

B.

Risk analysis

C.

Removing resources

D.

Acquiring resources

E.

Statement of work sign-off

F.

Stakeholder analysis

G.

Removing access

Buy Now
Questions 83

During timeline creation, the project manager is unsure if the development team can complete coding before new servers are installed in the IT department. Which of the following should the project manager do to increase project certainty?

Options:

A.

Hold a new backlog prioritization meeting.

B.

Add milestones to check the project's progress.

C.

Adjust the task relationship to complete coding in advance.

D.

Apply contingency buffers to the critical path.

Buy Now
Questions 84

Given the following network diagram:

Which of the following is the critical path?

Options:

A.

A-C-G-K-M

B.

A-B-D-l-L-M

C.

A-B-E-J-L-M

D.

A-B-F-L-M

Buy Now
Questions 85

A customer requests some changes to a product, and those changes are approved by the CCB. Which of the following should be changed first?

Options:

A.

ROI

B.

KPI

C.

RACI

D.

SOW

Buy Now
Questions 86

A project manager is organizing and running a project closure meeting. Which of the following best describes the objective of this meeting?

Options:

A.

To move the system to a production environment

B.

To obtain project sign-off

C.

To formalize the end of the contract

D.

To release resources

Buy Now
Questions 87

When introducing a new information asset, what is the MOST important responsibility of the asset owner?

Options:

A.

Information disposal

B.

Information classification

C.

Information access administration

D.

Information backup

Buy Now
Exam Code: PK0-005
Exam Name: CompTIA Project+ Certification (2024)
Last Update: Nov 23, 2024
Questions: 291

PDF + Testing Engine

$140

Testing Engine

$105

PDF (Q&A)

$90