Given the following information: Pessimistic estimate is 30 days Most Likely estimate is 15 days Optimistic estimate is 10 days Which of the following is the expected duration for this scheduled activity?
A customer requests that the products quality be reduced to control its cost. Which of the following actions should the project manager take FIRST?
During which of the following process groups is the availability of required resources for the project determined?
A project manager learns that a team member has falsified work experience, and does not have the knowledge required to complete the task. Which of the following should the project manager do?
Which of the following are characteristics of a projects critical path? (Select Two).
A project sponsor has requested that the training be delivered in parallel to a project's implementation in order to ensure the project is delivered on schedule. If accepted, this request is an example of:
Which of the following documents should be used to present the length of identified tasks?
A project has been delayed due to an ongoing labor dispute. The project sponsor asks the project manager to transfer the risk to complete the project on time. Which of the following is a method of transferring the risk?
Several team members have criticized the project manager for requesting that they work overtime in order to complete a project on time. Which of the following steps should the project manager take to resolve the conflict?
The project manager has outsourced a call center to a company in another region. The project manager receives reports that customers sometimes cannot hear the instructions given by call center employees. Which of the following is the MOST likely cause of the reports?
Which of the following activities occur during a project kick-off meeting? (Select Three).
The project cost performance index is 1.2 and the project manager has spent $71,248 dollars to date. The project is currently 50 percent complete. Which of the following is the earned value (EV)?
Two employees will not work on the same project together. The project manager tells the employees to talk to their supervisors because the supervisors recommended they work together. This is an example of which of the following conflict resolution styles?
Changing the project schedule to prevent a known risk is an example of which of the following risk responses?
A project manager has to complete an asset inventory project for a large corporation. Several departments have refused to allow access to the equipment to complete the project. The project manager should update which of the following?
The project has been terminated prematurely by the organization. Which of the following will the project manager need to complete?
Refer to the attached Exhibit.
Which of the following is the duration of the critical path in the diagram?
A project manager added some experienced team members to work on certain project activities in conjunction with inexperienced team members because the project is behind schedule. Which of the following BEST describes the technique the project manager is using?
A project manager has been informed that a project deliverable must be completed by September 1st. Which of the following BEST describes this situation?
Which of the following is the BEST point for a project manager to join a project?
The change control board has approved a change to the scope of a project. Which of the following actions should the project manager take NEXT?
In a highway project 5 miles (8 kilometers) out of the total 15 miles (24 kilometers) have been completed. The BAC is $900,000. Which of the following represents the EV of this project?
Which of the following would MOST likely be reviewed during a project kick-off meeting?
Monitoring and controlling project work is a control process function that spans from:
A project manager seeks to implement a change control system. Which of the following elements are essential for this system to be effective? (Select Three).
During the execution phase of a project, a change request has been approved to add activities to the critical path without altering the schedule. Which of the following techniques will the project manager MOST likely use to deliver the project on time?
Which of the following are characteristics of an approved project charter? (Select Two).
Which of the following risk response strategies involves shifting the negative impact of a threat, along with ownership of the response, to a third party?
Which of the following steps should a project manager take to ensure the quality of project deliverables for a customer? (Select Two).
To ensure that project status meetings are effective and productive, the project manager should:
During which of the following process groups is the availability of required resources for the project determined?
A project manager is conducting a root cause analysis with the project team. Which of the following tools should be utilized?
A product has been sent to an outside vendor for testing. During their testing it was determined that the product is not meeting the quality standards. The project manager scheduled a meeting to review their findings. Which of the following BEST describes this situation?
A project manager has failed to obtain the necessary permits from the local building commission. The project has been stopped because of a failure to understand the importance of:
Which of the following cost estimating techniques uses previous, similar projects as a basis of estimating costs for the current project?
Which of the following is the BEST way for a project manager to conduct a lessons learned session?
A major change has been approved by the change control board and it now needs to be scheduled for implementation. Which of the following is the BEST method of implementing the change?
Which of the following would a project manager organize and implement in order to provide decision oversight to scope changes?
After a change control board meeting, which of the following actions should the project manager do NEXT?
A project manager has just completed the work breakdown structure (WBS) with the project team. Which of the following would be used during activity sequencing?
Which of the following is described when a company requires version control of project documents?
The initial quality measurements used to determine if a variance has occurred is known as the:
The project team has completed phase testing. After testing, a subject matter expert (SME) notices that a component was skipped.
Which of the following should the project manager do?
Several project tasks cannot be completed because local resources are not available. The project manager has to outsource the work to find qualified resources. Which of the following risk responses is the project manager using?
An adjustment to the project has been approved and funding granted, but the project manager feels the modification is out of scope.
Which of the following should the project manager do?
To ensure the quality of implemented project change requests, which of the following will need to occur? (Select Two).
The change control board has requested that a project manager evaluate the impact of a major change request that will affect the timetable of several work-packages. Which of the following actions should the project manager undertake FIRST?
Which of the following is the BEST tool to determine how the frequency of an individual cause contributes towards the total result?