H12-425_V2.0 HCIP-Data Center Facility Deployment V2.0 Questions and Answers

Questions 4

Which of the following statements is false about the ECM of the UPS5000-E?

Options:

A.

As a control interface for the entire system, the ECM communicates with each module and provides a bus for communication between the dry contact card and the system control card.

B.

The ECM controls the bypass module to work properly, if one ECM is faulty, the UPS can still work in normal mode but cannot be manually switched to bypass mode.

C.

The ECM ensures equalized output currents between modules so that load power is equally shared.

D.

The ECM provides three types of CAN communication: monitoring CAN communication, intra-rack parallel CAN communication, and inter-rack parallel CAN communication.

Buy Now
Questions 5

In the FusionModule800 grounding solution, each cabinet is connected to the ground bar of the data center.

Options:

A.

True

B.

False

Buy Now
Questions 6

Which of the following position is recommended for installing the smart ETH gateway?

Options:

A.

Control skylight

B.

Inside a network cabinet

C.

At the inner side of a door header

D.

At the side of a cable trough

Buy Now
Questions 7

Which of the following PH values meets the water quality requirements of NetCol8000-E220?

Options:

A.

3

B.

5

C.

7

D.

9

Buy Now
Questions 8

In large-scale data centers such as financial securities centers and telecom hubs. UPSs with a capacity of 200 kVA or higher are usually used. For UPS5000-E-200k, 12 V battery packs are usually configured as backup power instead of battery racks.

Options:

A.

True

B.

False

Buy Now
Questions 9

When installing a water-cooled module, what is the minimum distance between the module and the wall?

Options:

A.

300 mm

B.

400 mm

C.

500 mm

D.

600 mm

Buy Now
Questions 10

A data center is at the Tier IV level and uses Huawei FusionModule2000 smart module. In this smart module, the PDU8000 integrated PDF cannot be used to supply power to IT loads and precision air conditioners at the same time because isolation requirements are not met.

Options:

A.

True

B.

False

Buy Now
Questions 11

For FusionModule2000, depending on different layout position, batteries can be deployed in the smart module or out of the smart module.

Options:

A.

True

B.

False

Buy Now
Questions 12

Which of the following statements about ECC800-Pro features are true?

Options:

A.

Supports multiple unlocking method including access card, password, fingerprint, and facial recognition.

B.

Supports the connection of eight access control devices and four cameras for a single smart module.

C.

Supports the cascadingof a maximum of 4 ECC800-Pros.

D.

Supports wizard-based deployment and commissioning.

Buy Now
Questions 13

On the ECC800-Pro WebUI, which of the following is the first-level menu of the NMS Application?

Options:

A.

System Settings

B.

Maintenance

C.

Home

D.

Monitoring

Buy Now
Questions 14

When the outdoor unit of a Huawei air-cooled air conditioner is installed horizontally, what is the minimum distance between the outdoor unit and the wall or obstacle?

Options:

A.

100 mm

B.

200 mm

C.

300 mm

D.

600 mm

Buy Now
Questions 15

In the FusionModule2000, if a device port complies with the Modbus RTU protocol, which device is used to connect to smart ETH gateway?

Options:

A.

ETH converter

B.

Access actuator

C.

Skylight actuator

D.

AC actuator

Buy Now
Questions 16

Which of the following methods can be used to open the access control for the FusionModule2000 smart module?

Options:

A.

Fingerprint

B.

Card reader

C.

Password

D.

Facial recognition

Buy Now
Exam Code: H12-425_V2.0
Exam Name: HCIP-Data Center Facility Deployment V2.0
Last Update: Nov 23, 2024