Winter Special Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: netbudy65

PK0-004 CompTIA Project + Questions and Answers

Questions 4

A project team has completed a major deliverable earlier than planned and wants to deliver it for testing. The team lead sends an email providing notice of task completion to the project manager.

Which of the following describes how the project manager can increase the likelihood that the deliverable moves to testing?

Options:

A.

Send an email to quality assurance and copy the project team.

B.

Call a meeting to hand off the deliverable to quality assurance.

C.

Hold a conference call to a review the next deliverable with the project team.

D.

Send an email to the project sponsor and copy the project team.

Buy Now
Questions 5

A project manager is assigned to a project that was previously managed by a peer project manager. The

project manager identifies several modifications that were deployed prior to CCB approval. Which of the

following change control processes is being mismanaged?

Options:

A.

Change validation with quality checks

B.

Regression planning

C.

Identify approval authority

D.

Change implementation

Buy Now
Questions 6

An organization recently restructured. Leaders feel they are not in a position to sign off on a required change, which is delaying a project.

Which of the following is the obstacle?

Options:

A.

Ability to identify approval authority

B.

Incomplete change control documentation

C.

Project team autonomy

D.

Change validation process

Buy Now
Questions 7

Which of the following tasks are responsibilities of the project manager role?

Options:

A.

Provide inputs, estimate tasks, and manage a team

B.

Manage the budget, perform quality assurance, and be accountable for artifacts

C.

Set deliverables, control risk, manage risk, and create a project charter

D.

Manage a team, marketing, roadblocks, and project steering

Buy Now
Questions 8

A project manager noted there were many possible features that could be incorporated into a project, and the customers wavered about whether to include particular features. Which of the following is the BEST approach to ensure appropriate delivery of the project?

Options:

A.

In one section of the project charter, specify which features are included in the project, in another section, specify which features are not included in the project.

B.

The scope statement should enumerate which features are included in the project and which features are not included in the project.

C.

At the beginning and end of every meeting, the project manager should consistently remind the project team which features are included in the project and which features are not included in the project.

D.

The project requirements document lists all the features that are included in the project, and the project manager diligently ensures that features not included in the project are not included in the MOU with the customer.

Buy Now
Questions 9

A company has been trying to implement a product with multiple challenges for more than two years. Both the company and the vendor mutually agree to cancel the project. Which of the following should be issued?

Options:

A.

MOU

B.

LOI

C.

NDA

D.

C&D

Buy Now
Questions 10

A key stakeholder has communicated a significant project scope change to the project manager. Which of the following actions should the project manager take FIRST?

Options:

A.

Submit a change request to the CCB.

B.

Implement the change to the project.

C.

Determine the impact of the requested change.

D.

Update the schedule to accommodate the change.

Buy Now
Questions 11

A project team is unable to meet at the same time, thus requiring project work handoff at each shift.

Which of the following constraints might the project team be facing?

Options:

A.

Geographic separation

B.

Technology limitations

C.

Language barriers

D.

Personal preferences

Buy Now
Questions 12

A Scrum team is completing a sprint; however, some tasks will need to carry over to the next sprint.

Which of the following should the Scrum master do to improve the team's velocity in the next sprint?

Options:

A.

Take a more hands-on leadership approach.

B.

Add the unfinished work to the backlog.

C.

Schedule a sprint retrospective.

D.

Hold additional daily stand-up meetings.

Buy Now
Questions 13

Which of the following is a risk strategy?

Options:

A.

Risk quantification

B.

Risk avoidance

C.

Risk identification

D.

Risk review

Buy Now
Questions 14

To control costs, project funding is being released under a waved approach. After passing each milestone, the project receives the next round of funding. Which of the following is hindered by this funding approach?

Options:

A.

Resource sharing

B.

Crash schedule

C.

Burn rate

D.

Team outsourcing

Buy Now
Questions 15

A number of requirements, conflicts, and reworks during a project delayed the schedule, increased the budget, and required replanning efforts.

Which of the following is MOST likely the cause?

Options:

A.

There were not enough resources assigned to the project execution team.

B.

The PMO was not involved in project initiation and planning.

C.

Proper team-building activities were not performed when starting the project.

D.

A few major stakeholders were overlooked during project initiation and planning.

Buy Now
Questions 16

Which of the following are characteristics of qualitative risk assessments as opposed to quantitative? (Choose two.)

