Which of the following is not a Product Owner responsibility?

Options:

A.

Maintaining the Product Backlog with current information

B.

Working with stakeholders to determine and detail product features

C.

Assigning tasks to team members

D.

Prioritizing the Product Backlog

Buy Now
Questions 5

The most encouraged time of day to hold a Scrum Daily Meeting is:

Options:

A.

A beginning of the day

B.

Immediately after lunch

C.

4:30 PM

D.

7:00 PM

Buy Now
Questions 6

Which of the following is reflected in a Sprint Burn down Chart?

Options:

A.

Team Members Name

B.

Number of Product Backlog Items Completed

C.

Number of Tasks Remaining

D.

Work Hours Remaining

Buy Now
Questions 7

Which of the following statements best explains what the term Sprint means in Scrum?

Options:

A.

A sprint is a specific amount of days for a team to test and resolve any issues prior to product release or shipment

B.

A sprint is a specific amount of days for a team to work at a sustainable pace to finish select work.

C.

A sprint is an agreed upon period of time for team members to select individual items from the product backlog to work on.

D.

A sprint is a specific amount of days for a team to work as many hours as needed to finish assigned work

Buy Now
Questions 8

Which two of the following are reasons for considering Agile? (Choose two.)

Options:

A.

Evaluating Data for Agile Marketing

B.

Focus on Customers

C.

Focus on Employees

D.

Evaluating Data based on Current trends

Buy Now
Questions 9

What is the major difference between Product Backlog and Sprint Backlog?

Options:

A.

The Product Backlog is equal to the Sprint Backlog

B.

The Product Backlog is a subset of the Sprint Backlog

C.

The Sprint Backlog is a subset of the Product Backlog

D.

The Sprint Backlog is owned by the Product Owner

Buy Now
Questions 10

How should items in the Product Backlog be ordered?

Options:

A.

Alphabetically first and then by list order in the Product Backlog

B.

Grouped by business features first and then chronologically by date of original business request

C.

Prioritized by business importance first. The items that result in biggest ROI, must be priorized first;

D.

Chronologically by date of original business request first and then by list order in the Product Backlog

Buy Now
Questions 11

Which objectives are covered as part of Sprint Planning?

Options:

A.

Understanding what functionality the Product Owner desires within the next Sprint and figuring out how to do it.

B.

Updating the scope of the release with all Sprints, end dates, and costs

C.

Reviewing current functionality that binds the software solution

D.

Recalculating empirical velocity, adjusting team capacity accordingly, and projecting end dates

Buy Now
Questions 12

The Development Team should have all the skills needed to:

Options:

A.

Complete the project as estimated when the date and cost are committed to the Product Owner.

B.

Turn the Product Backlog it selects into an increment of potentially shippable product functionality.

C.

Do all of the development work, but not the types of testing that require specialized testing, tools, and environments.

Buy Now
Questions 13

It's come to your attention that some team members feel that Carlos is a negative influence on the team. You can certainly understand why — he believes that everything is doomed. What should you do?

Options:

A.

Remove Carlos from the team.

B.

Use Carlos as an asset, particularly during risk identification

C.

Ignore him and hope it goes away

D.

Escalate the issue with the higher authorities

Buy Now
Questions 14

How many hours per day should a person on a Scrum team work?

Options:

A.

A sustainable pace, usually from 7-8 hours per day.

B.

An "ideal day" measuring only when he or she is productive.

C.

However many hours are needed to get the work done.

D.

14 hours.

Buy Now
Questions 15

Which two of the following are Seven Waste’s of Software Development? (Choose two.)

Options:

A.

Extra features

B.

Task Switching

C.

Path Analysis

D.

Process Integration

E.

Buy Now
Questions 16

Is Scrum Master a "management" position?

Options:

A.

Yes

B.

No

Buy Now
Questions 17

The individual, detailed pieces of work that are needed to convert a product backlog item into a working software component or solution are called:

Options:

A.

User Stories

B.

Use cases

C.

Line items

D.

Tasks

Buy Now
Exam Code: CSM-001
Exam Name: Certified Scrum Master (CSM)
Last Update: Dec 21, 2024
Questions: 119

PDF + Testing Engine

$134.99

Testing Engine

$99.99

PDF (Q&A)

$84.99