Cleveland Insurance (Cleveland) offers a range of insurance services. The main software used in the call centre is a customer relationship management (CRM) system. Cleveland perceived an urgent need to replace the existing CRM system to deal with the increasing number of customers and services.
Urgent Digital Ltd (Digital) is one of the bidders of Cleveland’s ITT for designing, building and managing the new CRM system. Its bid team is led by Hank Irvine, its technical director. Hank realises that winning the Cleveland contract (valued at approximately £50M) will enhance his career. During discussions with Cleveland, Hank offers certain assurances regarding timescales for the project. He has not carried out any investigations into the viability of the timescales. Hank has little idea whether the timescales can be met.
Cleveland decides that Digital’s bid meets with its requirements, especially given the assurances in timescale offered by Hank, and decides to proceed with it, subject to a formal contract. Eventually, a formal contract is signed by both parties. The initial assurances given by Hank about the timing of the project are never going to be achieved and are at best grossly exaggerated.
Cleveland brought the case to the court and sought rescission of contract with Digital. Is Cleveland’s claim appropriate in this case?
Which of the following best defines an ‘express’ term in general contract arrangements?
Which of the following is the contract provision that relieves the parties from performing their contractual obligations when certain circumstances like natural disasters, terrorist attacks, etc arise?
Under a framework agreement, which of the following are supplier selection mechanisms? Select TWO that apply:
Which of the following are true statements about RFQ process? Select TWO that apply.
Which of the following should be done by procurement professionals right after obtaining a pre-written specification for a critical item so that the added value will be the greatest?
Standard terms and conditions should become the governing terms for which group of items?
Which of the following are examples of incentives which can be embedded in contract terms? Select THREE that apply
Which of the following are likely to be advantages of using invitation to tender? Select TWO that apply:
SFO procurement manager sent a request for quotation to Vogon International in which he determined the contract terms and specification. In SFO's standard terms and conditions, it is stated that 'Goods shall be delivered and Services performed by the applicable Delivery Date. Supplier must notify Buyer 3 days prior to the Delivery Date if Supplier is likely to be unable to meet a Delivery Date.'
Vogon replied with a quotation without any amendment to SFO's terms & conditions. The SFO procurement manager found the prices were reasonable and submitted to senior management. Senior management team accepted that quotation and sent a notification to Vogon. On the Delivery Date, Vogon said they had no capacity to supply the product as the quotation due to a workers' strike. Did Vogon breach any agreement with SFO?
Which of the following should be used in a contract for window cleaning during the next three months?
EAC Facilities Management is planning for a new construction project in the suburban area. They decide to use NEC or FIDIC model form of contract for this project. Is this a right course of action?
When a contract has been agreed on the basis of a fraudulent misrepresentation, which of the following remedies are available?
A supermarket purchases a new batch of house cleaner from new supplier. The supermarket is concerned about possible damage that the house cleaner may cause to consumers' floor. What type of insurance must they cover?
Company A based in Canada signed a commercial contract with Company B in Egypt. Both countries are Contracting States to Vienna Convention on Contracts for the International Sale of Goods. The contract states that "The validity, interpretation, construction and performance of this Agreement shall be governed by the laws of Canada". Which of the following set of rules will be applied if dispute between contracting parties occurs?
If service level agreement is used as a schedule that makes up the contract, it will be most likely to be a part of...?
Which of the following is the procedure that makes no further competition under a framework agreement?
Which of the following KPIs is qualitative?
1. Openness and co-operation of supplier
2. Responsiveness of supplier
3. Customer satisfactory ratings
4. Cost management
5. OTIF deliveries
Which of the following is likely to reduce risks of different rules regarding when offers and acceptance become effective between legal systems?
Which of the following is the reason why liquidated damage clauses are embedded into a contract?