Options:

A.

Qualitative assessments are more difficult.

B.

Qualitative assessments are faster.

C.

Qualitative assessments require fewer resources.

D.

Qualitative assessments provide more accurate results.

E.

Qualitative assessments better identify opportunities.

Buy Now
Questions 17

A first-time project manager is developing a project charter.

Which of the following are key elements to have the project charter approved? (Choose two.)

Options:

A.

Project team

B.

Business case

C.

Detailed risks

D.

Requirements

E.

Service-level agreement

F.

Detailed budget

Buy Now
Questions 18

Which of the following risk management activities identifies the severity of a risk event?

Options:

A.

Quantification

B.

Identification

C.

Response

D.

Mitigation

Buy Now
Questions 19

The project team is creating a schedule for an upcoming project and attempting to determine when each task should occur.

Which of the following will assist the project team with building the schedule?

Options:

A.

Task sequencing

B.

Task predecessors

C.

Task dependencies

D.

Task prioritizing

Buy Now
Questions 20

Which of the following should receive regular communication during the planning phase of a project? (Choose two.)

Options:

A.

Collaboration site

B.

Change control board

C.

Subject matter experts

D.

Sponsor

E.

Human resources

Buy Now
Questions 21

A fire alarm goes off in the building where the project team works. Employees are instructed to leave the

premises immediately using the stairs; they are not to use elevators, and they must gather in one place outside

the building for further instructions. This is known as a:

Options:

A.

business change response

B.

change management response

C.

business continuity response

D.

risk management response

Buy Now
Questions 22

Which of the following is an example of quantitative risk management?

Options:

A.

Prioritizing risk mitigation response procedures

B.

Determining annual loss expectancy

C.

Sorting risks into three categories

D.

Assigning an owner to each identified risk

Buy Now
Questions 23

To resolve a dispute between two project team members, the project manager allows both parties to provide input on the final design. Which of the following resolution techniques is being used?

Options:

A.

Compromising

B.

Negotiating

C.

Avoiding

D.

Smoothing

Buy Now
Questions 24

An engineer is troubleshooting a malfunctioning physical deliverable and requires assistance from remote team members. Which of the following would be the BEST communication method for the engineer to use?

Options:

A.

Phone conversation

B.

Face-to-face meeting

C.

Instant messaging

D.

Video conference

Buy Now
Questions 25

Given the table below for a house construction project:

The table above is an example of which of the following project artifacts?

Options:

A.

Project plan

B.

SOW

C.

WBS

D.

RTM

E.

RBS

F.

Status report

Buy Now
Questions 26

A company recently discovered that it could save money by moving its call center to another country. The company entered into an agreement for call center services. Which of the following types of organizational change is this?

Options:

A.

Relocation

B.

Outsourcing

C.

Business process change

D.

Business demerger/split

Buy Now
Questions 27

A project manager has developed a schedule in which all tasks start as late as possible, and there is a focus on buffer utilization and work being completed in shorter periods of time. Which of the following methods is the project manager MOST likely using to develop the schedule?

Options:

A.

Critical chain

B.

Baseline

C.

Precedence diagram

D.

Arrow diagram

E.

Sprint plan

Buy Now
Questions 28

A project manager is not going to finish a project on time but cannot change the deadline or add more budget. Which of the following types of change would allow the project manager to finish the project successfully?

Options:

A.

Resources

B.

Communication

C.

Organization

D.

Quality

Buy Now
Questions 29

A project manager launched a survey for future end users of a new product under development. The sponsor received the survey results and realized the needs are different than the features currently being developed. The sponsor decided to cancel the project. Which of the following explains why the sponsor made this decision?

Options:

A.

Constraint reprioritization needed to be carried out.

B.

The cost of the changes would be more than planned.

C.

The survey was not stated in the project management plan.

D.

More than half of the project charter should be updated.

Buy Now
Questions 30

A stakeholder informs a project manager that a weekly status report has not been delivered via email, but the monthly status reports were received. Which of the following should the project manager do NEXT?

Options:

A.

Immediately send the current weekly status report

B.

Add email to the distribution list for the weekly status report

C.

Remove email from the distribution list for the monthly status report

D.

Consult the communications plan and act accordingly

Buy Now
Questions 31

Midway through a project, the building the team works in is destroyed by a hurricane. Which of the following

types of communication is BEST in this event?

Options:

A.

Incident response

B.

Business continuity response

C.

Resource change response

D.

Schedule response

Buy Now
Questions 32

A project manager chose an architect based on the architect’s presentation, but company policy states vendors must be selected based on the lowest bid. Which of the following applies to this situation?

Options:

A.

The PMO did not sign a letter of intent.

B.

The project manager neglected to conduct a communication requirements analysis.

C.

The project sponsor was not consulted in the final decision-making process.

D.

The project manager did not conform to the compliance standard.

Buy Now
Questions 33

A project has just begun, and people are not clear about the objectives.

Which of the following meeting types is needed?

Options:

A.

Stand-up

B.

Scheduling

C.

Impromptu

D.

Kickoff

Buy Now
Questions 34

A new project manager was hired to help transition projects from the waterfall style to an approach based on iterative refinement. This method has never been used by the organization and would mark a significant change in approach from previous projects. Which of the following should the project manager contact for guidance and approval for the new methodology?

Options:

A.

Project coordinator

B.

Project team

C.

Project management office

D.

Project sponsor

Buy Now
Questions 35

A project management team is discussing a potential risk event that would be devastating to the organization and prohibitively expensive to mitigate or insure against if it occurred. Which of the following is the BEST risk strategy to adopt?

Options:

A.

Accept

B.

Exploit

C.

Transfer

D.

Avoid

Buy Now
Questions 36

Ann, a customer, approaches the project manager of a portable computing device implementation project with a request to have a tablet instead of a laptop.

Which of the following steps should the project manager take NEXT?

Options:

A.

Supply Ann with the requested tablet.

B.

Have Ann submit a change request.

C.

Provide Ann with a copy of the project management plan.

D.

Inform Ann that she will receive what has been authorized.

Buy Now
Questions 37

A project manager receives an initial project assignment.

Which of the following documents is MOST likely to indicate the organizational structure for the project?

Options:

A.

Communication management plan

B.

Baseline

C.

Business case

D.

Organizational breakdown structure

Buy Now
Questions 38

Based on the information below:

AC=100

SV=80

EV=120

Which of the following is the CPI of the project?

Options:

A.

0.8

B.

0.83

C.

1.2

D.

1.25

Buy Now
Questions 39

As part of the early stages of a potential corporate acquisition, which of the following documents should the acquiring organization complete, showing regulators and investors the offered purchase price and target

closing date?

Options:

A.

Sales contract

B.

Memorandum of agreement

C.

Letter of intent

D.

Purchase order

Buy Now
Questions 40

A key stakeholder has asked project team members to work overtime on special projects. This is undermining the success of a time-sensitive project because the project team is too tired to complete the deliverables.

Which of the following steps should the project manager take to BEST resolve the issue?

Options:

A.

Ask the project sponsor for shared resources for the key stakeholder’s project.

B.

Ask the project sponsor for benched resources for the time-sensitive project.

C.

Ask the key stakeholder for low-quality resources for the time-sensitive project.

D.

Ask the project sponsor for dedicated resources for the time-sensitive project.

Buy Now
Questions 41

Which of the following indicators will assist the project manager in determining the health of the budget?

Options:

A.

SV

B.

CPI

C.

AC

D.

EV

E.

ETC

Buy Now
Questions 42

A vendor who is scheduled to arrive in two days encounters a delay and needs to reschedule the visit. The project manager needs a timely response from the project sponsor regarding the delay; however, the sponsor is in an all-day meeting and is not responding to email.

Which of the following is the BEST method to get the sponsor’s attention?

Options:

A.

Schedule an urgent meeting, overbooking one of the meetings.

B.

Delegate to the project coordinator.

C.

Text the sponsor asking for advice.

D.

Interrupt one of the meetings to speak to the sponsor.

Buy Now
Questions 43

Which of the following is the BEST indicator of project failure?

Options:

A.

Product deficiencies revealed during the monitor and control phase

B.

Project team members disagreeing on milestones

C.

Project deliverables completed behind schedule

D.

Several changes being made to the project

Buy Now
Questions 44

A project manager is informed that the project sponsor was terminated from the project effective immediately. To ensure business continuity, the project manager has been asked to assume additional tasks to complete

the project on time. Many of these tasks were performed by the former project sponsor.

Which of the following types of change does this illustrate?

Options:

A.

Internal reorganization

B.

Business demerger

C.

Outsourcing

D.

Business process change

Buy Now
Questions 45

A team shares authority between functional managers and project managers. The project manager's authority ranges from weak to strong. Which of the following organizational structures is described?

Options:

A.

Matrix

B.

Projectized

C.

Functional

D.

Hybrid

Buy Now
Questions 46

When an action is taken on a risk, which of the following is being done and which document needs to be updated?

Options:

A.

Mitigating risk, and the risk register should be updated

B.

Accepting risk, and the risk review document should be updated

C.

Avoiding risk, and the risk review document should be updated

D.

Exploiting risk, and the risk register should be updated.

Buy Now
Questions 47

A stakeholders asked for a change to the project. The project manager discussed and documented the desired change, and the proper authorities approved it.

Which of the following steps of the control was missed?

Options:

A.

Communicate the change

B.

Quality check

C.

Implementation

D.

Evaluate impact and justification

Buy Now
Questions 48

A project can be defined as:

Options:

A.

permanent and ongoing.

B.

temporary and unique.

C.

temporary and standard.

D.

permanent and unique.

Buy Now
Questions 49

During the planning phase of a construction project, the project team discovers the site is the nesting area birds, and construction could disrupt the bird’s patterns. Lobbyists would like the team to move the project down the road.

Which of the following constraint and influencer types are involved in this scenario?

Options:

A.

Environmental; resources

B.

Environmental; stakeholders

C.

Deliverables; resources

D.

Deliverables; stakeholders

Buy Now
Questions 50

A project coordinator notices there is a scheduling conflict with the weekly team meeting. The project

coordinator submits a request to hold the meeting at a different time will not negatively impact the scheduling.

Which of the following resources has the authority to authorize this change?

Options:

A.

Stakeholders

B.

Scrum master

C.

Project sponsor

D.

Project team

Buy Now
Questions 51

A project schedule lists a resource as 50% because it likely:

Options:

A.

is a shared resource.

B.

depict a resource shortage.

C.

signifies overallocation of a resource.

D.

notes underallocation of a resource.

Buy Now
Questions 52

A project sponsor has requested documentation to determine the scheduled activities for a project that is

running behind schedule. Which of the following documents should the project manager send to the sponsor to

quickly identify the project activities?

Options:

A.

RACI

B.

SWOT

C.

SOW

D.

WBS

Buy Now
Questions 53

Which of the following activity sequencing techniques uses nodes to symbolize activities and arrows to show how their dependencies are connected?

Options:

A.

Critical Path Method

B.

Arrow Diagramming Method

C.

Critical Chain Method

D.

Precedence Diagramming Method

Buy Now
Questions 54

Which of the following techniques modifies the schedule based upon resource constraints?

Options:

A.

Critical Chain Method

B.

Critical Path Method

C.

Arrow Diagramming Method

D.

Precedence Diagramming Method

Buy Now
Questions 55

Which of the following is a reason for assessing risk in a project?

Options:

A.

To identify new tasks

B.

To shorten the project timeline

C.

To avoid rework

D.

To establish a budget

Buy Now
Questions 56

A project manager at a projectized organization is finishing the objective goals for the appraisal process. Performance goals have been identified for colocated individuals working on the team. Which of the following is the appropriate communication method for relaying the goals to the team members?

Options:

A.

Email

B.

Distribution of printed media

C.

Face-to-face

D.

Video conferencing

Buy Now
Questions 57

The final project report should contain which of the following?

Options:

A.

Minutes of all the project meetings

B.

Project design documentation

C.

Detailed breakdown of the schedule

D.

Summary of the project cost

Buy Now
Questions 58

A PM notes a feature that was delivered does not appear in the latest requirement document. The PM

immediately submits a change request for remediation. Which of the following actions has the PM omitted?

Options:

A.

Identifying the risk

B.

Obtaining approval from the CCB

C.

Evaluating the impact of the risk

D.

Communicating to stakeholders

Buy Now
Questions 59

A local company is part of a hostile takeover by a multinational conglomerate. The Chief Executive Officer

(CEO) directs that all meetings be conducted via video conference to save costs and expedite communication.

This scenario is an example of:

Options:

A.

outsourcing.

B.

corporate acquisition.

C.

internal reorganization.

D.

process change.

E.

relocation.

F.

resource management.

Buy Now
Questions 60

A client has provided a list of deliverables to include in the project scope. Which of the following will allow the project team to ensure all deliverables are included in the final product while managing scope creep?

Options:

A.

Requirements traceability matrix

B.

Gantt chart

C.

SWOT analysis

D.

Project charter

Buy Now
Questions 61

As a project processes, the team appears disjointed. Meetings are not effective because the right team members are not in the discussion, and functional managers are questioning if the project manager has a true management plan.

Which of the following documents should be reviewed FIRST to uncover the issue?

Options:

A.

Communications plan

B.

Scope statement

C.

Project management plan

D.

Organizational chart

Buy Now
Questions 62

Two critical members have approached the project manager separately regarding personality conflicts. The

project manager cannot remove either from the project or separate their work activities. To help resolve the

conflict, which of the following would be BEST for the project manager to do?

Options:

A.

Send an email to the entire project team encouraging proper etiquette.

B.

Discuss the problem during the next daily status update.

C.

Perform an in-person meeting involving both parties.

D.

Schedule a mandatory team-building activity.

Buy Now
Questions 63

A project encountered a problem and reached a milestone. In which of the following documents will the stakeholders MOST likely find information on these events?

Options:

A.

Issues log

B.

Change log

C.

Status report

D.

Meeting minutes

Buy Now
Questions 64

The following tasks are required to complete an IT project that is behind schedule:

Which of the following is the critical path?

Options:

A.

3, 2, 4

B.

4, 2, 3

C.

3, 2, 1, 4

D.

4, 1, 2, 3

Buy Now
Questions 65

Which of the following analyses should a project manager use to determine problem areas for corrective action planning? (Select two.)

Options:

A.

Planned value

B.

Schedule variance

C.

Acceptable variance

D.

Cost variance

E.

Earned value

Buy Now
Questions 66

An organization has determined that all projects must use a remote dashboard to allow portfolio management. Which of the following would enforce this directive?

Options:

A.

Project management office

B.

Project sponsor

C.

Project manager

D.

Project coordinator

Buy Now
Questions 67

Which of the following is the MOST important component against which the project manager can analyze

project performance?

Options:

A.

Burn rate

B.

Project baselines

C.

KPIs

D.

Budget

Buy Now
Questions 68

A company is in the process of combining the human resources and marketing departments. Which of the following describes this change?

Options:

A.

Business process change

B.

Business merger

C.

Internal reorganization

D.

Interorganizational change

Buy Now
Questions 69

Which of the following describes KPIs?

Options:

A.

Analyses of organizational strengths and weaknesses

B.

Graphical representations of process flow

C.

Elements against which performance can be measured

D.

Collaboration platform tools

Buy Now
Questions 70

A vendor advises the project manager that a key component of the project is no longer available and recommends a higher-cost replacement. To have this change approved, the project manager submits a change request that contains which of the following?

Options:

A.

Description, cost difference of the replacement, and WBS

B.

Description, justification, and cost

C.

Cost difference of the replacement, justification, and communications plan

D.

Description, quality impact, and cost

Buy Now
Questions 71

Ann, one of the affected stakeholders, feels that the project team has not been giving periodic stakeholder updates and that her input has not been taken into account.

Which of the following should the project manager do to ensure stakeholder expectations are met?

Options:

A.

Ensure that Ann is involved during the testing phase of the project so she can call out functional gaps.

B.

Organize a walkthrough of the solution and ensure face-to-face updates occur every two weeks.

C.

Escalate the issue to the project steering committee that Ann is criticizing the project quality.

D.

Organize a requirements workshop to capture any gaps.

Buy Now
Questions 72

Which of the following represents additional unauthorized requirements from the client?

Options:

A.

Scope creep

B.

Changing scope baseline

C.

Change request

D.

Gold plating

Buy Now
Questions 73

A project manager is determining a project’s critical path to report the projected completion date to stakeholders.

Which of the following information will be required? (Select two.)

Options:

A.

Costs

B.

Dependencies

C.

Schedules

D.

Durations

E.

Holidays

F.

Milestones

Buy Now
Questions 74

Which of the following captures unforeseen activities throughout the project that need attention and resolution?

Options:

A.

Gantt chart

B.

Action items

C.

Project schedule

D.

Meeting minutes

Buy Now
Questions 75

The project's network map has a loop with multiple project outcomes.

This is the result of which of the following scheduling tools?

Options:

A.

Establishing project schedule baselines

B.

Critical Path Analysis

C.

Critical Chain Method

D.

Graphical evaluation and review technique

Buy Now
Questions 76

Which of the following resources outlines consequences of non-performance?

Options:

A.

Project sponsor

B.

Project team

C.

Customer

D.

Project management office

Buy Now
Questions 77

Which of the following project phases would MOST likely include a creating transition plan?

Options:

A.

Closing

B.

Initiation

C.

Execution

D.

Planning

Buy Now
Questions 78

In which of the following situations is a project manager MOST likely to use a process diagram?

Options:

A.

When describing a new business idea for the team to review

B.

When describing a new business workflow for the team to implement

C.

When describing a new business project for the team to implement

D.

When describing a new business acquisition for the team to review

Buy Now
Questions 79

Which of the following documents serves the primary purpose of requesting details about a vendor’s capabilities?

Options:

A.

RFP

B.

RFI

C.

RFQ

D.

NDA

Buy Now
Questions 80

A project manager has been assigned a complex project and does not know all the activities required to complete it.

Which of the following if the BEST approach to determine the work packages for the WBS?

Options:

A.

Brainstorming

B.

Analogous

C.

Bottom-up

D.

Forward pass

Buy Now
Questions 81

Which of the following tools would a project manager use to determine the root cause of an issue?

Options:

A.

Pareto Chart

B.

Ishikawa Diagram

C.

Histogram

D.

Monte Carlo Analysis

Buy Now
Questions 82

A project manager who is part of a global team wants to have a team building meeting and decides to hold a video conference.

Which of the following is MOST likely to be the main challenge the influences this decision?

Options:

A.

Geographical factors

B.

Language barriers

C.

Cultural differences

D.

Technology factors

Buy Now
Questions 83

The key stakeholders have reported the project pace as being slow. The project sponsor would like to cancel the project if it cannot be completed before the end of the year. The project is scheduled to be completed three months after the requested date.

To alter the pace of the project, which of the following should the project manager do FIRST?

Options:

A.

Give approval for the change requested by the project sponsor.

B.

Deny the request from the project sponsor.

C.

Document the change request from the project sponsor.

D.

Ask the project sponsor to change the request.

Buy Now
Questions 84

Which of the following are characteristics of a project? (Choose two.)

Options:

A.

A project is a temporary endeavor.

B.

A project provides a unique product, service, or result.

C.

A project is an ongoing endeavor.

D.

A project involves scheduled maintenance.

E.

A project includes life-cycle cost management.

Buy Now
Questions 85

During a project, the project manager discovers there is insufficient time allotted for quality control. The project manager prepared to submit a revised schedule to the CCB.

Given the attached chart, which of the following is the critical path if one day is added to each task for quality control?

Options:

A.

12 days

B.

16 days

C.

17 days

D.

22 days

Buy Now
Questions 86

A project manager is providing the lessons learned for a project that ran over budget and produced poor quality deliverables. Which of the following should the project manager include as part of the lessons learned?

Options:

A.

Risk register

B.

Post-mortem analysis

C.

Issue log

D.

Procurement report

Buy Now
Questions 87

A project has fallen behind schedule. Upon investigation, the project manager determines that team members have implemented requirements relayed via impromptu hallway meetings with the client.

Which of the following should the project manager do to resolve this issue?

Options:

A.

Update the scope management plan.

B.

Modify the project baselines.

C.

Implement change control management.

D.

Inform the stakeholders of the issue.

Buy Now
Questions 88

A project manager is trying to ensure the quality of the design and reduce the number of potential defects. The project manager would like to use the fishbone diagram to perform this analysis.

This type of modeling relies on:

Options:

A.

Prioritizing the specific event.

B.

Variance in the process over time.

C.

Causes of a specific event.

D.

Determining the number of events.

Buy Now
Questions 89

A risk with minor impact has been realized. There is no change to the triple constraint. The PM should notify the:

Options:

A.

internal project team.

B.

key stakeholders.

C.

affected team members.

D.

full project team.

Buy Now
Questions 90

A department manager asks a project manager about the status of a project that has only a few employees from the department assigned to it. Which of the following were MOST likely missed during project planning?

Options:

A.

Issue log and process diagram

B.

Resource analysis and Gantt chart

C.

Stakeholder analysis and communication plan

D.

Scatter chart and scope analysis

Buy Now
Questions 91

Two team members are arguing over two different approaches to complete a task. The project manager listens to both sides, determines neither approach will work, and directs the team members to use a third option.

This type of conflict resolution is known as:

Options:

A.

forcing.

B.

avoiding.

C.

smoothing.

D.

compromising.

Buy Now
Questions 92

Which of the following measurements would give the project manager the BEST estimate of the total cost of an active project?

Options:

A.

EAC

B.

BAC

C.

TCPI

D.

ETC

Buy Now
Questions 93

A project manager is justifying a required change with the associated impact on the project.

Which of the following is the NEXT step?

Options:

A.

Implementation

B.

Approval

C.

Validation

D.

Auditing

Buy Now
Questions 94

The chairperson of the board is visiting from another country and wishes to meet the project team members. The next project team meeting will be held next week, but the chairperson is leaving before the meeting. Which of the following actions should the project manager take?

Options:

A.

Schedule a conference call for the team meeting and invite the chairperson.

B.

Arrange an impromptu team meeting with the chairperson.

C.

Email the chairperson the meeting minutes from the scheduled meeting

D.

Invite the chairperson to the next project team meeting

Buy Now
Questions 95

A project manager is successfully adhering to an eight-week project schedule through week three. A change in the marketplace will require the project manager to deliver the product one week early.

Given the project schedule above, which of the following aspects are missing for the project manager to plan and execute an accelerated schedule? (Choose two).

Options:

A.

Cost

B.

Predecessors

C.

Lag

D.

Durations

E.

Resource loading

F.

Subtasks

G.

Float

Buy Now
Questions 96

A business has implemented a new online performance management tool that allows functional and project managers to rate employees online.

This action is known as which of the following?

Options:

A.

Business process change

B.

Organizational change

C.

Internal reorganization

D.

Business continuity planning

Buy Now
Questions 97

A vendor has accepted a proposed project from a customer.

Which of the following is MOST likely to be the first document created by the project manager?

Options:

A.

Project charter

B.

Project management plan

C.

Project statement of work

D.

Project schedule

Buy Now
Questions 98

Due to a new government regulation, a project change is required. The project manager evaluates the change and realizes a representative from the legal department will need to approve the change as well.

The project manager should:

Options:

A.

follow the change process flow and notify the legal department after the change is implemented.

B.

extend a formal invitation to the legal department representative to join the CCB.

C.

hold a separate meeting with the legal department representative and ask for approval.

D.

notify the legal department representative in the event of an upcoming audit.

Buy Now
Questions 99

A project team has finished creating a WBS and started developing a schedule. The team should FIRST determine the:

Options:

A.

durations.

B.

tasks.

C.

critical path.

D.

resources.

Buy Now
Questions 100

A project manager has been asked to prepare and present a review of the execution phase. Which of the following is the BEST audience for this review?

Options:

A.

Vendors

B.

Key stakeholders

C.

Resources

D.

Project team

E.

Business analysts

Buy Now
Questions 101

Team members have reported poor sound quality during critical, time-sensitive conference calls. Which of the following may be a more effective means of communication?

Options:

A.

One-on-one meetings

B.

Project wiki

C.

Text messages

D.

Social media

Buy Now
Questions 102

During the execution phase of a project, a project task has run longer than anticipated.

Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete?

Options:

A.

12 days

B.

14 days

C.

16 days

D.

19 days

Buy Now
Questions 103

A part that is needed to complete Task 3 has been backordered and will arrive three days later than scheduled. Task 3 must be complete for Task 4 to start. There is one day of float for the two tasks. Which of the following represents the number of days the project schedule will be delayed?

Options:

A.

Zero

B.

One

C.

Two

D.

Three

Buy Now
Questions 104

The project team is distributed throughout a single country. The scrum master has decided to hold remote "stand-ups" on a daily basis. Which of the following would be the MOST effective means to do this?

Options:

A.

Instant messaging

B.

Video conference

C.

Phone call

D.

Collaboration website

Buy Now
Questions 105

Assuming an iterative approach, which of the following will be conducted at the end of each iteration?

Options:

A.

SCRUM retrospective

B.

Kickoff meeting

C.

Budget baseline

D.

Risk review

Buy Now
Questions 106

A company is hired to perform some of another organization’s work. Which of the following types of organizational change is described?

Options:

A.

Outsourcing

B.

Business process change

C.

Shared resources

D.

Split

Buy Now
Questions 107

Which of the following would indicate a project manager is working in a matrix-based organization?

Options:

A.

The project manager has full authority over resources and the project.

B.

The project manager has no authority over the project resources and limited-to-no authority over the project.

C.

Resources align to the project, report to the project manager, and have no functional home at the end of the project.

D.

Resources report to business area functional managers and return to the functional area at the end of the project.

Buy Now
Questions 108

An authorized change to a construction project was implemented. During the modification, the team identified a defect in which the change caused the building power output to be outside the KPPs.

Which of the following actions should the project manager take?

Options:

A.

Submit a new change request.

B.

Initiate the regression plan.

C.

Add remediation to the schedule.

D.

Accept the new power output.

Buy Now
Questions 109

A project manager needs to track the actual and estimated start and finish dates of all WBS work packages.

Which of the following is a necessary step to record the actual durations?

Options:

A.

Establish each WBS work package resource.

B.

Establish and set the baseline.

C.

Establish and set the quality gates.

D.

Establish the tollgates.

Buy Now
Questions 110

Two team members completely disagree on how to complete a specific task. The project manager observes the conflict but takes no immediate action.

Which of the following techniques is the project manager using?

Options:

A.

Compromising

B.

Smoothing

C.

Withdrawing

D.

Accepting

Buy Now
Questions 111

A project manager was directed to complete a project sooner than previously planned. Which of the following is the MOST cost-effective step to take to ensure the project’s success?

Options:

A.

Reduce the scope

B.

Increase the budget

C.

Decrease staff

D.

Update the WBS

Buy Now
Questions 112

A project team is mainly based in a metropolitan area. The team also has members in a remote area, where Internet access is limited and unstable.

Which of the following factors will MOST likely influence the communication methods used in the project?

Options:

A.

Personal preferences

B.

Technological factors

C.

Language barriers

D.

Cultural differences

Buy Now
Questions 113

A project manager has contracted a third-party vendor to achieve milestones. Which of the following risk strategies is the project manager applying?

Options:

A.

Transfer

B.

Accept

C.

Avoid

D.

Mitigate

Buy Now
Questions 114

Which of the following documents should be used to provide high-level reporting to key stakeholders?

Options:

A.

Dashboard

B.

Communication plan

C.

Statement of work

D.

Project charter

Buy Now
Questions 115

Which of the following describes risk mitigation?

Options:

A.

The transfer of the risk to another entity or project inside or outside the organization, along with associated costs.

B.

The understanding of the risk with a detailed explanation of how the project intends to address the potential for occurrence.

C.

The quantification of the risk in terms of how much the risk could potentially cost the project or parent organization.

D.

The weighting or prioritization of the risk against all other identified risks within this project or others associated with it.

Buy Now
Questions 116

Several team members report that meeting objectives are not being met.

Which of the following documents would a project manager create to make team meetings more effective? (Choose two.)

Options:

A.

Create an SOW prior to each meeting and adhere to it.

B.

Create a meeting agenda prior to each meeting and adhere to it.

C.

Create a lessons learned list prior to each meeting and adhere to it.

D.

Create a project charter prior to each meeting and adhere to it.

E.

Create an action item list during the meeting and adhere to it.

F.

Create a corrective action plan prior to each meeting and adhere to it.

G.

Create a WBS prior to each meeting and adhere to it.

Buy Now
Questions 117

A project’s key stakeholders have requested significant changes that will affect the scope. To adjust the project scope, which of the following need to be changed? (Choose two.)

Options:

A.

Cost performance parameter

B.

Project schedule

C.

KPI

D.

Corrective action plan

E.

WBS

Buy Now
Questions 118

The project manager has had a large number of change requests approved by the project steering committee, but has been given no extra time to deliver the project.

Which of the following schedule compression techniques should be used by the project manager?

Options:

A.

Rescheduling

B.

Crashing

C.

Rebaselining

D.

Control scope

Buy Now
Questions 119

Which of the following job roles is primarily tasked with communicating the project timeline changes?

Options:

A.

Project scheduler

B.

Project manager

C.

Project sponsor

D.

Project coordinator

Buy Now
Exam Code: PK0-004
Exam Name: CompTIA Project +
Last Update: Nov 21, 2024
Questions: 796

PDF + Testing Engine

$140

Testing Engine

$105

PDF (Q&A)

$90